High Court Of Delhi
PARMESHRI DASS AND SONS - Appellant
Versus
UNION OF INDIA - Respondent
Suit 2343A of 1998
Decided On : 08/24/2000
( 1 ) THIS petition under Section 20 of the Arbitration Act, 1940 (for short the Act) seeking directions to the respondents to file the arbitration agreement in the Court and for reference of the disputes to the Arbitrator to be appointed as per terms of the contract, raises the question whether the petition was filed within three years from the date when the cause of arbitration arose, the limitation prescribed under Article 137 of the Limitation Act, 1963 ?
( 2 ) THE petitioner filed the above petition alleging therein that it is a registered partnership firm. The respondents invited tenders for execution of the work named "provision of MT complex and Misc. Accn. for RRH at Delhi Cantt". The petitioner s tender was accepted. The contract documents were duly signed. The work was to commence on 17th December, 1991. Stipulated date of completion was 16th June, 1993 (18 months); General conditions of the contract provided for Settlement of all claims and disputes between the parties arising out of the contract by way of arbitration under Clause 70 of the contract. The petitioner mobilised resources and material, and completed the work despite several hindrances on 31st January, 1994; on 1st February, 1994 respondents were requested for issuance of completion certificate arid for preparation of final bill. The petitioner made claim for certain deviations etc. Respondents pointed out certain defects in the work which were removed. However, in final bill the amounts demanded by the respondents were "not included. The petitioner informed the chief Engineer that payments for the claims made by him were not included in the final bill and same was signed by him under protest, On 15th February, 1995 the petitioner addressed a letter to the "engineer-in-Chief", Army Headquarters, Kashmir House, New Delhi requesting for appointment of an Arbitrator in terms of the contract. In response vide letter dated 1. 3. 1995 Senior Surveyor on behalf of Engineer-in-Chief asked some in formation, which was also furnished by the petitioner on 25th March, 1995. Ultimately on 1st March, 1996 Chief Engineer informed the petitioner that his claim stood waived and extinguished. The petitioner claims that cause of arbitration commenced from this date.
( 3 ) RESPONDENTS filed the reply raising preliminary objection pleading that the petition is barred by limitation. On 25th July, 2000, it was clarified by the respondents that without prejudice to their rights they do not intend to file reply on merits to the petition at this stage.
( 4 ) ON the basis of the pleadings of the parties and the documents filed by them, following undisputed facts emerge:
(I) In l991-92 petitioner was allotted work for construction of MT complex at RRH, Delhi Cantt, which was completed and in 1994 final bill was prepared. Petitioner sought extra payment for certain deviations and also raised other claims. Final bill was signed by the petitioner under protest raising certain claims, but no protest was recorded at the time of receipt of payment. (ii) On 18th February, 1995 petitioner wrote to the Engineer-in-Chief, Army Headquarters, Kashmir House, New Delhi requesting appointment of the Sole Arbitrator as per Clause 70 of the contract. Copies of the letter were sent to, (a) Chief Engineer, Delhi Zone, Delhi, (b) Chief Works Engineer. (CWE),rrh, and (c) Garrison Engineer,p-2, RRH, Delhi - Cantt, Delhi. (iii) Senior Surveyor for Engineer-in-Chief vide letter dated 1st March, 1995 sought some further information from the petitioner. Copy of this letter was sent to the Chief Engineer. The petitioner sent required information on 25th March, 1995 to the office of Engineer-in-Chief with copies to Chief Engineer, CWE and Garrison Engineer, P-2. (iv) Garrison Engineer, P-2 on 26th June, 1995 sent parawise reply repudiating the claims of the petitioner stated that in case the departmentis dragged in the arbitration, the petitioner would have to bear the costs. Copy of this letter
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.