IN THE HIGH COURT OF KARNATAKA
Krishna S.Dixit, J.
H. \N. Pruthivinarayan – Appellant
Versus
Managing Director, Ksrtc – Respondent
Writ Petition No. 2940 of 2023 (GM-TEN)
Decided On : 04-10-2023
FORCE MAJEURE - TENDER PROCESS - CONSTITUTION OF INDIA, ARTICLE 39(b) and (c); COVID-19 NOTIFICATIONS DATED 19/2/2020 AND 13/5/2020; ARBITRATION ACT - The court examined the implications of force majeure due to the COVID-19 pandemic on the contractual obligations of the petitioner. It interpreted the relevant notifications and case law to conclude that the pandemic extended the contract period, thus affecting the validity of the tender process initiated by the respondents. The court emphasized the need for a balance between competing interests and the importance of arbitration in resolving disputes arising from the contract.
Fact of the Case:
The petitioner, an ongoing contractor, challenged a tender notification issued by the KSRTC for commercial complexes, arguing that the COVID-19 pandemic extended the contract period and that the tender process violated his rights under the existing contract.
Finding of the Court:
The court found merit in the petitioner's argument regarding the extension of the contract period due to the pandemic. It acknowledged the impact of COVID-19 on commercial activities and recognized the need for the tender process to respect the ongoing arbitration regarding the contract.
Issues: Whether the COVID-19 pandemic constituted a force majeure event that extended the contract period; whether the tender process could proceed while arbitration was ongoing; and whether the petitioner had a legitimate expectation of contract renewal.
Ratio Decidendi: The court held that the pandemic was a force majeure event that justified an extension of the contract period. It distinguished between the extension of the contract due to force majeure and the renewal of the contract, emphasizing that the latter was subject to arbitration. The court also highlighted the importance of judicial review in tender processes, particularly when public interest is at stake.
Final Decision: The court partially allowed the writ petition, ruling that the impugned tender notification should not be given effect until the arbitration proceedings were concluded. It ordered that the premises already allotted to third parties remain undisturbed while ensuring that the petitioner could access unlet premises upon payment of the required fees.
JUDGMENT
1. Petitioner, claiming to be an ongoing contractor, is tapping the writ jurisdiction of this Court for assailing the Notification dtd. 10/1/2023 issued by the 2nd respondent at Annexure-G calling for e-Tender inter alia in respect of commercial complexes in the KSRTC bus stand at Hassan. The habendum of the said tender in colloquial reads as under:

2. Learned Senior Advocate appearing for the Petitioner seeks to falter the tender in question on the ground of force majeure namely COVID-19 Pandemic; the two Central Government Notifications dtd. 19/2/2020 and 13/5/2020 have the effect of elongating the twelve year contract period pro tanto; there is lapse on the part of respondents in discharging certain contractual obligations briefly stated in para 5 of the petition, despite representations; Petitioner had filed a few cases such as W.P.No.30258/2018, C.M.P No.233/2018, W.P.No.8992/2021, W.P.No.16705/2022 (respondents W.A.No.27/2023); bifurcation of subject matter of tender is unsustainable; impugned action defeats legitimate expectation; Petitioner has got right of extension of the contract; there being an ongoing arbitration, without its culmination into an award, the impugned tender could not have been flouted. The counsel relied upon certain Rulings in support of these submissions.
3. Learned Panel Counsel appearing for the Respondents resisted the Writ Petition repelling the submission made on behalf of the Petitioner. The Statement of Objections have been filed on 14/3/2023 opposing the Writ Petition; the allegations of non- performance of contractual obligations are denied; petition is misconceived, an arbitrator having been appointed; Petitioner's submission transcends the parameters fixed by the Apex Court in the CAs referred to infra; Petitioner has committed breach of contract and in any way the contract has come to an end by efflux of time; respondents being the owners of the premises in question have a greater leverage in awarding contracts and the arguable split of the items cannot be found fault with; Article 39(b) and (c) of the Constitution would support such a split; matter having ultimately gone in C.A.Nos.3625 and 3623-3624/2023, the observations made by the Apex Court in its order dtd. 8/5/2023 are pressed into service. The Panel Counsel cited certain Rulings in support of his contentions.
4. Having heard the learned counsel for the parties and having perused the Petition papers, this court grants partial indulgence in the matter for the following reasons:
(b) Let me examine the very concept of force majeure. McCardie J. in Lebeaupin v. Crispin ([1920] 2 K.B. 714), has given an account of what is meant by "force majeure" with reference to its history:
"..
Commissioner of Central Excise vs. Srikumar Agencies
Dhanrajamal Gobindram vs. Shamji Kalidas and Co
Energy Watchdog vs. Central Electricity Regulatory Commission
The court established that the COVID-19 pandemic qualifies as a force majeure event, warranting an extension of contractual obligations, and underscored the necessity of arbitration in resolving disp....
No relief can be granted by a lower court when the issue is pending before the Supreme Court. The petitioner should seek appropriate relief from the Supreme Court.
Tender Process - Extension of period of Contract - Placed on successful bidders may be extended/repeated at sole discretion of Corporation for a further period of up to 12 months including increasing....
Public authorities must act fairly and cannot arbitrarily terminate contracts without justification, reinforcing the legitimacy of expectations within public-private partnerships.
Occurrence of commercial difficulty, inconvenience or hardship in performance of the conditions agreed to in the contract can provide no justification to wriggle out of the contractual obligations wh....
Judicial interference in the matter of tenders and contracts is limited and the court should exercise restraint in interfering with the administrative decision-making process.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.