A.Y.SAKHARE, M.B.SHAH
State of Bihar and others – Appellant
Versus
Hindustan Construction Co. Ltd. and others – Respondent
2.On 25th April 1989, the plaintiffs were awarded a contract for construction of Icha dam across river Khadkai at village Kuju, Bihar for an amount of Rs. 39,71,31,019. The duration of the contract was for a period of 42 months, i.e. upto 24th April 1992. Clause 5 of the said contract provides for obligation on the part of the plaintiffs to furnish bank guarantee for 10% of the contract price as performance guarantee. Clause 9 of the contract casts obligation upon the plaintiffs to furnish bank guarantees against mobilisation advance given by the defendant Nos. 4 to 6. As per the plaintiffs the b