SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2001 Supreme(Bom) 825

IN THE HIGH COURT OF BOMBAY
(NAGPUR BENCH)
J.N. Patel, J.
Vishindas Bhagchand.... Petitioner.
Versus
Chairman, Maharashtra State Electricity Board others.... Respondents.
Misc. Application (Arbitration) No. 118 of 2001, decided on 7-9-2001.
Advocates appeared :
S.C. Mehadia, for petitioner.
G.E. Moharir, for respondent Nos. 2 and 3.

Headnote:ARBITRATION ACT, 1940

       Section 43- Limitation Act, 1963, Article 137- Cause of action- Where parties reached agreement after accrual of cause of action for referring the matter to the arbitration, held it will not suspend the cause of action and the running of limitation will not be stopped

       ARBITRATION AND CONCILIATION ACT, 1996

       Sections 11(6), 43 and 21-Limitation Act, 1963, Article 137- Appointment of Arbitrator- Where notice issued to the respondent on 22.8.1997, whereby respondent was called upon to make appointment of arbitrator in term of contract and on 20.9.1997 respondent denied the claim giving reasons, cause of action between the parties commenced by virtue of Section 21 of the Act, therefore application for appointment of arbitrator under Section 11 (6) on 17.4.2001 will be barred by limitation in view of Article 137 of Limitation Act.

JUDGMENT - J.N. PATEL, J.:---M/s. Vishindas Bhagchand, a Partnership Firm, has applied to this Court for appointment of Arbitrator in order to resolve the disputes with the respondents.

2. It is the case of the petitioner-Firm that the respondents invited tenders for construction of Post Water Treatment Plant, Hydrogen Generation Plant, A.H. Plant, Switchgear Building for C.T. Electrical Groundings and other associated works at Chandrapur Thermal Power Station, Stage-III 2X500 MW-Unit 5 and 6, as per the tender No. 8 BC. The petitioner's tender was accepted by the respondents and they were issued works order dated 3-11-1988. Under the contract, the work was to be completed on 31-1-1991, but the same was required to be continued upto 1-8-1991 when it was short closed by the respondents.

3. It is the case of the petitioner-Firm that though the work was short closed on 1-8-1991, the respondents had not cleared the final bill of the petitioner. By the letter dated 24-10-1996, the respondent No. 3 called upon the petitioner for settlement of certain issues for finalising the appeal, pursuant to which the petitioner attended the office of the respondent No. 3 and discussed the pending issue, but the same could not be settled and, therefore, the petitioner served the respondents with notice dated 22-8-1997, raising the pending issue and calling upon the respondent No. 1 to make appointment of Arbitrator as per terms of the contract. By notice dated 20-9-1997, the respondents denied the claim lodged by the petitioner and expressed inability to comply with the notice by stating out various reasons in their notice. According to the petitioner, inspite of this, the parties continued to correspond and negotiate in the matter for settlement of bill and it is in the course of these negotiations, certain issues between them were settled.

4. It is submitted that the respondent No. 3, by the telegram dated 27-7-1999, called upon the petitioner to attend his office for acceptance of the final bill on which the partners of plaintiff-firm on 7-8-1999. The final bill as prepared by the respondents was not acceptable to the petitioner and, therefore, on the same day, the petitioner had given a letter to the respondent No. 3, informing that the measurements are not in dispute. The reduced rates of aluminium window/Ventilators are not accepted. The petitioner also did not accept the penal rate of recovery of steel. The petitioner pointed out to the respondent No. 3 that the final bill is accepted under protest. Again by letter dated 9-8-1999, the petitioner-firm informed the respondents that the final bill is not acceptable to them and requested for release of the bank guarantee worth Rs. 6.02 lacs. The petitioner had pointed out to the respondents that the final bill is minus 1.50 lacs and, therefore, it is not acceptable to them and offered that the respondents, till the settlement of the final bill, may retain the bank guarantee of Rs. 2.50 lacs and return the balance bank guarantee of Rs. 3.52 lacs. The parties had discussion in the matter in the office of the respondent No. 3 on 4-1-2000 which was placed on record by the petitioner through letter dated 5-1-2000. It is the case of the petitioner-firm that the respondents released the bank guarantee worth Rs. 3.52 lacs and did not settle the dispute and, therefore, again by letter dated 16-3-2000, requested the respondents to settle the said issues. But, the petitioner did not get any response. Therefore, the petitioner, by letter dated 30-9-2000, pointed out to the respondents that there are three pending issues relating to (i) penal steel recovery, (ii) payable rate for sluice valves, (iii) Payable rate for supply of aluminium doors and windows. In the said communication, the respondents were informed that on failure to settle the aforesaid three issues, the petitioner will be constrained to resort to arbitration. The respondents having failed to settle the matter, the petitioner-firm, by registere




























Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top