High Court of Andhra Pradesh
SANJAY KUMAR, J.
BGR Energy Systems Limited
Versus
A.P.Power Generation Corporation Ltd.
Writ Petition No.11875 of 2010
Decided On : 09-09-2010
Electricity (Supply) Act, 1948 – Section 3 – Electricity Act, 2003 – Sections 185, 70 – Prescription of pre-qualification criteria by the Andhra Pradesh Power Generation Corporation Limited (APGENCO) at variance with the guidelines issued by the Central Electricity Authority (CEA) is called in question – Held, Except for a bald allegation, the petitioner company has not substantiated that the tender conditions were tailor made to exclude it from the competitive process or that its disqualification was actuated by malice or malafides – That being so, the prescription of higher standards in the pre-qualification criteria by the APGENCO cannot be said to be illegal – Consequential disqualification of the petitioner company by application of such higher standards is therefore equally free of illegality – Writ Petition Dismissed (Paras 41, 42)
Prescription of pre-qualification criteria by the Andhra Pradesh Power Generation Corporation Limited (APGENCO) at variance with the guidelines issued by the Central Electricity Authority (CEA) is called in question.
2. The APGENCO invited pre-qualification bids for selection of qualified bidders for execution of Engineering, Procurement and Construction (EPC) contracts for Balance of Plant (BoP) works for its 1 x 600 MW Coal Fired Thermal Power Station at Kakatiya Thermal Power Plant (TPP) Stage-II in Chelpur Village, Ghanapuram Mandal, Warangal District and its 1 x 600 MW Rayalaseema TPP Stage-IV in Kadapa District, Andhra Pradesh. This invitation to offer was posted on the website of the APGENCO on 25.08.2009 and was published in Hindu English daily newspaper on 29.08.2009. Responding thereto, eight bidders, including the petitioner company, submitted their bids before the closing date, 10.09.2009. The notification specified the following eligibility criteria, amongst others:
“2.1. The bidder should have executed contracts on an Engineering, Procurement and Construction (EPC) basis for at least one (1) no. Coal Based/Lignite Based/Gas Based Combined Cycle Power Plant of installed capacity not less than 300 MW which has been commissioned during last seven (7) years and has been in successful operation for a period of not less than one (1) year as on the date of bid opening. ………
………
3.4 The average annual turnover of the bidder/consortium leader should be at least Rs.500 crore during the preceding three consecutive years. ………”
3. Admittedly, the petitioner company did not satisfy the aforestated eligibility conditions but submitted its bid. By letter dated 25.02.2010 the petitioner company addressed the APGENCO complaining of the above pre-qualification requirements which were not in accordance with the CEA’s guidelines or the previous tenders of the APGENCO and requested it to modify the said requirements so as to permit the petitioner company to participate in the tender process.
4. Stating that it had learnt that the APGENCO had decided in May, 2010 to qualify only three out of the eight bidders to its exclusion, the petitioner company filed the present writ petition. Challenge was laid against the petitioner company’s disqualification on the basis of what it termed to be illegal and unauthorized tender conditions.
5. By order dated 26.05.2010, this Court directed status quo obtaining as on that date to be maintained. However, by subsequent order dated 04.06.2010, this Court permitted the APGENCO to undertake further process in pursuance of the tender notification but restrained it from finalizing the tenders until further orders.
6. Aggrieved thereby, the APGENCO filed the present vacate stay application in WVMP No.2068 of 2010. However, with the consent of the learned counsel, the main writ petition itself is taken up for consideration and disposal.
7. It is the case of the petitioner company that during the years 2005-08, the APGENCO had issued four tenders relating to execution of BoP works, in all of which the pre-qualification requirements were far lower than those prescribed in the subject notification. The petitioner company claimed to have emerged successful in bidding for the above works. The main thrust of the attack is however as to the disparity between the criteria prescribed in the subject notification and the CEA’s guidelines which are said to be statutory. It is alleged that prescribing such higher pre-qualification requirements is without rationale and would restrict healthy competition. The petitioner company further alleged that these pre-qualification criteria have been prescribed to ensure that the petitioner company is eliminated from the competition as it had emerged the successful bidder in the earlier projects.
8. In its counter, the APGENCO assailed the locus of the petitioner company to challenge the norms of eligibility/pre-qualification prescribed in the tender notification af
I.V.R.Constructions Ltd V. Sukdevraj Sharma And Bros. (1998 (6) ALD 467).
Reliance Energy Ltd. V. Maharashtra State Board Development Corpn. Ltd. (2007) 8 SCC 1)
Union Of India V. International Trading Co. (2003) 5 Scc 437)
Raunaq International Ltd. V. I.V.R. Construction Ltd. (1999) 1 SCC 492)
Master Marine Services (P) Ltd. V. Metcalfe & Hodgkinson (P) Ltd. (2005) 6 SCC 138):
Siemens Public Communication Networks (P) Ltd. V. Union Of India (2008) 16 SCC 215)
Directorate Of Education V. Educomp Datamatics Ltd. (2004) 4 SCC 19)
Assn. Of Registration Plates V. Union Of India (2005) 1 SCC 679)
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.