SUPREME COURT OF INDIA
SANJIV KHANNA, CJI., SANJAY KUMAR, K.V. VISWANATHAN, JJ.
M/S. ABCI Infrastructures Pvt. Ltd. - Appellant
VERSUS
Union of India And Others - Respondents
Civil Appeal No. of 2025 (Arising out of Special Leave Petition (Civil) No. 25394 of 2023)
Decided On : 14-02-2025
(A) Government Contract – Tender – Encashment of Bank Guarantee – BRO justified encashing bank guarantee by citing delays caused by issuing a second notice inviting bids – This claim is baseless – BRO’s claim that delay was entirely due to Appellant’s mistake is flawed, ignoring BRO’s own lapses – Mistakes, including by authorities, should be resolved through corrective steps – A practical approach could have avoided delay, which was caused by BRO’s refusal to acknowledge Appellant’s genuine error and the unwarranted cancellation of the bid – Appellant to pay Rs.1 Crore to BRO, as a consequence of their error – Upon receiving this payment, BRO shall return Appellant’s original bank guarantee or demand draft of Rs.15.04 Crores within one week. (Paras 12, 13 and 16)
(B) Contract Act, 1872 – Section 20 – Mistake – A mistake may be unilateral or mutual, but it is always unintentional – If it is intentional, it ceases to be a mistake – Mistakes or errors, though avoidable, are committed inadvertently – They have varied consequences in law – Where both parties to an agreement are under a mistake as to matter of fact essential to an agreement, agreement is void. (Para 5)
Facts of the case:
Short question before Court is whether BRO was justified in accepting bid of Rs.1,569, and on failure of Appellant to execute agreement asking for forfeiture vide encashment of bank guarantee of Rs.15,04,64,000.
Findings of Court:
Alleged two-month delay by Appellant is incorrect. Error, submitted on 03.06.2023, became apparent only when financial bids were opened on 24.08.2023. Appellant promptly acknowledged mistake on 25.08.2023.
Result : Appeal allowed.
Key Points: - (!) - (!) - (!) - (!) - (!) - (!)
JUDGMENT
SANJIV KHANNA, CJI.
Leave granted.
2. This is an avoidable litigation. No doubt, there was a mistake on the part of the Appellant – M/s ABCI Infrastructure Private Limited, albeit, instead of taking a pragmatic approach, Respondent No. 2 – Border Road Organisation [Hereinafter, “BRO.”] under the Ministry of Defence, Union of India, adopted an obdurate and overly legalistic stance, causing a delay in the project's execution.
3. We begin by briefly discussing the facts of the case:
o Ten bidders, including the Appellant, had submitted their online Technical and Financial Bids on 03.06.2023. The Appellant, like others, had furnished a bank guarantee of Rs.15,04,64,000/-.
o On 05.06.2023, technical bids were opened and seven bidders, including the Appellant, were declared technically qualified.
o On 24.08.2023, the financial bids of seven bidders, including the Appellant, were opened and the results were declared.
o The Appellant was ranked as L-1 bidder, with the bid price of Rs.1,569/- (Rupees One thousand five hundred and sixty-nine only). According to the Appellant, they had quoted a bid price of Rs.1,569 crores. However, due to what they claim was a system
error, the quoted amount appeared as just Rs.1,569.
o The Appellant claims that they discovered the mistake on 24.08.2023 when the financial bids were opened and announced, and therefore, on the next day, 25.08.2023, they informed the authorities that their actual bid was Rs.1,569 crores, not Rs.1,569. They attributed the error to a typographical mistake or a critical technical issue with the server. While we would not accept the plea of system error, the figure quoted was clearly unrealistic, a patent error and a mistake given the scale and nature of the work tendered. Though the mistake was bald-faced, what followed is incomprehensible, with BRO, insisting on accepting the bid, in spite of letters from the Appellant wanting to withdraw from the tender.
o BRO, guided by the Evaluation Committee, instead of accepting the obvious, vide letter dated 26.08.2023, called upon the Appellant to justify the quoted amount of Rs.1,569 by providing a detailed price analysis, including the scope of work, completion schedule, risk allocation, safety requirements, and proof of capability to complete the project, by 31.08.2023.
o On 30.08.2023, the Appellant reiterated that their intended bid was Rs.1,569 crores, not Rs.1,569, attributing the error to a technical or typographical mistake.
o On 07.09.2023, the Appellant sent another letter stating they should not be considered the L1 bidder, and the bank guarantee of Rs.15,04,64,000 may be returned to them without encashment.
o On 12.09.2023, the Appellant again wrote emphasizing that the bid was an error and that the bid security should not be forfeited.
o Vide letter 16.09.2023, BRO, unmoved, wrote to the Appellant’s bank, the State Bank of India, stating that the Appellant had been declared a defaulter, and their bid security was to be forfeited. The bank was asked to encash the bank guarantee and remit Rs.15,04,64,000 to BRO.
o The Appellant filed a writ petition before the High Court of Himachal Pradesh at Shimla, which stands dismissed by the impugned judgment dated 07.10.2023.
4. The short question before us is whether BRO was justified in accepting the bid of Rs.1,569, and on the failure of the Appellant to execute the agreement asking for forfeiture vide encashment of bank guarantee of Rs.15,04,64,000.
5. A mistake may be unilateral or mutual, bu
West Bengal State Electricity Board v. Patel Engineering Company Limited and Others
Moffett, H. and C. Co. v. Rochester
M/s Omsairam Steels & Alloys Pvt. Ltd. v. Director of Mines and Geology, BBSR & Ors.
Mistake – A mistake may be unilateral or mutual, but it is always unintentional – If it is intentional, it ceases to be a mistake – Mistakes, including by authorities, should be resolved through corr....
Courts may mitigate penalties for inadvertent bidding errors, emphasizing fairness in tender processes.
Tender conditions prohibiting the modification or withdrawal of bids after submission are strictly binding. A unilateral clerical error by a bidder does not entitle them to equitable relief or the re....
E-auction – Mistake in bid – While undertaking exercise of judicial review of matters relating to tenders, court has to strike a fair balance between interests of Government, which is always expected....
The sanctity of the offer made by the tenderer must be respected, and once a bid has been submitted pursuant to a tender, it has to be the price which the tendering authority is bound to consider whi....
The timing of offer acceptance and withdrawal in relation to EMD forfeiture is crucial in determining the applicability of tender clauses and the entitlement to EMD return.
Government Contract – Sanctity of tender process is paramount and should be maintained at all cost – While benefit or accrual of more revenue to public exchequer is certainly an important aspect, equ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.