SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1996 Supreme(SC) 62

1996(1) Supreme 264
SUPREME COURT OF INDIA
A.M.Ahmadi C.J.I. and S.C. Sen, J.
State of Maharashtra & Anr. - Appellants
versus
M/s. National Construction Company,
Bombay & Anr. - Respondents
C.A.No. 1497 of 1996
(Arising out of SLP (Civil) No.13023 of 1995)
Decided on 9.1.1996

IMPORTANT POINT
When earlier suit is dismissed on technical ground it is not decided on merits and this will not operate as res-judicata in subsequent suits.

Headnote:(i) Civil Procedure Code, 1908 - Section 11 Expl. IV p Res judicata - Dismissal of suit on technical grounds - Dismissal confrmed in appeal - Decision being not on merits, would not be res judicata in a subsequent suit. (Para 8)

(ii) Civil Procedure Code, 1908 - Order 2 Rule 2 - Suit to include whole of claim - First suit filed to enforce the bank guarantee - Second suit filed to claim damages for breach of contract relating to work - Whether second suit is barred under Order 2 Rule 2 ? (No, as causes of action in both the suits are distinct). (Paras 17 & 18)

JUDGMENT

Ahmadi, CJI.-The appellants are the State of Maharastra and its Executive Engineer who was posted at the Masonry Dam Division, Nathnagar, during the relevant period. In 1967, the appellant invited tenders for Performing work on the masonry portion of the Paithan Dam on Godavari River, as part of the Jayakwadi Project, Stage-I (hereinafter called "the work"). the first respondent, M/s. National Construction Company, Bombay (hereinafter called "the contractor") submitted its tender offer for the work which was conditionally accepted by the appellants on 30.3.1967.

2. On 6.1.1968, the second respondent, the Central Bank of India (hereinafter called "the Bank"), executed performance guarantee No. 57/22 whereby it guaranteed that the contractor would faithfully conform to the terms and conditions of the contract to be entered into between the appellants and the contractor. Under the terms of the guarantee, the Bank was jointly and severally liable with the contractor for the latter s default in performance; the liability of the Bank being limited to Rs. 14.12.836/-, i.e 5% of the contract price. The guarantee was to remain in force till 3.7.1972. Soon thereafter, on 8.1.1968, the contract for commencing construction was executed. However, no work was intiated for almost two years. On 11.12.1969, the appellants gave an ultimatum to the contractor to begin work. It is alleged that instead of commencing work, the contractor abandoned the work on 19.12.1969. The appellants allege that the contractor did not respond to their repeated requests for recommencing work, forcing them to employ other agencies for completing the work. In the process, by 31.5.1972, they claim they had incurred expenses totalling Rs. 1,44,18,970.24.

3. At this stage, on 21.6.1972, the appellants filed Short Cause Suit No. 491/72 only against the Bank on the original side of the Bombay High Court praying for the recovery of Rs. 14,12,836/-, which was the amount stipulated in performance guarantee No. 57/22, with interest. It would be pertinent to note that the suit was filed before the guarantee lapsed on 3,7,1972. On 17.1.1983, the Bombay High Court dismissed the suit for non-joinder of parties, holding that the contractor was a necessary partly for deciding the issue of default and the bank s consequent liability. In appeal against this order, Appeal No. 303/83, the appellants included the contractor as a party in the cause title of the memo of appeal but the appeal was dismissed on 7.4.1983 on the very same ground. It may, however, he clarified that the contractor was not impleaded as a party by the Court s order.

4. On the same day, 7.4.1983, the appellants filed Spl. Civil Suit No. 29/83 against both the contractor and the bank in the Court of the Civil Judge (Senior Division) at Aurangabad. In this suit, the appellants claimed Rs. 1,13,27,298.16, with interest, from the contractor by way of damages for breach of contract. This was inclusive of their claim for Rs. 14,12,836/- against the bank under the performance guarantee.

5. On 28.7.1992, the learned Civil Judge dismissed the Suit holding that as the cause of action was identical to the one in the former suit, it was barred by res judicata under Explanation IV to Section 11 as also Order 2 Rule 2 of the Civil Procedure Code, 1908 (hereinafter called "the Code"). The appellants appealed against this order on the ground that the two suits were based on separate causes of action and the dismissal of the former on a technical ground could not act as a bar against the latter. On 9.7.1993, a Division Bench of the Bombay High Court by the decision impugned herein dismissed the appeal. Feeling aggrieved, the appellants have approached this Court by way of special leave.

6. We may first dispute of the plea based on Section 11, Explanation IV, of the Code. That section deals with the doctrine of res judicata and provide that any matter which might or ought to have been made a ground for defence or attack in the




























Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top