SUPREME COURT OF INDIA
KURIAN JOSEPH, R. BANUMATHI, JJ.
UNION OF INDIA – APPELLANT(S)
VERSUS
BESCO LTD. – RESPONDENT(S)
CIVIL APPEAL NO. 4483 OF 2017 (Arising out of S.L.P.(C) No. 17838 of 2014)
WITH
SPECIAL LEAVE PETITION (CIVIL) NO. 26614 OF 2014
Decided On : 27-04-2017
(2008) 10 SCC 240; (2014) 9 SCC 288; (2009) 8 SCC 520 – Relied upon
(2004) 10 SCC 504; (2011) 12 SCC 349 – Distinguished
(b) Arbitration and Conciliation Act, 1996 – Section 11(6) – Arbitration agreement not stipulating any specific person or official for appointment as arbitrator – High Court rightly appointed an independent arbitrator. (Para 11)
Facts of the case:
The short question arising in this case is whether the Chief Justice of a High Court or any person or institution designated by him, while exercising power under Section 11(6) of The Arbitration and Conciliation Act, 1996 is bound to nominate an arbitrator as specified in the agreement for arbitration. The designated Judge in the High Court took the view that the appellant has lost the mandate to appoint an arbitrator since it failed to appoint the arbitrator within the permitted time and hence nominated an independent arbitrator.
Finding of the Court:
There is no infirmity in the impugned order.
Result: Appeal and SLP dismissed.
JUDGMENT
KURIAN, J.
CIVIL APPEAL NO. 4483 OF 2017 (Arising out of S.L.P.(C) No. 17838 of 2014)
Leave granted.
2. The short question arising for consideration in this case is whether the Chief Justice of a High Court or any person or institution designated by him, while exercising power under Section 11(6) of The Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”) is bound to nominate an arbitrator as specified in the agreement for arbitration. The designated Judge in the High Court took the view that the appellant has lost the mandate to appoint an arbitrator since it failed to appoint the arbitrator within the permitted time and hence nominated an independent arbitrator.
3. Mr. Maninder Singh, learned Additional Solicitor General, placing reliance on Union of India and another v. M.P. Gupta, (2004) 10 SCC 504 and Union of India and others v. Master Construction Company, (2011) 12 SCC 349 submitted that the designated Judge, exercising the power under Section 11(6) of the Act, is bound to nominate a person as stipulated in the agreement for arbitration. In M.P. Gupta (supra), the relevant clauses on arbitration contained a provision that the arbitrators should be Gazetted Railway Officers. It may also be relevant in this context to note that the arbitration agreement contained a specific provision that it is a term of contract that no person other than a gazetted railway officer should act as an arbitrator/umpire and if for any reason, that is not possible, the matter is not to be referred to arbitration at all. This Court hence set aside the order passed by the designated Judge who had nominated a retired Judge as the sole arbitrator. In Master Construction Company (supra), the question in issue was, in fact, left open.
4. Mr. Dushyant Dave, learned Senior Counsel appearing for the respondent submits that once the right of a party to nominate an arbitrator is forfeited, the Chief Justice or the designated Judge under Section 11(6) of the Act is free to nominate any qualified person as arbitrator and that the Chief Justice or the designated Judge is not bound to nominate the arbitrator as specified in the agreement. Our attention has been invited to Northern Railway Administration, Ministry of Railway, New Delhi v. Patel Engineering Company Limited, (2008) 10 SCC 240 and North Eastern Railway and others v. Tripple Engineering Works, (2014) 9 SCC 288.
5. In Patel Engineering Company Limited (supra), a three-Judge Bench of this Court held that the Chief Justice or the designated Judge, if required, is free to deviate from the arbitration clause and nominate an independent person; but while doing so, due regard shall be given to the qualifications prescribed in the arbitration agreement, as required under Section 11(8) of the Act.
6. In Tripple Engineering Works (supra) also this Court reiterated the position that the Chief Justice or the designated Judge was free to deviate from the terms of the contract.
Paragraphs-6 and 7 read as follows:
“6. The “classical notion” that the High Court while exercising its power under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter for short “the Act”) must appoint the arbitrator as per the contract between the parties saw a significant erosion in ACE Pipeline Contracts (P) Ltd. v. Bharat Petroleum Corpn. Ltd. wherein this Court had taken the view that though the contract between the parties must be adhered to, deviations therefrom in exceptional circumstances would be permissible. A more significant development had come in a decision that followed soon thereafter in Union of India v. Bharat Battery Mfg. Co. (P) Ltd. wherein following a three-Judge Bench decision in Punj Lloyd Ltd. v. Petronet MHB Ltd. it was held that once an aggrieved party files an application under Section 11(6) of the Act to the High Court, the opposite party would lose its right of appointment of the arbitrator(s) as per the terms of the contract. The implication that the Cour
Union of India and another v. M.P. Gupta
Union of India v. Master Construction Company
Northern Railway Administration, Ministry of Railway, New Delhi v. Patel Engineering Company Limited
North Eastern Railway v. Tripple Engineering Works
Indian Oil Corporation and others v. Raja Transport Private Limited
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.