SUPREME COURT OF INDIA
Abhay S. Oka, Ujjal Bhuyan, JJ.
M/s. Interstate Construction – Appellant
Vs.
National Projects Construction Corporation Ltd. – Respondent
Civil Appeal No. 3461 of 2025
Decided On : 15-05-2025
(A) Arbitration and Conciliation Act, 1996 - Section 31(7)(a) - Award of interest by Arbitrator - Interest has to be awarded as specified in contract and in absence of any contract, as per discretion of Arbitral Tribunal - Award of interest like award of cost are ancillary matters. Therefore, the expressions sum for which the award is made and the sum directed to be paid by an arbitral award contextually refers to the award on the substantive claims and not ancillary or consequential directions relating to interest or cost - Interest may be for whole or any part of period between date on which cause of action arose and date on which award is made - There is now a statutory recognition of power of Arbitral Tribunal to grant pre-reference interest from date on which cause of action arose till the date on which award is made - Arbitral Tribunal can exclude a period from the date on which cause of action arose till the date on which the award is made for the purpose of grant of interest - Arbitral Tribunal can grant interest for whole or any part of period between date on which cause of action arose and date on which award is made - It can be a composite period or said period can be further sub-divided. (Paras 28, 32, 34, 35 and 39)
(B) Arbitration and Conciliation Act, 1996 - Sections 31(7)(a) and 31(7)(b) - Sum awarded - Sum awarded would mean principal amount plus interest awarded from the date of cause of action up to date of award - Sum awarded in Section 31(7)(a) would mean principal amount plus interest awarded - As per Section 31(7)(b) of 1996 Act, sum (principal amount + interest) would carry further interest at the rate of 2 per cent higher than current rate of interest prevalent on date of award to date of payment. (Para 44)
Facts of the case:
Vide impugned judgment), Division Bench of High Court of Delhi (High Court) allowed appeal of National Projects Construction Corporation Limited, (NPCC) filed under Section 37 of Arbitration and Conciliation Act, 1996, setting aside that part of judgment and order dated 02.08.2021 passed by a Single Judge of High Court under Section 34 of 1996 Act upholding directions contained in Paragraph 58(b) of award.
Findings of Court:
Division Bench had fallen in error by holding that Arbitral Tribunal had no jurisdiction to award interest for two periods i.e. pre-reference and pendente lite when statute provides for only one period viz. from the date when the cause of action arose till the date of the award.
Result : Civil Appeal allowed.
JUDGMENT :
Ujjal Bhuyan, J.
This appeal by special leave is directed against the judgment and order dated 01.08.2023 passed by the Division Bench of the High Court of Delhi in FAO (OS) (Comm) No.175 of 2021.
2. It may be mentioned that by the aforesaid judgment and order dated 01.08.2023 (impugned judgment), Division Bench of the High Court of Delhi (High Court) allowed the appeal of National Projects Construction Corporation Limited, (NPCC) or the respondent hereinafter, filed under Section 37 of the Arbitration and Conciliation Act, 1996 (briefly ‘the 1996 Act’ hereinafter) setting aside that part of the judgment and order dated 02.08.2021 passed by a learned Single Judge of the High Court under Section 34 of the 1996 Act upholding the directions contained in paragraph 58(b) of the award dated 28.10.2020 as well as setting aside the directions of the arbitral tribunal as contained in paragraph 58(b) of the said award.
3. Relevant facts may be briefly noted.
4. Respondent had engaged the services of the appellant for executing a contract relating to Ramagundam Super Thermal Power Project, Ramagundam, District Karimnagar in the then composite State of Andhra Pradesh. In this regard, two separate work orders were issued:
(ii) Work Order No. 917344/2382 in respect of the work foundation package work, stage-II, at Ramagundam Super Thermal Power Project;
5. Thereafter, contract agreement was entered into between the parties. As per clause 4 of the conditions of contract read with clause 15 of the special conditions attached to the work orders, all the disputes and differences between the parties were to be settled by way of arbitration.
6. It is stated that appellant had completed the contract work in the year 1987. Respondent had paid the appellant the contractual dues after withholding certain sums on account of recoveries. Appellant disputed such recoveries. Additionally, appellant also raised certain claims which were not accepted by the respondent.
7. In view of such disputes and differences, appellant invoked the arbitration clause by issuing notice dated 17.05.1993.
8. Respondent did not take immediate steps for appointment of an arbitrator. After considerable delay, by communication dated 07.10.1997, respondent appointed Shri Shivamoy Ghosh, Additional General Manager, NPCC, Madras Sector, Chennai as the sole arbitrator to arbitrate on the subject dispute.
9. Appellant filed statement of claims before the learned arbitrator on 20.01.1998 claiming an aggregate amount of Rs.4,46,29,404.00 along with pendente lite and future interest at the rate of 24 percent per annum till final realization of the amount.
10. Appellant sought for a direction from the learned arbitrator to the respondent to supply various documents related to the dispute. However, learned arbitrator only permitted the appellant an opportunity to inspect the documents and did not issue any direction to the respondent for supply of copies.
11. Aggrieved thereby, appellant filed a petition under Section 14 of the 1996 Act before the High Court seeking termination of the mandate of the learned arbitrator and for appointment of a new arbitrator in his place. This petition was registered as OMP No. 214/2002. By order dated 11.10.2004, learned Single Judge terminated the mandate of Shri Shivamoy Ghosh and appointed Shri A.S. Chandhiok, Sr. Advocate, as the sole arbitrator.
12. Respondent challenged the said order of the learned Single Judge dated 11.10.2004 before the Division Bench of the High Court in FAO (OS) No.241/2004. By order dated 02.02.2005, Division Bench appointed Shri L.R. Gupta, retired Director General of CPWD as the sole arbitrator.
13. Before Shri L.R. Gupta, the learned arbitrator, respondent while filing its reply to the statement of claims filed by the appe
Sayeed Ahmed and Company Vs. State of Uttar Pradesh
Pam Developments Private Limited Vs. State of West Bengal
State of Haryana Vs. S.L. Arora
Hyder Consulting (UK) Ltd. Vs. Governor, State of Orissa
UHL Power Company Ltd. Vs. State of Himachal Pradesh
Delhi Airport Metro Express Private Ltd. Vs. Delhi Metro Rail Corporation
Morgan Securities and Credits Private Ltd. Vs. Videocon Industries Limited
(1) Interest has to be awarded as specified in contract and in absence of any contract, as per discretion of Arbitral Tribunal - Arbitral Tribunal can grant pre-reference interest from date on which ....
An arbitral award's stipulations on interest must be strictly enforced as per the parties' agreement, disallowing claims for compound interest unless explicitly provided, reinforcing party autonomy i....
Arbitral Tribunal's power to grant interest for the period post award till realization is subject to the discretion only in respect to the rate as it is the mandate of the law to grant such interest ....
The court clarified that post-award interest includes both principal and pre-award interest, overruling previous decisions that restricted such calculations.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.