SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2009 Supreme(SC) 809

SUPREME COURT OF INDIA
Lokeshwar Singh Panta, R V Raveendran
STATE OF RAJASTHAN AND ANR.
v.
FERRO CONCRETE CONSTRUCTION PVT. LTD.
Civil Appeal No. 2764 of 2009
Decided on : April 22, 2009.

Advocates appeared:
Vijay Hansaria, Jatinder Kumar Bhatia, B. N. Jha, Sneh Kalita - Appellants.
Dushyant Dave, Ravindra Shrivastava, Kishore Shrivastava, Kunal Verma, Rajul Shrivastava, Aniruddh Rajput, Manish Chaudhary, C. G. Solshe - Respondent.

Headnote:

Arbitration Act, 1940 - Section 20 read with Section 8 - Common Terms of Reference - Arbitration agreement - Appointment of arbitrator - Employer filed its reply to the claim statement, and also made five counter-claims aggregating before the arbitrator - Held, Rejection of Counter-Claim No. 5 is consequential - As noticed above, the court does not sit in appeal over the award of the arbitrator and cannot re-appreciate the evidence to arrive at a different conclusion - Award on these items does not attract any of the grounds on which award could be set aside - Therefore, rejection of these claims is also not open to interference - Appeals partly allowed

Judgement Key Points

Key Points: - The arbitrator's jurisdiction and validity of appointment when the appointing authority did not refer disputes explicitly (!) - Whether certain awards (notably Claim No. 1 and Claim No. 37A) were liable to be set aside for legal misconduct or error apparent on the face of the award, including misapplication of contract terms and improper reliance on mortgage/status of mobilization advance (!) (!) (!) (!) (!) - The appropriate rate and period of interest on awards under the old Arbitration Act (1940) and the Interest Act, 1978, including pre-reference, pendente lite, and future interest, and the legality of awarding 18% interest in such cases, with the Court reducing to 9% for pre-reference, pendente lite, and future periods (!) (!) (!)

Question 1?

Question 2?

Question 3?


Judgment

R. V. Raveendran, J.

Leave granted. Heard learned counsel.

The appellants ('the employer') invited tenders for the manufacture, laying, testing and commissioning of water pipeline of a length of 37.41 km. under a water supply scheme in Ajmer District. Tenders were received from various tenderers including respondent (hereinafter referred to as 'the contractor'). As different tenderers had stipulated different terms and conditions, the tenderers were invited for discussions, and Common Terms of Reference (for short 'CTR') were formulated on 22.02.1988 and the original tender conditions stood modified to the extent of the alterations in the CTR.

Thereafter, the offer of the respondent was accepted and a work order dated 23.08.1988 was issued to him stipulating the period for completing the contract as two years from that date. There was an amendment to the work order on 08.11.1988. The employer and the contractor entered into an agreement dated 11.01.1989 enumerating and stipulating the documents which will form part of the contract and the modifications agreed in regard to certain terms. The value of the work as per the work order was Rs. 9,91,94,602.50. Ten per cent of the value of work (Rs. 99.19 lakhs) which was agreed to be released as mobilization advance, was released to the contractor between 25.01.1989 and 05.05.1989. The contractor created an equitable mortgage over its plant by depositing its title deeds thereto as security for the mobilization advance. By letter dated 15.12.1990, the contractor confirmed that the original title deeds will remain in deposit with the employer till the entire amount of advance was repaid in full with interest.

The contract (Clause 23 of General Conditions of Contract) provided for settlement of disputes by arbitration. By letter dated 18.06.1990 respondent invoked the provision for arbitration and sought appointment of an arbitrator to decide its claims aggregating to Rs. 2,01,66,547, arising on account of certain alleged omissions and commissions of the employer. Another dispute was raised in respect of the rate payable for work done subsequent to the due date of completion (22.08.1990). On 22.08.1990, the contractor stopped the work. By that date it had manufactured 15.26 km. of pipes and had laid 11.6 km. out of them and tested only 1.4 km. of pipeline as against the total contracted quantity of 37.41 km. On 13.09.1990, the employer notified the contractor that if he did not resume the work, the balance of the work would be got executed through an alternative agency in terms of the contract, by treating the contract as having been abandoned on 22.08.1990, and recover the excess cost from the contractor.

The respondent - contractor sent a reply dated 03.11.1990 stating its efforts to complete the work were rendered futile on account of the delays and breaches on the part of the employer; and it was necessary to enter into a fresh agreement as the tender was not accepted in the manner in which it ought to have been accepted. The contractor did not resume the work. The contractor's stand was that in the absence of an extension of time for completion by mutual consent before the stipulated date for completion, it was not liable to continue the work on the tendered rates. The employer on 30.03.1991 made a final demand calling upon the contractor to state whether it was ready to re-start and complete the remaining work and if so to submit a revised time schedule for such completion. As the contractor did not resume the work, the employer initiated steps to get the balance work executed through an alternative agency. In the meanwhile, the contractor filed a suit against the appellant in the District Court, Ajmer and obtained a temporary injunction restraining the employer from imposing liquidated damages.

The contractor made an application to the District Court, Ajmer, under Section 20 read with Section 8 of the Arbitration Act, 1940 ('the Act' for short) for filing the arbitration

































































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top