2013 Supreme(SC) 394

SUPREME COURT OF INDIA
Aftab Alam, K.S. Radhakrishnan & Ranjan Gogoi, JJ.
Orissa Mining Corporation Ltd. - Petitioner
Versus
Ministry of Environment & Forest & Others - Respondents
WRIT PETITION (CIVIL) NO. 180 OF 2011
Decided On : April 18, 2013

Headnote:

Constitution Of India,1950 - Articles 25 and 26 - Forest (Conservation) Act, 1980 - Section 2- Amendment Rules 2012 - MoEF appointment Central Mining Planning and Design Institute - Gram Sabha determining the claims - Sterlite (parent company of Vedanta) filed an application on 19.3.2003 before MOEF for environmental clearance for the purpose of starting an Alumina Refinery Project (ARP) in Lanjigarh Tehsil of District Kalahandi, stating that no forest land was involved within an area of 10 kms. The 4th respondent – Vedanta, in the meanwhile, had also filed an application on 6.3.2004 before this Court seeking clearance for the proposal for use of 723.343 ha of land (including 58.943 ha of reserve forest land) in Lanjigarh Tehsil of District Kalahandi for setting up an Alumina Refinery. Noticing that forest land was involved, the State of Orissa submitted a proposal dated 16.08.2004 to the MoEF for diversion of 58.90 hectare of forest land which included 26.1234 hectare of forest land for the said ARP and the rest for the conveyor belt and a road to the mining site. The State of Orissa, later, withdrew that proposal. The MoEF, as per the application submitted by M/s Sterlite, granted environmental clearance on 22.9.2004 to ARP on 1 million tonne per annum capacity of refinery along with 75 MW coal based CPP at Lanjigarh on 720 hectare land, by delinking it with the mining project. Later, on 24.11.2004, the State of Orissa informed MOEF about the involvement of 58.943 ha of forest land in the project as against “NIL” mentioned in the environmental clearance and that the Forest Department of Orissa had, on 5.8.2004, issued a show-cause-notice to 4th respondent for encroachment –Held, We are, therefore, inclined to give a direction to the State of Orissa to place these issues before the Gram Sabha with notice to the Ministry of Tribal Affairs, Government of India and the Gram Sabha would take a decision on them within three months and communicate the same to the MOEF, through the State Government. On the conclusion of the proceeding before the Gram Sabha determining the claims submitted before it, the MoEF shall take a final decision on the grant of Stage II clearance for the Bauxite Mining Project in the light of the decisions of the Gram Sabha within two months thereafter Refinery Project is well advised to take steps to correct and rectify the alleged violations by it of the terms of the environmental clearance granted by MoEF. Needless to say that while taking the final decision, the MoEF shall take into consideration any corrective measures that might have been taken by the Alumina Refinery Project for rectifying the alleged violations of the terms of the environmental clearance granted in its favour by the MoEF.

62. The proceedings of the Gram Sabha shall be attended as an observer by a judicial officer of the rank of the District Judge, nominated by the Chief Justice of the High Court of Orissa who shall sign the minutes of the proceedings, certifying that the proceedings of the Gram Sabha took place independently and completely uninfluenced either by the Project proponents or the Central Government or the State Government - Petition disposed

JUDGMENT

K. S. RADHAKRISHNAN, J.

1. Orissa Mining Corporation (OMC), a State of Orissa Undertaking, has approached this Court seeking a Writ of Certiorari to quash the order passed by the Ministry of Environment and Forests (MOEF) dated 24.8.2010 rejecting the Stage-II forest clearance for diversion of 660.749 hectares of forest land for mining of bauxite ore in Lanjigarh Bauxite Mines in Kalahandi and Rayagada Districts of Orissa and also for other consequential reliefs.

2. OMC urged that the above order passed by the MOEF has the effect of neutralizing two orders of this Court passed in I.A. Nos. 1324 and 1474 in Writ Petition (C) No. 202 of 1995 with I.A. Nos. 2081-2082 (arising out of Writ Petition No. 549 of 2007) dated 23.11.2007 reported in (2008) 2 SCC 222 [hereinafter referred to as ‘Vedanta case’] and the order passed by this Court in I.A. No. 2134 of 2007 in Writ Petition No. 202 of 1995 on 08.08.2008 reported in (2008) 9 SCC 711 [hereinafter referred to as the ‘Sterlite case’]. In order to examine the issues raised in this writ petition, it is necessary to examine the facts at some length.

FACTS:

3. M/s. Sterlite (parent company of Vedanta) filed an application on 19.3.2003 before MOEF for environmental clearance for the purpose of starting an Alumina Refinery Project (ARP) in Lanjigarh Tehsil of District Kalahandi, stating that no forest land was involved within an area of 10 kms. The 4th respondent – Vedanta, in the meanwhile, had also filed an application on 6.3.2004 before this Court seeking clearance for the proposal for use of 723.343 ha of land (including 58.943 ha of reserve forest land) in Lanjigarh Tehsil of District Kalahandi for setting up an Alumina Refinery. Noticing that forest land was involved, the State of Orissa submitted a proposal dated 16.08.2004 to the MoEF for diversion of 58.90 hectare of forest land which included 26.1234 hectare of forest land for the said ARP and the rest for the conveyor belt and a road to the mining site. The State of Orissa, later, withdrew that proposal. The MoEF, as per the application submitted by M/s Sterlite, granted environmental clearance on 22.9.2004 to ARP on 1 million tonne per annum capacity of refinery along with 75 MW coal based CPP at Lanjigarh on 720 hectare land, by delinking it with the mining project. Later, on 24.11.2004, the State of Orissa informed MOEF about the involvement of 58.943 ha of forest land in the project as against “NIL” mentioned in the environmental clearance and that the Forest Department of Orissa had, on 5.8.2004, issued a show-cause-notice to 4th respondent for encroachment of 10.41 acres of forest land (out of 58.943 ha for which FC clearance proposal was sent) by way of land breaking and leveling.

4. The State of Orissa, on 28.2.2005 forwarded the proposal to MOEF for diversion of 660.749 ha of forest land for mining bauxite ore in favour of OMC in Kalahandi and Rayagada Districts. The Central Empowered Committee (CEC), in the meanwhile, addressed a letter dated 2.3.2005 to MOEF stating that pending the examination of the project by CEC, the proposal for diversion of forest land and/or mining be not decided.

5. Vedanta, however, filed an application I.A. No. 1324 of 2005 before this Court seeking a direction to the MoEF to take a decision on the application for forest clearance for bauxite mining submitted by the state Government on 28.2.2005 for the Refinery project. The question that was posed by this Court while deciding the above-mentioned I.A. was whether Vedanta should be allowed to set up its refinery project, which involved the proposal for diversion of 58.943 ha. of forest land. CEC had, however, objected to the grant of clearance sought by Vedanta on the ground that the Refinery would be totally dependent on mining of bauxite from Niyamgiri Hills, Lanjigarh, which was the only vital wildlife habitat, part of which constituted elephant corridor and also on the ground that the said project would obstruct the proposed wild






























































































































































































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top