IN THE SUPREME COURT OF INDIA
Surinder Singh Nijjar, J.
Bipromasz Bipron Trading SA
Vs.
Bharat Electronics Limited (BEL)
Arbitration Petition No. 19 of 2011
Decided On : 08.05.2012
Arbitration and Conciliation Act, 1996–Section 11(6)–Appointment of Arbitrator–Apex Court would have power to appoint a person other than named Arbitrator where named Arbitrator is not likely to be impartial–It would not be unreasonable for petitioner to entertain plea that Arbitrator appointed by respondent would not be impartial–Retired Chief Justice of Madras High Court appointed as sole Arbitrator. (Paras 40, 41 and 43)
(2003)5 SCC 413; (2010) 9 SCC 157–Relied.
1992 Supp. (1) SCC 471–Distinguished.
ORDER
Surinder Singh Nijjar, J.
1. In this petition, under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as "the Arbitration Act") read with paragraphs 2 and 3 of the appointment of the Arbitrators by the Chief Justice of India Scheme, 1996, the Petitioner seeks reference of the disputes to an independent and impartial sole Arbitrator. In terms of the arbitration agreement, the Petitioner has issued the necessary notice and the Respondent has not agreed for such appointment of an independent arbitrator.
2. It appears that the Respondent is not opposing the petition on the ground that the disputes cannot be referred to arbitration. The only objection raised by the Respondent is that the disputes have to be referred to the Chairman and Managing Director of the Respondent or his nominee, in terms of the arbitration Clause 10 of General Terms and Conditions of Purchase Order (Foreign). The aforesaid arbitration clause reads as under:
Arbitration - All disputes regarding this order shall be referred to B E L Chairman & Managing Director or his nominee for arbitration who shall have all the powers conferred by the Indian Arbitration & Conciliation Bill 1996 or any statutory modification thereof in force.
3. In view of the above, reference need only be made to the skeletal facts necessary for adjudicating the issues raised by the parties.
4. On 6th October, 2008, the Respondent issued a Purchase Order (PO) to the Petitioner through which it sought to purchase the materials/goods, namely, Hydraulic Motor, Actuating Cylinder, EL Motor EDM, Converter and GYRO Unit.
5. The purchase order was issued along with a printed Annexure IV of "General Terms and Conditions of Purchase Order (Foreign)". As noticed above, the relevant arbitration clause is contained in the aforesaid general terms and conditions. The Petitioner claims that fifth item, as stated above, was GYRO Unit EK.2.369.113. CE in 174 Nos. The entire agreed terms of sale by the Petitioner was against 100% payment through Letter of Credit through the State Bank of India, Trade Finance Code of Civil Procedure, 16, Whannels Road, Egmore, Chennai, India, to the Petitioner and the said Letter of Credit was to be opened immediately after getting confirmation regarding readiness of the stock with the Petitioner. The GYRO Unit (174 in Nos.) were to be provided by the Petitioner to the Respondent as per the aforesaid agreement and the Petitioner took immediate steps to supply the said units to the Respondent. The Petitioner made huge investments in that regard and procured required materials. The specifications of GYRO Units, as per the specifications, did not stipulate, expressly or impliedly, the type of damping. While the entire process was going on, the Respondent issued a letter dated 5th June, 2009 to the Petitioner stating that as per the Respondent's directives, all pending supplies as on that date, from the Petitioner were to be "put on hold" and directed the Petitioner not to dispatch any pending items including those for which Letter of Credit had been established until further communication from the Respondent. After the aforesaid communication, the Respondent did not issue any communication to the Petitioner for supply of the said goods till 3rd December, 2009. In response to the aforesaid communication, the Petitioner sent 10 units of GYRO Stabilizers along with the Certificate which was issued by the Russian Company (manufacturer) for a lot of 24 units. It appears that the Respondent, on the basis of the inspection report dated 17th November, 2009, rejected two GYRO Units (out of total 10) on the ground that the same were defective. The defects pointed out were that "Turret not moving in 'Auto' mode" and "vibration in elevation observed in Turret". The other 8 Units were accepted. The Petitioner, therefore, called for payment of 8 accepted GYRO Units and assured the rectification of two rejected units. Through the communication dated 28th Dec
State of Punjab v. Amar Singh Harika : AIR 1966 SC 1313
Union of India and Anr. v. M.P. Gupta (2004) 10 SCC 504
Collector of Central Excise, Madras v. M.M. Rubber & Company
Denel (Proprietary) Limited v. Bharat Electronics Limited and Anr. : (2010) 6 SCC 394
Denel (Proprietary) Limited v. Ministry of Defence : (2012) 2 SCC 759
Greater Mohali Area Development Authority and Ors. v. Manju Jain and Ors. : (2010) 9 SCC 157
Indian Oil Corporation Limited and Ors. v. Raja Transport Private Limited : (2009) 8 SCC 520
Laxminarayan R. Bhattad and Ors. v. State of Maharashtra and Anr. : (2003) 5 SCC 413
Municipal Corporation of Delhi v. Qimat Rai Gupta and Ors. : (2007) 7 SCC 309
Northern Railway Administration, Ministry of Railway
Bachhittar Singh v. State of Punjab and Anr. : AIR 1963 SC 395
RITE Approach Group Ltd. v. Rosoboronexport : (2006) 1 SCC 206
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.