ANDHRA PRADESH HIGH COURT AT AMARAVATI
Subba Reddy Satti, J.
Dr. Daggubati Venkateswara Rao – Appellant
Versus
Government of India, Ministry of Road And Transport, Rep. By Its Secretary, Transport Bhavan, Sansad Marg, New Delhi ? 110001 & Ors. – Respondents
Writ Petition No. 993 of 2023
Decided On : 12-01-2023
National Highways Act - Writ Petition - The court directed the respondent to follow the procedure under Section 3(C) of the National Highways Act and consider the objections of the petitioner by providing a personal hearing.
Fact of the Case:
The petitioner filed a writ petition seeking a Writ of Mandamus to declare the inaction of the respondents in not considering the petitioner's objections under Section 3(C) of the National Highways Act as illegal and to direct the respondents to consider the objections.
Finding of the Court:
The court disposed of the writ petition with a direction to the 3rd respondent to follow the procedure under Section 3(C) of the Act and consider the objections of the petitioner by providing a personal hearing.
Issues: Inaction of respondents in considering petitioner's objections under Section 3(C) of the National Highways Act.
Ratio Decidendi: The court emphasized the need for the respondent authorities to follow the procedure under the National Highways Act and consider the objections of the petitioner before taking further action.
Final Decision: The writ petition was disposed of with a direction to the 3rd respondent to follow the procedure under Section 3(C) of the National Highways Act and consider the objections of the petitioner by providing a personal hearing.
JUDGMENT
Subba Reddy Satti, J. - This writ petition is filed seeking the following relief:
'to issue a Writ, order or direction more particularly one in the nature of Writ of Mandamus declaring the action of the respondents 2 and 3 in not taking action on the petitioner?s objections dated 18.11.2022 filed as under Section 3(C) of National Highwaus Act is illegal, irregular, arbitrary violative of provisions of National Highways Act, 1956 and consequently direct the respondents 2 and 3 to consider and decide the petitioner?s objections dated 18.11.2022 filed as under Section 3(C) of National Highways Act to the notification issued by the respondents as under Section 3(A) of National Highways Act..'.
2. The 3rd respondent issued notification under Section 3(A) of National Highway Act in "Andhra Prabha? newspaper dated 11.11.2022. Petitioner?s land is shown in the notification. The purpose of acquisition is for the expansion and widening of vadarevu to nakerekal National Highway No.167A. Pursuant to the above notification, the petitioner submitted objections on 18.11.2022 to the 3rd respondent within 21 days as mandated.
3. The grievance of the petitioner is that without considering the objections, the authorities are proceeding further. According to the petitioner, the respondent authorities are erecting survey stone in his land. Hence, the writ petition.
4. Heard learned counsel for the petitioner and learned Government Pleader for Revenue.
5. Learned Government Pleader would submit that the notification dated 11.11.2022 was issued under Section 3(A) of National Highway Act. The petitioner submitted explanation/objection on 18.11.2022. The Joint Collector, RB & R, Bapatla was appointed as CALA vide Gazette SO 4066(E) dated 30.08.2022. Section 3(C) is under process. The respondent authority will strictly follow the procedure under Sec 3(c) of the Act and thereafter issue declaration under Section 3(D), 3(G) etc.
6. In view of the instructions given by the Deputy Executive Engineer, (R & B) NH Sub Division, Guntur to the learned Government Pleader passed on to this Court, the Writ Petition is disposed of with a direction to the 3rd respondent to follow the procedure contemplated under Section 3(C) of Act and consider the objections of the petitioner by providing personal hearing. No order as to costs. It is needless to observe that without following the procedure under National Highways Act, the respondent authorities shall not dispossess the petitioner from his land.
Miscellaneous petitions, if any pending, in this case, shall stand closed.
AI
Authorities under the National Highways Act are not required to consider objections submitted prior to formal notification when objections are not filed within the prescribed timeframe.
The court emphasizes the importance of public projects and the minimal impact on the petitioner's land due to the acquisition, while ruling that the procedure under Section 3-C was followed.
Absence of any reference to a plan in the Notification and infact non-availability of any plan linked to the notification, fortifies argument that the description of the land under acquisition in the....
Notifications must meet the statutory requirements and furnish all the details in the notification issued at the first instance. Vague notifications may not be quashed, and the court may direct the r....
The court emphasized the importance of timely filing of objections in land acquisition proceedings and the limited scope of judicial review in such matters, particularly when the project is for publi....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.