Andhra Pradesh High Court
Judges : N.Y.HANUMANTHAPPA, NEELAM SANJIVA REDDY
I.V.R.Constructions Ltd - Appellant
Versus
Sukdevraj Sharma and Bros - Respondent
Decided On : 09-11-98
TENDER - ACCEPTANCE - JUDICIAL REVIEW - SCOPE - CONTRACTUAL OBLIGATIONS - ENFORCEMENT - WRIT JURISDICTION - BIAS - ALLEGATION - JUDICIAL REVIEW - SCOPE - ADMINISTRATIVE ACTION - JUDICIAL RESTRAINT - CONTRACTUAL POWERS - GOVERNMENT - FAIRNESS - REASONABLENESS - NON-ARBITRARINESS - ABSENCE OF MALA FIDES - JUDICIAL INTERFERENCE - SCOPE - CONTRACTUAL MATTERS - REVIEW - SCOPE.
Fact of the Case:
The petitioner, a class contractor, submitted a tender for the construction of a Gateway Technical Building for Videsh Sanchar Nigani Ltd. at Madhapur, Hyderabad. Seven contractors submitted tenders, including the petitioner and the 4th respondent. The 2nd respondent, the Executive Engineer, Telecom, Civil Division-I, opened all the sealed tenders in the presence of the contractors and read out the rate of each item of the schedule for the information of the tenderers present. The same was noted by them. The 2nd respondent also read out the total amount of each tender and the rates/quantum quoted by the various tenderers. The petitioner's tender was the lowest. However, the 2nd respondent accepted the tender of the 4th respondent, who quoted a higher price than the petitioner. The petitioner challenged the acceptance of the 4th respondent's tender by way of a writ petition, alleging that the 2nd respondent misled him and informed him that the 4th respondent quoted Rs. 19.00 per kg for item No. 20, but in fact he quoted Rs. 21.00 per kg. The petitioner also alleged that the entire exercise of finalising the tender was a preplanned, fraught with suspicion, doubt and appears to be very carefully stage-managed at the behest of the 4th respondent. The 2nd respondent denied the allegations made by the petitioner and submitted that the tender of the 4th respondent was accepted after exercising due diligence and care and after taking the legal advice from the Law Ministry to protect the interest of the department, but not otherwise as alleged by the petitioner. The 4th respondent also denied the allegations made by the petitioner and submitted that the quoting of two rates for item No. 20 was occasioned inadvertently in the 4th respondent's office in that the staff of the 4th respondent while highlighting the rate of Rs. 19.00 by encircling it, by mistake failed to strike off the rate of Rs. 20.00. The learned single Judge allowed the writ petition and directed the official respondents to re-tender the work to the successful bidder.
Finding of the Court:
The Court held that the acceptance or rejection of a tender is governed by the conditions of the tender. As per the terms of the tender a discretion is given to the department either to accept or reject the tender without assigning any reasons. It is settled principle that there cannot be any interference by the High Court under Article 226 of the Constitution of India in contractual obligations unless it is shown such an entrustment of contract is violative of Article 14 of the Constitution of India or it results in depriving of fundamental right or at least a statutory right. The Court further held that the petitioner has not shown how, by accepting the tender of R-4, his right has been affected and such acceptance is violative of Article 14 of the Constitution of India. However, if there is any impropriety, fraud or mischief alleged to have been played by the authorities in accepting the tender of the fourth respondent and rejecting his tender the petitioner has to agitate the same before appropriate forum by leading evidence and Article 226 is not the proper remedy.
Issues: 1. Whether the High Court can interfere with the acceptance or rejection of a tender by the department under Article 226 of the Constitution of India? 2. Whether the petitioner has locus standi to challenge the acceptance of the 4th respondent's tender? 3. Whether the acceptance of the 4th respondent's tender was biased or mala fide?
Ratio Decidendi: 1. The High Court cannot interfere with the acceptance or rejection of a tender by the department under Article 226 of the Constitution of India unless it is shown that such an entrustment of contract is violative of Article 14 of the Constitution of India or it results in depriving of fundamental right or at least a statutory right. 2. A rival tenderer has locus standi to challenge the acceptance of a tender by the department if it is shown that such acceptance or rejection is arbitrary or discriminatory, which is causing loss to the State. 3. The acceptance of the 4th respondent's tender was not biased or mala fide.
Final Decision: The Court allowed the writ appeals filed by the respondents and dismissed the writ appeal filed by the petitioner. The Court held that the order passed by the learned single Judge so far as it relates to the cancelling the allotment of work to the 4th respondent by accepting his tender and directing the authorities to call for fresh tenders is incorrect and the same is quashed.
( 1 ) ALL these three appeals have been filed against the order of this Court dated 1-5-1998 passed in WPNo. 3912ofl998.
( 2 ) SINCE the question involved in these appeals is one and the same, they are heard together and disposed by a common judgment.
( 3 ) WP No. 3912 of 1998 was filed by M/s Sukhdevraj Sharma and Brothers against four respondents, namely (1) Union of India, Department of Telecommunications, (2) Executive Engineer, Telecom, Civil Division-I, (3) Chief Engineer, Telecom, Civil Zone and (4) M/s. IVR Constructions Ltd. , seeking a direction to the 2nd respondent to accept the petitioner s tender which is the lowest.
( 4 ) AFTER hearing both sides, the learned single Judge passed the impugned order directing the respondents-authorities to retender the work and allot it to the successful bidder. Aggrieved by this, the Respondent Nos. 1 to 3 filed WA No. 982 of 1998, the 4th respondent filed WANo. 973 of 1998. Also the petitioner WA No. 980 of 1998 aggrieved by this order in so far it not granting the relief sought by him, namely to accept the petitioner s tender being the lowest one.
( 5 ) FOR purpose of convenience, the rank of the parties is as in the writ petition.
( 6 ) THE facts which are not in dispute are as follows: The petitioners are s Class contractors. The 2nd respondent issued a notice inviting tenders for construction of Gateway Technical Building for Videsh Sanchar Nigani Ltd. , at Madhapur, Hyderabad. Seven contractors submitted their tenders. The petitioner firm and the 4th respondent firm are among them. The department (2nd respondent) opened all the 7 sealed tenders in the presence of the contractors and read out the rate of each item of the schedule for the information of the tenderers present. The same was noted by them. The 2nd respondent also read out the total amount of each tender and the rates/ quantum quoted by the various tenderers as noted herein:1) M/s. Sukhdevraj Sharma and Bros. . Rs. 1,89,21,685-002) M/s. Lakshman Singh and Bros. . Rs. 2,64,44,645-003) M/s. V. K. Bhat. . Rs. 1,98,02,335-004) M/s. Janardhan Rao. . Rs. 1,86,90,795-005) M/s. A. Naraharirao (Conditional ). . Rs. 2,33,84,345-006) M/s. IVR Constructions. . Rs. 1,93,71,099-007) M/s. Kwality Constructions. . Total amount not given.
( 7 ) THE grievance of the petitioner is that on 23-1-1998 he enquired with the 2nd respondent as to who was the lowest tenderer and the petitioner was informed that his tender would be accepted. While so, the petitioner heard on 6-2-1998 that the 2nd respondent was likely to accept the tender of the 4th respondent, who quoted higher price than the petitioner. According to the petitioner, the 4th respondent quoted Rs. 21. 00 per kg for item No. 20. The 2nd respondent misled the petitioner and informed that the 4th respondent quoted Rs. 19. 00 per kg for item No. 20, but in feet he quoted Rs. 21. 00 per kg as noted by all the persons present at the time of opening the tenders. Immediately, the petitioner got issued a telegram through his Counsel calling upon the 2nd respondent to reject the tender of the 4th respondent and accept its tender being the lowest. It was alleged by the petitioner that the entire exercise of finalising the tender was a preplanned, fraught with suspicion, doubt and appears to be very carefully stage-managed at the behest of the 4th respondent. The 2nd respondent gave reply on 9-2-1998 to the telegram sent by the petitioner. The petitioner also replied to the departmental authorities on 9-2-1998 pointing the mischief played on the petitioner and the gross irregularity committed by the authorities in accepting the tender of the 4th respondent, when the petitioner was the lowest tenderer. The petitioner lastly submitted that the petitioner is working for the department of Telecommunications for the past 15 years carrying on prestigious constructions all over India. The finalisation of the present tender in favour of the 4th respondent was the resul
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.