IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
M. SATYANARAYANA MURTHY, J.
Perumalla Madhusudhan Rao - Petitioner
Versus
The AP TRANSCO - Respondent
Writ Petition No. 25757 of 2020
Decided On : 26-02-2021
Industrial Disputes Act, 1947 – Section 12 – Termination of Services – Constitution of India, 1950 – Article 226 – Petitioners, who were working under the contractor – M/s.Sterling and Wilson Private Limited, filed this petition under Article 226 of the Constitution of India against the AP TRANSCO and its officials to declare the action of respondent No.3 in orally terminating the services of the petitioners from Electrical High Tension 132/33 KV Sub-Station, Vinjamuru and not allowing petitioners for duties with effect from 23.11.2020 on the ground that the contract of the then contractor of Electrical High Tension 132/33 KV Sub-Station, Vinjamuru vide letter dated 20.11.2020 of respondent No.3 as illegal, arbitrary, discriminative, contrary to the ratio laid down by the Apex Court in para 46 at page 151 in “State of Haryana v. Piara Singh, (1992) 4 SCC 118” and also in para-18 of the judgment in “K. Ravinder v. A.P. Generation Corporation Limited, Hyderabad, (2000) 6 ALD 56” and contrary to the letter and spirit of the Memo No. CGM (HRD/ DS/ AS.III/ PO.VII /Adm/D.No.3596/04, dated 27.12.2004 besides violative of Article 14, 16 and 21 of the Constitution of India and consequently, direct the respondents to allow the petitioners to discharge their usual daily duties just like before 23.11.2020 in their respective capacities irrespective of the fact of change of contractors from time to time.
Finding of court: Imposition of such condition to engage the workers being engaged by other contractor is made mandatory in the judgment, but the concept of contract is totally different as there is bargain with the employees by the independent contractor and if such direction is given to the respondents herein, there is no possibility of engaging highly skilled, skilled or unskilled workers by the independent contractor of his choice settling the bargain regarding salaries etc., it impedes the very purpose of maintenance contract of 132/33 KV Sub-Station, Vinjamuru – One of the reliefs claimed by the petitioners is to permit them to discharge their duties as usual. – Unless, maintenance work is entrusted to another independent contractor and the said contractor engages the services of the petitioner, they cannot be allowed to discharge their duties. – Another contention of the petitioners is that as per memo all Superintending Engineers/Operation are informed to advice the contractors not to change the labour who were already working with the respective contractors. – No doubt, in view of the instructions issued in memo, respondent No.3 is bound to adhere to the memo referred above in the event of change of contractor and it is for respondent No.3 to incorporate such condition keeping in view the law laid down by the learned Single Judge of the High Court of Andhra Pradesh at Hyderabad in “K. Ravinder v. A.P. Generation Corporation Limited, Hyderabad” (referred supra) and in the memo, at least the interest of the petitioners shall be protected to some extent. – Even if, the services of the petitioners are engaged by the Contractor, they are not entitled for regularisation or absorption in the department in the absence of any rules for their absorption or regularisation. – Petitioners contended that they were orally terminated by the respondents. – The question of termination of petitioners does not arise as there was no relationship of employee and employer between the petitioners and the respondents and their services were engaged by independent contractor, who is not a party to this petition. – As soon as the contract is terminated, the petitioners are not entitled to work in 132/33 KV Sub-Station, Vinjamuru. – Hence, the alleged termination is neither true nor correct and this Court cannot declare the alleged oral termination of the services of the petitioner as illegal and arbitrary. – Court find that it is a fit case to issue a direction to respondent No.3 to advice the contractors not to change the labour who were already working with the respective contractors.
Result: Writ Petition Dismissed
ORDER :
1. The petitioners, who were working under the contractor – M/s.Sterling and Wilson Private Limited, filed this petition under Article 226 of the Constitution of India against the AP TRANSCO and its officials to declare the action of respondent No.3 in orally terminating the services of the petitioners from Electrical High Tension 132/33 KV Sub-Station, Vinjamuru and not allowing petitioners for duties with effect from 23.11.2020 on the ground that the contract of the then contractor of Electrical High Tension 132/33 KV Sub-Station, Vinjamuru vide letter dated 20.11.2020 of respondent No.3 as illegal, arbitrary, discriminative, contrary to the ratio laid down by the Apex Court in para 46 at page 151 in “State of Haryana v. Piara Singh, (1992) 4 SCC 118” and also in para-18 of the judgment in “K. Ravinder v. A.P. Generation Corporation Limited, Hyderabad, (2000) 6 ALD 56” and contrary to the letter and spirit of the Memo No. CGM (HRD/ DS/ AS.III/ PO.VII /Adm/D.No.3596/04, dated 27.12.2004 besides violative of Article 14, 16 and 21 of the Constitution of India and consequently, direct the respondents to allow the petitioners to discharge their usual daily duties just like before 23.11.2020 in their respective capacities irrespective of the fact of change of contractors from time to time.
2. The case of the petitioners in nutshell is that all the petitioners were appointed through notification published in a newspaper, on contract/outsourcing basis during May, 2019 as High Skilled, Skilled and Un-skilled labourers to work at Electrical High Tension (EHT) 132/33 KV Sub-Station, Vinjamuru. More particularly to operate and maintain the said Sub-Station, M/s.Sterling and Wilson Pvt., Ltd., was given contract for carrying out operation work along with construction package for a period of 2 years at 132/33 KV Sub-Station, Vinjamuru by engaging 4 number of Diploma in Electrical Engineers and 4 numbers of ITI Electrician Trade and 3 numbers of un-skilled persons for the period from 01.06.2019 till 31.05.2021.
3. While the things stood thus, in recent past, vide letter dated 20.11.2020, the manning contract of contractor for 132/33 KV Sub-Station, Vinjamuru got terminated with effect from 23.11.2020 on the ground that the contractor committed irregularities in appointing Contract/Outsourcing Workmen for respective Sub-Stations. Before terminating the contract itself, the contractor denied the irregularities in appointments. But they were allowed to continue in attending maintenance of 132/33 KV Sub-Station, Vinjamuru. In spite of the fact that the contract is subsisting till 31.05.2021 to continue in their respective posts, they were thrown out forcibly on 23.11.2020 after completion of 10 am shift with a view to replace the petitioners from another set of contract employees. Factually, even after completion of 31.05.2021, the respondents have no right to terminate their services, mechanically, except for proven misconduct. On 26.11.2020, all the petitioners brought their grievance to the notice of respondent No.3, but, they did not give any acknowledgment. In continuation of earlier representation, the petitioners submitted elaborate representation dated 01.12.2020, and brought their grievance to the notice of respondent No.1, requested to do justice, but the same did not yield any fruitful result.
4. The main grounds urged by the petitioners are as follows:
(b) The very thought of replacing the petitioners with another set of contract/outsourcing workmen is illegal and contrary to the principle laid down by the Apex Court in “State of Haryana v. Piara Singh” (referred supra).
(c) The petitioners further contended that the services of contract employees ca
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.