SUPREME COURT OF INDIA
B.V. NAGARATHNA, SATISH CHANDRA SHARMA, JJ.
M/s. Parsvnath Film City Ltd. – Appellant
Versus
Chandigarh Administration and Others – Respondents
Civil Appeal No. 6162 of 2016
WITH
The Secretary, Information Technololgy, Chandigarh Administration – Appellant
Versus
M/s. Parsvnath Film City Ltd. and Others – Respondents
Civil Appeal No. 10490 of 2017
Decided On : 20-03-2025
JUDGMENT :
B.V. NAGARATHNA, J.
1. Two appeals, namely, Civil Appeal No. 6162 of 2016 and Civil Appeal No. 10490 of 2017, are disposed of by this common judgment.
Civil Appeal No. 6162 of 2016
2. The appellant in Civil Appeal No. 6162 of 2016, M/s Parsvnath Film City Limited (hereinafter “appellant”) has approached this Court against the impugned judgment of the High Court of Punjab and Haryana at Chandigarh in FAO No. 5816 of 2015 (O&M) partially allowing the appeal filed by the respondents (i) Chandigarh Administration and (ii) the Secretary, Information Technology, Chandigarh Administration under Section 37 of the Arbitration and Conciliation Act, 1996 (for short “the Act”). The High Court, vide the impugned judgment, set aside the award of the Arbitral Tribunal dated 10.03.2012 and the order of the Additional District Judge, Chandigarh in Arbitration Case No. 530 of 2013 dated 08.04.2015, thereby sustaining the respondent’s action in forfeiting 25% of the bid amount, i.e. Rs. 47.75 crores.
3. The respondents have filed Civil Appeal No. 10490 of 2017 against the same impugned judgment on the ground that it did not allow the other claims raised by them, such as (i) interest on delayed payment of Annual Ground Rent; (ii) forfeiture of Rs. Five crores paid by the appellant towards the bid security; (iii) recovery of performance security shortfall of Rs. Five crores along with interest and (iv) recovery of other miscellaneous expenses.
4. Respondent Nos. 3-5 in both these appeals are the members of the Arbitral Tribunal who have been added as only proforma respondents.
5. The facts of the case relate to the respondents deciding to establish a Multimedia-cum-Film City at Chandigarh. To that end, it published an advertisement dated 29.03.2006 inviting “Expression of Interest for Multimedia-cum-Film City” as an integrated project in Sarangpur, Chandigarh on a leasehold land admeasuring thirty acres. The project involved setting up of state-of-the-art facilities for:
(ii) a multimedia park.
(iii) a multimedia information-cum-entertainment centre.
(iv) a multimedia college.
The expression of interest complete in all respects was to be submitted on or before 28.04.2006. Out of the fourteen companies which submitted the expression of interest, six were selected, including the appellant herein. Consequent upon technical presentations and submission of technical bids, four companies were shortlisted, including the appellant herein. A copy of the Request for Proposal and the Draft Development Agreement was sent to the appellant by the respondent on 24.11.2006.
6. On receipt of the same, a pre-bid meeting was held on 08.12.2006 and various clarifications were sought on the proposal, which were furnished by the respondents vide letter dated 15.12.2006. Thereafter, the shortlisted companies, including the appellant, submitted their respective bids, and since the offer of the appellant was the highest, the respondents issued letter of acceptance in favour of the appellant on 18.01.2007. In that letter, the appellant was asked to take steps for execution of the Development Agreement within a period of twenty days from the letter and to also arrange the upfront amount.
7. By letter dated 21.02.2007, appellant stated that they would sign the Development Agreement, but requested (i) for demarcation of the project site, as without the same, they could not proceed with the work and (ii) preparation of the layout plan to be annexed with the Development Agreement. Thereafter, on 01.03.2007, appellant furnished 25% of the bid amount, i.e. Rs. 47.75 crore, by way of Demand Draft.
8. On 02.03.2007, the appellant expressed its readiness to sign the Development Agreement. However, as the final demarcation was yet not settled, it requested that:
(ii) The payment of next instalment due which was 75% of the bid price to be pai
The court ruled that unreasonable delays by one party in fulfilling contractual obligations can lead to frustration of contract, justifying the other party's claims for relief.
The court upheld the trial court's dismissal of the appeal against the arbitration award, confirming that there was no patent illegality or grounds for interference under the Arbitration and Concilia....
The Court's power while exercising jurisdiction under Section 37 of the Act is limited, and it cannot undertake an independent assessment on the merits of the Award.
The court confirmed that judicial interference in arbitral awards is limited to cases of patent illegality or perverse findings, respecting the finality of arbitration.
The main legal point established in the judgment is the interpretation of contract terms, breach of contract, and the limited scope of interference with the arbitrator's award based on the violation ....
The court emphasized that arbitral awards should not be interfered with solely based on disagreements with findings, affirming the limited grounds for appeal under Section 34 of the Arbitration Act.
The court reiterated that a party's failure to perform contractual obligations negates the other's right to enforce the contract, emphasizing limited interference in arbitral awards.
The appellate jurisdiction under section 37 is limited to the grounds prescribed under section 34. Courts cannot re-appreciate evidence or substitute their views for that of the arbitrator, provided ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.