IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
RAVI NATH TILHARI, J.
E.V. Rama Rao – Petitioner
Versus
The State of Andhra Pradesh – Respondent
Writ Petition No. 25816 of 2022
Decided On : 16-08-2022
Constitution of India, 1949 – Article 226 – A.P. Municipal Corporation Act, 1965 – Section 452 – A.P. Metropolitan Regional and Urban Development Authority Act, 2016 – A.P. Building Rules, 2017 – Rule 3 – Doctrine of Fairness – Power of High Court to issue Certain Writs – Learned counsel for petitioner learned GP for Municipal Administration representing respondent Sri G. Naresh Kumar, representing learned counsel for respondents – Held, Respondent shall proceed to pass fresh orders in accordance with law after taking into consideration petitioner’s explanation submitted – It shall be open to petitioner to file additional reply to notice provisional order additional reply is filed same shall also be considered by concerned authority in accordance with law – Writ Petition is allowed.
JUDGMENT :
RAVI NATH TILHARI, J.
1. Heard Sri P. Rajasekhar, learned counsel for the petitioner, learned GP for Municipal Administration, representing respondent No. 1 and Sri G. Naresh Kumar, representing Sri M. Manohara Reddy, learned counsel for respondents No. 2 and 3.
2. With the consent of the learned counsels for the parties, the writ petition is being decided at the admission stage without calling for counter affidavit.
3. This writ petition has been filed under Article 226 of the Constitution of India for the following reliefs:
4. Sri P. Rajasekhar, learned counsel for the petitioner, submits that the petitioner is the absolute owner and is in possession of house site admeasuring 1050 sq. yards covered by D. No. 23B-5-2/1 situated in Edaravari street, Revenue Ward No. 26, RR Peta, Eluru, West Godavari District. Pursuant to the petitioner’s application dated 10.10.2018, the 2nd respondent granted building permission vide Permit No. 1075/0339/B/ELR/RRPet/2018, dated 30.10.2018 for construction of G+5 floors and though the petitioner raised only G+4 floors but as per the sanctioned plan. The 2nd respondent issued a provisional order/notice under Section 452 (1) and 461 (1) of A.P. Municipal Corporation Act, 1965, (in short ‘MC Act 1965’) and under sections 86, 89 (1&2), 90(1) of A.P. Metropolitan Regional and Urban Development Authority Act, 2016, which Act of 2016, according to the learned counsel for the petitioner has no application, giving details of the deviations/violations identified in the tabular form and asking the petitioner to submit reply as to why the deviations/violations could not be removed/altered or pulled down within specified time, failing which, it will be treated as a continuous and intentional offence and further action will be taken as per the provisions mentioned in the provisional order.
5. The petitioner submitted reply dated 16.07.2021, Ex.P3, acknowledging the show cause notice/provisional order, and submitting that due to some ‘Vastu’ complaints there is some deviation in the construction and requested in effect and substance that as per the Government norms and the regularization scheme, the petitioner is willing to pay for regularization of such deviations. The 2nd respondent through its Commissioner passed the impugned order dated 12.08.2022, Ex.P5, confirming the provisional order. Challenging which, the present writ petition is filed.
6. Sri P. Rajasekhar, learned counsel for the petitioner, submits that though the petitioner filed reply to the show cause notice/provisional order, but in the impugned order, in the first paragraph, it is incorrectly mentioned that the petitioner did not submit any reply to the show cause notice, whereas in the last paragraph, it has been mentioned that the reply given is not satisfactory, which as such contains contradictory statements. He further submits that the petitioner’s reply, in fact, has not been considered, in as much as the petitioner’s prayer for regularization of deviations shown in the show cause notice/provisional order has not been considered at all, but the order merely states that the reply given is not satisfactory which is in fact no consideration and frustrates the purpose of giving the notice and filing of reply.
7. Sri P. Rajasekhar further submits that the deviations as mentioned in the provisional order da
ACES, Hyderabad vs. Municipal Corporation of Hyderabad
The main legal point established in the judgment is that unauthorized construction exceeding the permissible limit cannot be regularized under the Act of 2016.
The judgment establishes the principle that unauthorised constructions cannot be regularized under the amended provisions of the Acts. It emphasizes the need to prevent illegal and unauthorized const....
A person responsible for unauthorized construction has no right to reconstruct the same after demolition and then apply for regularization.
A satisfactory explanation offered by the owner of an unauthorized construction must be considered before proceeding with demolition, and demolition should not be resorted to if the deviations are mi....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.