SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Kar) 2908

IN THE HIGH COURT OF KARNATAKA,AT DHARWAD
M.NAGAPRASANNA, J.
The Executive Engineer (Ele), Karnataka Power Transmission Corporation Ltd. – Appellant
Versus
K. S. Sukumar @ Sukumar, S/o. K. S. Mrutynujaya @ Mrutynujayappa Dvg – Respondent
Writ Petition No. 106405 Of 2024 C/W Writ Petition Nos. 105356 Of 2024 ,105483 Of 2024, 106406 Of 2024 ,106408 Of 2024 ,106515 Of 2024 , 106521 Of 2024 ,103240 Of 2025 ,103241 Of 2025 , 103242 Of 2025 ,103415 Of 2025 ,103418 Of 2025 , 103444 Of 2025 ,103461 Of 2025 ,103506 Of 2025 , 103645 Of 2025 ,103647 Of 2025 ,104103 Of 2025 , 104104 Of 2025 ,104140 Of 2025 ,104246 Of 2025 , 105196 Of 2025 ,105359 Of 2025 ,105409 Of 2025 , 105412 Of 2025 ,105413 Of 2025
Decided On : 17-11-2025

Advocates Appeared:
For the Appellant : Sri. B. S. Kamate, Adv.

Compensation claims under the Indian Telegraph Act must be filed within three years of the cause of action, with failure to adhere resulting in dismissal due to limitation.

Headnote:(A) Indian Telegraph Act, 1885 - Section 16(3) - Limitation Act, 1963 - Article 137 - Claim for compensation for use of land for a power line filed nine years post-installation found time-barred - The petitioner contended the application was ex-facie barred by limitation; the court held that constructions on the claimant's land provided constructive notice to the claimant - The District Judge issued compensation despite failure to address limitation - Error deemed legally unsustainable - Petition allowed, previous order set aside. (Paras 1-17)

(B) Jurisdiction - The court emphasized that applications under Section 16(3) are treated as applications to civil courts, thus subject to the three-year limitation under Article 137. (Paras 11-12)

Facts of the case:
The respondent filed for compensation due to a power line installation on his land without prior notice. The petitioner argued the claim was barred by limitation due to the elapsed time since the installation.

Findings of Court:
The court found the claim petition filed in 2020 for compensation was time-barred, ruling favorably for the petitioner.

Issues: Whether the District Judge erred in granting compensation despite the claim being beyond the limitation period.

Ratio Decidendi: The court recognized that the installation date constitutes constructive notice, imposing an obligation on the claimant to act promptly, invalidating the compensation grant as legally erroneous.

Result: Writ petition allowed; previous order set aside.

Table of Content
1. issue covered by precedents (Para 1)
2. construction of power line on respondent's land (Para 2)

ORDER :

M.NAGAPRASANNA, J.

1. Learned counsel appearing for the parties in unison would submit that the issue involved in the present lis stands completely covered by the judgment rendered by the Hon’ble Apex Court, which has been followed by a Co-ordinate Bench of this Court. The Co-ordinate Bench has held as follows:

“The KPTCL has filed the captioned petition assailing the order dated 17.06.2023 passed by the learned II Additional District Ballari in Misc.P.No.198/2020, thereby allowing the petition filed under Section 16(3) of the Indian Telegraph Act, 1885 (hereinafter referred to as ‘the Act’ for short) and directed the Corporation to pay compensation of Rs.51,400/- with interest at the rate of 8% p.a. from the date of petition till its realization.

2. The brief facts leading to the case are as under:

The petitioner/Corporation has drawn 400 KV High Tension Power Line with tower over the respondent’s land. This factual matrix is admitted by the Corporation. Respondent/claimant filed petition under Section 16(3) of the Act claiming compensation against the petitioner/Corporation for having utilized the land of the respondent bearing R.S.No.8/1/A of M.Lakkalahalli village. This petition is filed by the respondent/claimant alleging loss of land and crop and diminution of the land value.

3. The present petitioner/Corporation on receipt of notice filed objections and seriously disputed the claim made by the respondent. The petitioner/Corporation also contended that the claim made by the respondent/claimant is barred by limitation since the petition is filed after lapse of nine years, and there is no cause of action.

4. The respondent/claimant and the petitioner/Corporation to substantiate their respective claim let in oral and documentary evidence. The learned District Judge while answering point No.1 held that the respondent/land owner is entitled to claim compensation. Though the learned District Judge refers to an application filed under Section 5 of Limitation Act, the court was of the view that petitioner/Corporation did not issue any notice to respondent and therefore, respondent was not aware of his rights and damages. The learned District Judge has further held that the cause of action accrued to the respondent/land owner is not disclosed by the action of the petitioner/Corporation since no notices were issued to respondent and therefore, performance certificate marked at Ex.R2 indicating the date of accomplishment of installation and construction of 400KV DC line on 12.04.2012 cannot be accepted. This finding is perverse. The very installation of 400 KV DC line amount to constructive notice and therefore respondent/land owner ought to have taken to recourse through law as provided under Indian Telegraph Act.

5. This Court has carefully heard the submissions of the learned counsel for the petitioner/Corporation as well as the learned counsel for the respondent/claimant. It has also given anxious consideration to the legal principles laid down by the Hon’ble Apex Court in KERALA STATE ELECTRICITY BOARD, TRIVANDRUM V. T.P. KUNHALIUMMA, reported in (1976) 4 SCC 634. The said decision has been followed by a Coordinate Bench of this Court in W.P.No.22208/2019 and further affirmed by the Division Bench in W.A.No.100366/2022 and connected matters. This Court has also given due consideration to the judgments relied upon by the learned counsel for the respondent/claimant. The following point would arise for consideration.

“Whether the order impugned granting compensation invoking Section 16(3) of the Telegraph Act, 1885 is perverse and contrary to Ex.R2 and therefore contravenes the law declared by the Hon’ble Apex Court in the case of the Kerala Electricity Board, Trivandrum vs T.P.Kunhaliumma?”

Finding on the point:

6. Before this Hon’ble Court proceeds to delve into the substantive issue arising for consideration in the pr

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top