IN THE HIGH COURT OF KARNATAKA
Sachin shankar Magadum, J.
Godolphine India Private Limited - Appellant
Versus
UM Projects LLP - Respondent
Writ Petition No. 10281 of 2022(GM-CPC)
Decided On : 01-07-2022
Order Attachment - Arbitration and Conciliation Act, 1996 - Section 9, Order XXI Rule 22 of CPC - The court discussed the provisions of Section 9 of the Arbitration and Conciliation Act, 1996 and Order XXI Rule 22 of the Civil Procedure Code. It interpreted the scope of Section 9(3) of the Act and its applicability once an application under Section 9(1) has been 'entertained' by the court. The court also considered the implications of the amendment to Section 9 of the Act, 1996 and its impact on the execution proceedings. The judgment highlighted the practical approach adopted by the Apex Court in Arcelor Mittal Nippon Steel India Ltd. Vs. Essar Bulk Terminal Limited, (2022) 1 SCC 712, in interpreting the term 'entertain' under Section 9(3) of the Act, 1996.
Fact of the Case:
The petitioner filed a writ petition challenging the order of the Executing Court attaching their bank account based on an order passed under Section 9 of the Arbitration and Conciliation Act, 1996. The petitioner contended that the impugned order violated principles of natural justice and that the remedy of the parties lay before the Arbitration Tribunal.
Finding of the Court:
The court found that the impugned order did not contravene the amended provisions of Rule 22(1) of Order XXI of CPC and that the restriction under Section 9(3) of the Act, 1996 did not apply once an application under Section 9(1) had been 'entertained' by the court. The court dismissed the writ petition, allowing the execution proceedings to continue.
Issues: The issues involved the violation of principles of natural justice in the impugned order, the applicability of the amended provisions of Rule 22(1) of Order XXI of CPC, and the interpretation of Section 9(3) of the Act, 1996 in light of the practical approach adopted by the Apex Court.
Ratio Decidendi: The court's decision was based on the interpretation of Section 9(3) of the Act, 1996 and the practical approach adopted by the Apex Court in Arcelor Mittal Nippon Steel India Ltd. Vs. Essar Bulk Terminal Limited, (2022) 1 SCC 712, in defining the term 'entertain' under Section 9(3) of the Act, 1996.
Final Decision: The writ petition was dismissed, allowing the execution proceedings to continue.
ORDER
1. The captioned writ petition is filed by the judgment debtor feeling aggrieved by order dated 22.4.2022 passed by Executing Court thereby attaching the Bank Account of the petitioner to an extent of Rs.97,58,580/-.
2. The respondent-decree holder filed an application under Section 9 of Arbitration and conciliation Act, 1996 (for short "Act, 1996") before the Commercial Court seeking a direction against the present petitioner to pay outstanding rent and maintenance charges amounting to Rs.1,93,41,675/-. The said application was contested by the petitioner herein and the Commercial Court by order dated 4.3.2022 allowed the application.
3. Feeling aggrieved by the said order, the petitioner herein preferred a Commercial Appeal in Commercial Appeal No.140/2022. The Division Bench of this Court declined to entertain the grounds urged in the appeal and consequently, dismissed the appeal and confirmed the order passed by the Commercial Court passed under Section 9 of the Act, 1996. The Division Bench of this Court has also observed in its order that the liability of the petitioner to pay admitted rent in terms of the lease deed dated 10.6.2020 has no nexus or connection whatsoever to the permission granted by the Commercial Court to the present petitioner to deposit 40% of the monthly sums pending adjudication in AA.127/2021.
4. Based on the order of the Commercial Court passed under Section 9 and the order passed in Commercial Appeal, the respondent-decree holder has filed the present execution proceedings. The executing Court on an application filed by the respondent-decree holder has passed the impugned order thereby attaching the account of the petitioner herein.
5. Sri. Srivasta, learned Senior Counsel appearing for the petitioner reiterating the grounds urged in the writ petition would vehemently argue and contend that the impugned order under challenge is passed in gross violation of principles of natural justice. Referring to the provisions of Order XXI Rule 22 of CPC, the learned counsel contended that a show-cause should be issued where an application for execution is levied more than two years after the date of decree. Referring to Order 21 Rule 22 (3) of CPC, he would point out that the show-cause notice has to be issued if the material on record indicated that there is substantial injury sustained by the judgment debtor.
The second limb of argument canvassed by the learned counsel is that, the remedy of the parties lies before the Arbitration Tribunal and therefore, the respondent-decree holder cannot file an execution to recover the amount which is the subject matter of arbitration before the commencement of the arbitral proceedings.
6. After the matter was heard for some time, the learned Senior Counsel for the petitioner sought for short accommodation and at his request, the matter was adjourned and in the interregnum the petitioner sought for amendment to raise additional grounds. By way of proposed amendment, the petitioner has raised additional grounds inter alia contending that there is an amendment to Section 9 of the Act, 1996, wherein two further sub-Sections have been introduced. Referring to this amended sections, it is submitted by the learned counsel that the Executing Court has virtually misinterpreted the provisions of Section 9 prior to amendment which was inapplicable to the present case on hand. He would sum up his arguments by contending that failure to issue notice violates the principal tenet of natural justice.
7. Per contra, the learned counsel appearing for the respondents repelling the contentions canvassed by learned Senior Counsel appearing for the petitioner would however contend that the issue in regard to whether an order passed under Section 9 assumes the status of a decree is dealt by the Apex Court in catena of judgments and the said issue is no more res integra. Placing reliance on the judgment rendered by this Apex Court in the case of State of Karantaka .vs. Vishwabharathi House Build
Arcelor Mittal Nippon Steel India Ltd. vs. Essar Bulk Terminal Limited
The main legal point established in the judgment is the interpretation of Section 9(3) of the Arbitration and Conciliation Act, 1996 and its applicability once an application under Section 9(1) has b....
Commercial Courts are empowered to execute arbitral awards under the Arbitration and Conciliation Act, reaffirming the intent of the Commercial Courts Act for speedy resolution of commercial disputes....
The Commercial Courts Act, 2015 grants jurisdiction to Commercial Courts for executing arbitral awards related to commercial disputes, emphasizing expedited resolution.
An application under Section 9 of the Arbitration and Conciliation Act can be maintained post-arbitral award until satisfaction of the award, but the court retains discretion on whether to entertain ....
Financial transactions resembling financier dealings qualify as commercial disputes under Commercial Courts Act, requiring execution before Commercial Court.
Parties should address delays in court proceedings at the appropriate court level before seeking intervention from higher courts.
The court held that under the Arbitration and Conciliation Act, only the court that entertained the initial arbitration application has jurisdiction to enforce the award, reinforcing exclusive enforc....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.