IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
M.VENKATA RAMANA
The State of A.P. - Appellant
Versus
P.N.Srinivasulu Reddy - Respondent
APPEAL SUIT No.15 of 2009
Decided On : 01-03-2021
Evidence Act – Section 101 – Code of Civil Procedure, 1908 – Section 96 – Agreement – This is a regular appeal preferred under Section 96 CPC against the decree and judgment in O.S. of the Court of the learned Senior Civil Judge – Respondent laid a claim against the appellants for Rs.5,60,564.96 ps. with future interest at 24% p.a. from the date of the suit till realisation and for costs. – Dispute is relating to a work contract which was in respect of special repairs to the road viz., K.M.13/4 to 17/4 via Gandavaram, Peddaputhedu and Peyyalapalem – An agreement was entered into between the respondent and the appellants when the respondent became lowest tenderer for value of Rs.10,73,702/-for the estimated contract value of Rs.9,79,771/-at 9.59% excess, based on SSR 97-1999. – It was accepted by the 2nd respondent. – The work was to be completed within six months of handing over the site and as per the work agreement, the site was handed over on 19.09.1998 on account of which the work was to be completed within six months therefrom by 18.03.1999. – Breach of this contract is alleged by both the parties in performance of the terms and conditions thereunder which has lead to this action by the respondent against the appellants. – Whether the respondent is entitled for damages as claimed and if the appellants committed breach of contract in question
Finding of court: Counsel for the respondent also contended that grounds have to be raised in the memorandum of appeal and that the learned Government Pleader addressed arguments without raising such grounds. – Conservator of Forests Nizamabad Circle, Nizamabad and Ors. vs. K. Sridhara Reddy, AIR 1968 AP 198 is relied on by the learned counsel for the respondent in this respect. – When the appeal is presented in terms of Section 96 CPC and when this Court is considering this appeal not only as a last Court of fact but also in terms of law, it is open for the appellants to canvass on all such issues relating to disputed facts and law. – Therefore, when a re-appraisal of the material is sought on behalf of the appellants, the same cannot in any manner be injuncted to. – Respondent is entitled for interest on the amount arrived at as stated above from the date of the decree till realisation at 9% p.a.
Result: Appeal Is Allowed In Part
JUDGMENT :
This is a regular appeal preferred under Section 96 CPC against the decree and judgment in O.S.No.31 of 2005 of the Court of the learned Senior Civil Judge, Kovur,
Nellore District.
2. The defendants are the appellants. The plaintiff is the respondent.
3. The respondent laid a claim against the appellants for Rs.5,60,564.96 ps. with future interest at 24% p.a. from the date of the suit till realisation and for costs.
4. This dispute is relating to a work contract which was in respect of special repairs to the road viz., K.M.13/4 to 17/4 via Gandavaram, Peddaputhedu and Peyyalapalem. An agreement was entered into between the respondent and the appellants when the respondent became lowest tenderer for value of Rs.10,73,702/-for the estimated contract value of Rs.9,79,771/-at 9.59% excess, based on SSR 97-1999. It was accepted by the 2nd respondent. The work was to be completed within six months of handing over the site and as per the work agreement, the site was handed over on 19.09.1998 on account of which the work was to be completed within six months therefrom by 18.03.1999. Breach of this contract is alleged by both the parties in performance of the terms and conditions thereunder which has lead to this action by the respondent against the appellants.
5. The specific case set up by the respondent in the plaint was as under:
(b) Seven claims in all were raised by the respondent on account of the interest payable for delayed payments even though the appellants were required to make such payments fortnightly or monthly of submission of each bill, at the rate of 24% p.a. Second claim pertains to the amount withheld and pooled by the appellants of Rs.14,350/-towards further security deposit which was due for payment on 01.12.1999 on which he is also entitled for interest at 24% p.a. from 01.12.1999 to 31.03.2005 of Rs.14,063/-and in all Rs.28,413/-. Third claim is in respect of Rs.59,672/-that was not paid to the respondent for the work done, which is payable with interest at 24% p.a. and thus in all Rs.1,10,989-92 ps. Claim no.4 is in respect of overheads for establishment, salaries etc., in maintaining site office as well as regular office with interest thereon, in all Rs.1,41,504/-till date of the suit. Fifth claim is in respect of anticipated loss of profit at the rate of Rs.1,41,504/-computed at the rate of 15% on the total value of the contract. Sixth claim relates to retention of earnest money deposit liable to be repaid with interest and in all Rs.43,000/-. Seventh claim is for Rs.50,000/-for unjust determination of the contract.
(c)Thus, the respondent claimed the relief against the appellants and to pass a decree in his favour.
6. The 3rd appellant filed a written statement opposing the claim of the respondent adopted by the appellants 1 and 2.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.