2013 Supreme(Kar) 911
High Court of Karnataka
S. ABDUL NAZEER, J.
Karnataka Road Development Corporation Limited
Versus
Mallaradhya & Another
Writ Petition No. 16967 of 2013 (LA-RES)
Decided on: 17-09-2013
Subject
Land Acquisition - Compensation
Act Referred
CONSTITUTION OF INDIA : Art.14
LAND ACQUISITION ACT : S.4(1), S.18(1), S.6(1), S.20(b), S.20(c), S.19(b), S.50(2), S.50
Headnote
Advocate Appeared:
For the Petitioner:B.B. Bajentri, Advocate.
For the Respondents:R1, G. Praseeth, Advocate, R2, R.B. Sathyanarayana Singh, HCGP.
1. In this case, the petitioner has called in question the validity of the judgment and award dated 31.03.2011 in LAC No.58/2007 on the file of the Civil Judge (Sr.Dn.) Maddur, whereby the Court below has enhanced the compensation from Rs.17/- per sq.ft. to Rs.250/- per sq.ft.
2. Petitioner is a Corporation established under the Indian Companies Act, 1956. It is a State Government undertaking. It was established with the object of executing the project relating to road development in the State of Karnataka. It takes up the projects from Public Works and Inland Water Transport Departments for the construction of roads and expansion projects.
3. The Deputy Commissioner of Mandya District had issued notification dated 17.01.2005 under Section 4(1) of the Land Acquisition Act, 1894 (for short 'the Act') for acquisition of land at Gejjalagere village, Maddur taluk, Mandya District for widening of the Bangalore - Mysore State Highway No.17. This was followed by a final notification dated 16.01.2006. The Land Acquisition Officer determined the compensation at Rs.17/- per sq.ft. Being dissatisfied with the award, the first respondent filed an application (Annexure 'B') under Section 18 (1) of the Act for determining higher market value. The second respondent referred the matter to the Civil Court on 22.06.2007. The Civil Court registered the reference as LAC No.58/2007. It has enhanced the compensation at Rs.250/- per sq.ft.
4. Learned Counsel for the petitioner would contend that the lands have been acquired for the widening of the State Highway No.17. The notification issued under Sections 4(1) and 6(1) of the Act shows that the petitioner is the executing agency of the work. The petitioner is allocated with the funds by the State Government. The compensation amount is paid through the petitioner being the executing agency. Thus, the petitioner is interested in the reference. The order of reference does not contain the name of the petitioner. Petitioner had no notice of the proceedings pending before the Court. The name of the petitioner finds a place in the award as respondent No.1. Since the petitioner is interested person in the reference, the Land Acquisition Officer ought to have included its name in the reference and the reference Court ought to have issued the notice under Section 20(b) and (c) of the Act to the petitioner.
5. On the other hand, learned Counsel appearing for the respondents have sought to justify the impugned award.
6. I have carefully considered the arguments of the learned Counsel made at the Bar and perused the records of the trial Court.
7. As stated earlier, the petitioner is a State Government undertaking. It was established mainly with the object of executing the project relating to development of roads in the State of Karnataka. The State Government allocates funds to the petitioner for executing the project of construction or extension of roads. The compensation is paid to the land owners through the petitioner.
8. The notifications issued by the Deputy Commissioner proposing to acquire lands shows that the acquisition is for the purpose of widening of State Highway No.17 by the petitioner herein. The relevant portion of the notification is as under:
(“Language”)
9. The Land Acquisition Officer passed award determining the compensation at Rs.17/- per sq.ft. The 1st respondent filed an application as per Annexure 'B' under Section 18(1) seeking reference for determination of higher compensation. In the application, the name of the petitioner has not been included. The names of the second respondent and the Executive Engineer of the Public Works Department are found in the application. On receipt of the reference, the court below registered the case as LAC.No.58/2007. The order sheet does not contain the name of the petitioner. It contains the name of Public Works Department, Mandya and Special Land Acquisition Officer, Mandya. The court below issued notice to the parties on 13.07.2008. The file does no