IN THE HIGH COURT OF KARNATAKA AT BENGALURU
M.I. Arun, J.
H.S. Abdul Riyaz Basha S/o H.P. Abdul Shakur - Petitioner
Versus
The State of Karnataka Rep. by Its Principal Secretary Industries and Commerce And Ors. – Respondents
Writ Petition No.26117 of 2022 (LA-KIADB)
Decided On : 17-01-2024
Acquisition Process - Karnataka Industrial Areas Development Act, 1966 - The court set aside the preliminary notification for land acquisition due to the unreasonable delay of 14 years in issuing the final notification, emphasizing the need for proper study before land acquisition and the inconvenience caused to landowners by the prolonged acquisition process.
Fact of the Case:
The petitioner filed a writ petition to set aside the preliminary notification for land acquisition, as the final notification had not been issued and no award had been passed for the said lands after 14 years.
Finding of the Court:
The court found that the delay of 14 years in issuing the final notification was unreasonable and set aside the preliminary notification for land acquisition.
Issues: Unreasonable delay in issuing final notification for land acquisition under the Karnataka Industrial Areas Development Act, 1966.
Ratio Decidendi: The court emphasized the need for proper study before land acquisition, the inconvenience caused to landowners by the prolonged acquisition process, and the lapse of the acquisition process due to the unreasonable delay in issuing the final notification.
Final Decision: The preliminary notification for land acquisition was set aside, and the writ petition was disposed of accordingly.
ORDER :
1. In the instant case, the preliminary notification was issued on 11.12.2009 acquiring certain lands which include 1 acre 20 guntas of land in Survey No.236 and 2 acres 27 guntas of land in Survey No.237/1 of Kondareddypalli village, Kasaba Hobli, Bagepalli Taluk, Chikkaballapura District, which the petitioner contends that it belongs to him. However, the final notification has not been issued and award has also not been passed in respect of the said lands. Hence, the present writ petition is filed with a prayer to set aside the preliminary notification.
2. The fact that the preliminary notification was issued in the year 2009 and no final notification has been issued thereafter is not disputed by the respondents.
3. The acquisition is being done as per the provisions of the Karnataka Industrial Areas Development Act, 1966 ('the Act' for short). Though the Act does not specify the time within which a final notification has to be issued, the respondents are expected to issue a final notification within a reasonable time and the delay of 14 years cannot be considered reasonable. As already stated above, even till today, after lapse of 14 years, the final notification is not issued.
4. The Karnataka Industrial Areas Development Act, 1966 is enacted to make provision for the orderly establishment and development of industries in suitable areas in the State. To achieve this object, the Karnataka Industrial Areas Development Board is established and it is required to specify areas for industrial development and make available lands therein for establishment of industries. The Board in discharge of its statutory functions has to first determine the area that is required for establishment of industries after making the necessary study and only thereafter should venture to acquire the lands required. It should not indulge in notifying the lands which are not required. It is seen on many occasions, in recent orders, the Board in its preliminary notification seeking to acquire vast tracts of land and in the final notification end up acquiring less than 50% of the original lands proposed. This shows that proper study is not conducted by the Board before venturing into acquiring the lands. Further, after issuance of preliminary notification, if the acquisition process is not completed at a faster pace, it will cause huge inconvenience to the persons whose lands are notified by way of preliminary notification. It will prevent them from exploiting the potential of the land to its fullest extent, as passing of preliminary notification is a deterrent for them to develop the lands as desired by them nor will purchasers come forward to purchase the said land.
5. In the instant case, as more than 14 years have lapsed after issuance of the preliminary notification and nothing has been done in pursuance of the same to complete the acquisition formalities, it has to be held that the acquisition process has lapsed and the preliminary notification is liable to be struck down. It is needless to state that setting aside the preliminary notification will not preclude the respondent/KIADB from initiating fresh acquisition process in accordance with law, if it so desires.
6. Hence, the following:
The preliminary notification bearing No.CI 532 SPQ 2009 dated 11.12.2009 issued by respondent no.1 under Section 28(1) of the Act is set aside insofar as it relates to the lands of the petitioner is concerned.
The writ petition stands disposed of accordingly.
Unreasonable delay in issuing the final notification for land acquisition can lead to the lapse of the acquisition process and the setting aside of the preliminary notification.
Inordinate delay of 14 years in land acquisition invalidates the process, necessitating quashing of prior notifications and ensuring entitlement to compensation under the 2013 Act.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.