2025 KHC 44113
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
V.SRISHANANDA, J.
Andrew Yule & Co. Ltd. - Appellant
Vs.
Smt. Asha U Suvarna W/o Udayachandra D. Suvarna - Respondent
Civil Revision Petition No. 129 of 2019
Decided On : 30-10-2025
Advocate Appeared :
For the Appellant : Sri. Manmohan P.N, Advocate
For the Respondent : Sri. Dheeraj, Advocate For Sri. Sanath Kumar Shetty K, Advocate
| Table of Content |
|---|
| 1. factual background of the case (Para 3 , 4 , 5 , 6) |
| 2. defendant's jurisdiction argument (Para 12 , 13 , 15) |
| 3. ratio on jurisdiction considerations (Para 14 , 26) |
| 4. observations on the nature of jurisdiction (Para 19 , 21 , 25) |
| 5. conclusion and directions for expedited trial (Para 30 , 31) |
ORDER :
V.SRISHANANDA, J.
Heard Sri.P.N.Manmohan, learned counsel for the revision petitioner and Sri.Dheeraj, learned counsel appearing on behalf of Sri.Sanath Kumar Shetty K., learned counsel for the respondent.
2. Defendant in O.S.No.137/2004 is the revision petitioner challenging the order passed by the II Additional Senior Civil Judge and CJM, Mangaluru on I.A.No.4 dated 14.02.2019 whereby one of the defences taken by the defendant is that the Court has no jurisdiction, was tried as preliminary issue and held against the defendant.
3. Facts of the case which are utmost necessary for disposal of the revision petition are as under:
3.1. A suit came to be filed by the plaintiff with the following prayer:
“The plaintiff therefore prays for a judgment and decree granting the following reliefs:
1. Directing the defendant to pay a sum of Rs.25,22,811-00 as morefully set out in schedule ‘A’ herebelow together with future interest thereon at 18% per annum from this date till realization.
2. Grant costs of suit.
3. Grant such other and further reliefs.
3.2. In the plaint, it is contended that plaintiff is carrying on the business under the trade name M/s. Tanvi Cement Products in Mangaluru. Plaintiff is a manufacturer of PCC Poles and Spun Pipes.
3.3. Defendant company which is a Government of India Enterprise, had placed order for supply of pre- stressed concrete poles of specified specifications as per the following purchase orders:
i. Bearing No.ESGTU/LP-2000/00113 dated 23.11.2000
ii. Bearing No.ESGTU/LP-2000/00200 dated 06.03.2001
3.4. As per the purchase order No.i, defendant had ordered for supply of 630 numbers of 9 meter long 300 kg working load pre-stressed concrete poles at the rate of Rs.1,550/- per pole besides Rs.450/- as transport and loading charges.
3.5. As per the purchase order No.ii, defendant has ordered 629 numbers of 9 meter long 300 kg working load pre-stressed concrete poles with Rs.1,550/- per pole besides Rs.450/- per pole towards the transportation and unloading charges.
3.6. Plaintiff submitted that as per the purchase orders, plaintiff at the first instance, supplied 600 numbers of pre-stressed concrete poles which had been duly taken delivery by the defendant after due inspection and tests.
3.7. Plaintiff submitted bills of a aggregate value of Rs.12,00,000/- for the supply made between the period from 24.03.2001 to 29.05.2001. However, the payments were not made by the defendant promptly as per the accepted terms of the purchase orders. The defendant made payment of Rs.3,00,000/- as against sum of Rs.12,00,000/- that too after a long delay of 16 months which is in violation of the terms of the purchase order. Balance sum of Rs.9,00,000/- remained to be unpaid. 3.8. Plaintiff had also manufactured balance PSC poles and kept ready. Plaintiff was waiting for the defendant to take the delivery of the same, but defendant failed to take the delivery of the finished concrete poles of 30 numbers in respect of the purchase order No.1.
3.9. Plaintiff has been facing serious problems for keeping finished products inasmuch as the manufactured poles were occupying large space in the staking yard and plaintiff had also invested huge sum of money for manufacturing the concrete poles.
3.10. Plaintiff further contended that there was a penalty clause of ½% for the delayed period subject to maximum of 5% per value of the undelivered portion.
3.11. It is also contended by the plaintiff that the purchase order stipulated payment of 100% payment within 30 days from the date of receipt of the manufactured poles by the defendant and plaintiff demanded the balance sum of Rs.9,00,000/- from the defendant.
3.12. Further, said sum remained unpai
A.B.C. Laminart Pvt. Ltd. v. A.P.Agencies
Swastik Gases Private Limited v. Indian Oil Corporation Limited reported
Jurisdiction in contract disputes depends on where significant acts occurred, not solely on contractual jurisdiction clauses.
The main legal point established in the judgment is the application of territorial jurisdiction under section 20 of the CPC, emphasizing the significance of the location of the contract's making and ....
The validity of the jurisdiction clause in an agreement and the determination of cause of action based on the place of goods supply and payment location.
The main legal point established in the judgment is that the issue of territorial jurisdiction can be tried as a preliminary issue under Order XIV Rule 2 of the Civil Procedure Code.
Point of Law : Recover of amount - Jurisdiction - Section 20 clearly provides that a court within whose local limits the cause of action, “wholly or in part”, arises, would have territorial jurisdict....
The main legal point established in the judgment is that parties can, by agreement, exclude the jurisdiction of one Court and the suit would lie in the Court to be agreed upon by the parties.
Point of Law : Return of plaint – Jurisdiction of Court- Work Contract - Cause of action for the institution of the suit has arisen at Raipur where the alleged contract was executed Hence Court has j....
The jurisdiction of courts in civil matters is determined by the location of payments made, as established under Section 20 of the CPC.
The issue of territorial jurisdiction is a mixed question of law and fact, and cannot be decided as a preliminary issue.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.