SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(SC) 340

SUPREME COURT OF INDIA
SANJIV KHANNA, CJI., SANJAY KUMAR, K.V. VISWANATHAN, JJ.
M/S. ABCI Infrastructures Pvt. Ltd. - Appellant
VERSUS
Union of India And Others - Respondents
Civil Appeal No. of 2025 (Arising out of Special Leave Petition (Civil) No. 25394 of 2023)
Decided On : 14-02-2025

Advocates appeared:
For the Petitioner(s): Mr. Mukul Rohatgi, Sr. Adv. Mr. Gaurav Khanna, AOR Ms. Natasha Sahrawat, Adv. Ms. Deepali Bhanot, Adv. Mr. Gautam Barnwal, Adv. Mr. Rudraksh Pandey, Adv. Ms. Alisha Roy, Adv.
For the Respondent(s): Ms. Archana Pathak Dave, A.S.G. Dr. N. Visakamurthy, AOR Mr. Yashraj Singh Bundela, Adv. Mr. Raman Yadav, Adv. Mr. Hitarth Raja, Adv. Mr. Udit Dedhiya, Adv. Mr. Mukesh Kumar Maroria, Adv. Mr. Sanjay Kapur, AOR Mr. Surya Prakash, Adv. Mr. Arjun Bhatia, Adv. Ms. Shubhra Kapur, Adv. Ms. Mahima Kapur, Adv.

IMPORTANT POINT
Mistake – A mistake may be unilateral or mutual, but it is always unintentional – If it is intentional, it ceases to be a mistake – Mistakes, including by authorities, should be resolved through corrective steps.

Headnote:

(A) Government Contract – Tender – Encashment of Bank Guarantee – BRO justified encashing bank guarantee by citing delays caused by issuing a second notice inviting bids – This claim is baseless – BRO’s claim that delay was entirely due to Appellant’s mistake is flawed, ignoring BRO’s own lapses – Mistakes, including by authorities, should be resolved through corrective steps – A practical approach could have avoided delay, which was caused by BRO’s refusal to acknowledge Appellant’s genuine error and the unwarranted cancellation of the bid – Appellant to pay Rs.1 Crore to BRO, as a consequence of their error – Upon receiving this payment, BRO shall return Appellant’s original bank guarantee or demand draft of Rs.15.04 Crores within one week. (Paras 12, 13 and 16)

(B) Contract Act, 1872 – Section 20 – Mistake – A mistake may be unilateral or mutual, but it is always unintentional – If it is intentional, it ceases to be a mistake – Mistakes or errors, though avoidable, are committed inadvertently – They have varied consequences in law – Where both parties to an agreement are under a mistake as to matter of fact essential to an agreement, agreement is void. (Para 5)

Facts of the case:

Short question before Court is whether BRO was justified in accepting bid of Rs.1,569, and on failure of Appellant to execute agreement asking for forfeiture vide encashment of bank guarantee of Rs.15,04,64,000.

Findings of Court:

Alleged two-month delay by Appellant is incorrect. Error, submitted on 03.06.2023, became apparent only when financial bids were opened on 24.08.2023. Appellant promptly acknowledged mistake on 25.08.2023.

Result : Appeal allowed.

Judgement Key Points

Key Points: - (!) - (!) - (!) - (!) - (!) - (!)

What is the legality of enforcing encashment of a bank guarantee when a bid error is clearly evident and promptly disclosed?

What are the conditions under which a bidder’s mistake in bid submission may be corrected or relief granted under the Indian Contract Act, 1872 (Section 20) and related equitable principles?

What are the Court’s determinations regarding responsibility for delays and corrective steps in public contract bidding when a bidder commits a unilateral mistake?


JUDGMENT

SANJIV KHANNA, CJI.

Leave granted.

2. This is an avoidable litigation. No doubt, there was a mistake on the part of the Appellant – M/s ABCI Infrastructure Private Limited, albeit, instead of taking a pragmatic approach, Respondent No. 2 – Border Road Organisation [Hereinafter, “BRO.”] under the Ministry of Defence, Union of India, adopted an obdurate and overly legalistic stance, causing a delay in the project's execution.

3. We begin by briefly discussing the facts of the case:

    o On 23.02.2023, BRO invited bids for the design and construction of two-lane twin tunnels, approximately 4.1 kilometres long, at Shinkun La Pass, including civil, electrical, and mechanical work, with approaches connecting the Darcha-Padam Highway to NHDL specifications in Himachal Pradesh and Ladakh. The estimated cost of the project was Rs.15,04,64,00,000/- (Rs. 1,504.64 crores). The project was to be completed within 48 months. The bid security amount was Rs.15,04,64,000/- (Rs. 15.04 crores)

    o Ten bidders, including the Appellant, had submitted their online Technical and Financial Bids on 03.06.2023. The Appellant, like others, had furnished a bank guarantee of Rs.15,04,64,000/-.

    o On 05.06.2023, technical bids were opened and seven bidders, including the Appellant, were declared technically qualified.

    o On 24.08.2023, the financial bids of seven bidders, including the Appellant, were opened and the results were declared.

    o The Appellant was ranked as L-1 bidder, with the bid price of Rs.1,569/- (Rupees One thousand five hundred and sixty-nine only). According to the Appellant, they had quoted a bid price of Rs.1,569 crores. However, due to what they claim was a system

    error, the quoted amount appeared as just Rs.1,569.

    o The Appellant claims that they discovered the mistake on 24.08.2023 when the financial bids were opened and announced, and therefore, on the next day, 25.08.2023, they informed the authorities that their actual bid was Rs.1,569 crores, not Rs.1,569. They attributed the error to a typographical mistake or a critical technical issue with the server. While we would not accept the plea of system error, the figure quoted was clearly unrealistic, a patent error and a mistake given the scale and nature of the work tendered. Though the mistake was bald-faced, what followed is incomprehensible, with BRO, insisting on accepting the bid, in spite of letters from the Appellant wanting to withdraw from the tender.

    o BRO, guided by the Evaluation Committee, instead of accepting the obvious, vide letter dated 26.08.2023, called upon the Appellant to justify the quoted amount of Rs.1,569 by providing a detailed price analysis, including the scope of work, completion schedule, risk allocation, safety requirements, and proof of capability to complete the project, by 31.08.2023.

    o On 30.08.2023, the Appellant reiterated that their intended bid was Rs.1,569 crores, not Rs.1,569, attributing the error to a technical or typographical mistake.

    o On 07.09.2023, the Appellant sent another letter stating they should not be considered the L1 bidder, and the bank guarantee of Rs.15,04,64,000 may be returned to them without encashment.

    o On 12.09.2023, the Appellant again wrote emphasizing that the bid was an error and that the bid security should not be forfeited.

    o Vide letter 16.09.2023, BRO, unmoved, wrote to the Appellant’s bank, the State Bank of India, stating that the Appellant had been declared a defaulter, and their bid security was to be forfeited. The bank was asked to encash the bank guarantee and remit Rs.15,04,64,000 to BRO.

    o The Appellant filed a writ petition before the High Court of Himachal Pradesh at Shimla, which stands dismissed by the impugned judgment dated 07.10.2023.

4. The short question before us is whether BRO was justified in accepting the bid of Rs.1,569, and on the failure of the Appellant to execute the agreement asking for forfeiture vide encashment of bank guarantee of Rs.15,04,64,000.

5. A mistake may be unilateral or mutual, bu

    Click Here to Read the rest of this document
    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    SupremeToday Portrait Ad
    supreme today icon
    logo-black

    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

    Please visit our Training & Support
    Center or Contact Us for assistance

    qr

    Scan Me!

    India’s Legal research and Law Firm App, Download now!

    For Daily Legal Updates, Join us on :

    whatsapp-icon Back to top