IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
U. DURGA PRASAD RAO, J.
Tokala Manikantham – Appellant
Versus
The Union of India – Respondent
Writ Petition No.5913 of 2020
Decided on : 15-02-2021
Constitution of India, 1950 – Article 300-A – Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 – Sections 3, 6 – Writ of mandamus – Land Acquisition – Petitioners pray for a writ of mandamus declaring the land acquisition proceedings initiated under the Notification S.O. issued under Section 3(1) and the Declaration S.O. issued under Section 6(1) of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 in so far as the lands of the petitioners in Sy.No.126/7 of Loya and Sy.No.153/3 of Munagapadu villages of G.Konduru Mandal, Krishna District, as illegal, arbitrary and violative of the provisions of Article 300-A of the Constitution of India and consequently set aside the same and pass such other orders as deemed fit in the circumstances of the case.
Finding of court: Respondent produced copies of returned registered postal covers which contain an endorsement that since the addressees were residing in Gaddu Manugu village, the registered letters were redirected to G.Konduru. – Further, the copies of notices would show that they were sent to respondents 4 and 5 and as they refused to receive, the same were affixed to the door. – Thus on a conspectus of facts and documents, Court is unable to accept the contention of the petitioners that they were not served with the copies of Section 3(1) notification so as to submit their objections. – The other contention of the petitioners that the original alignment as per peg marks did not include their land and later on the pressure of some influential persons, alignment was changed to include the lands of the petitioners also do not hold much water for the reason that the alignment of pipeline will be approved by the Central Government taking into consideration various aspects. – Admittedly, the project is at the verge of completion except the stretch where the petitioners’ lands are located. – Having regard to the involvement of larger public interest, as the avowed object of the project is to transport petroleum and other related minerals from Paradeep to Hyderabad, the notifications under Section 3 and 6 of the PMP Act cannot be set aside. – The decision cited by them will not improve their case. – Thus, the petitioners are entitled to only compensation if they were not already paid.
Result: Writ Petition Disposed of
ORDER:
The petitioners pray for a writ of mandamus declaring the land acquisition proceedings initiated under the Notification S.O.No.2098 dated 06.09.2017 issued under Section 3(1) and the Declaration S.O.No.637 dated 11.04.2018 issued under Section 6(1) of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 (for short, ‘the PMP Act’) in so far as the lands of the petitioners in Sy.No.126/7 of Loya and Sy.No.153/3 of Munagapadu villages of G.Konduru Mandal, Krishna District, as illegal, arbitrary and violative of the provisions of Article 300-A of the Constitution of India and consequently set aside the same and pass such other orders as deemed fit in the circumstances of the case.
2. The petitioners’ case succinctly is thus:
(b) On further enquiry, the petitioners came to know that the Paradeep-Hyderabad Pipeline project was initiated in the year 2016 and the respondents have fixed Peg markings which fall under the project pipeline alignment. In the year 2016, the lands of the petitioners did not fall in the pipeline alignment. The land acquisition proceedings were completed in all the Mandals except G.Konduru Mandal. At that time, due to interference of vested interests, the land acquisition proceedings in G.Konduru Mandal were stopped for the purpose of changing the alignment of the pipeline to suit the needs of the vested interest and to exclude their lands from the alignment. Originally the pipeline alignment was going in straight line between G.Konduru Village and IOCL Terminal at Kavuluru Village. However, after changing the pipeline alignment, Section 3(1) notification under the PMP Act was issued on 06.09.2017 proposing to acquire the lands of the petitioners and some others with changed alignment. The changed alignment is very much expensive as it took a long deep curve making the project much costlier. In the process, the respondents have given a go by to the mandatory procedure contemplated under the PMP Act and the PMP Rules. A duty is cast on the 2nd respondent, who is the competent authority, to cause public notification inviting the objections and consider the same and pass appropriate order. However, nothing was done in that regard. Hence, the impugned notificati
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.