SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2003 Supreme(Bom) 329

IN THE HIGH COURT OF BOMBAY
Shah A.P. Deshmukh D.K., JJ.
Oil Natural Gas Corporation Ltd. .... Appellant.
Versus
Comex Services SA.... Respondent.
Appeal No. 1358 of 1998 in Arbitration Petition No. 107 of 1997 in Award No. 89 of 1997, decided on 12-3-2003.
Advocates appeared :
D.R. Zaiwalla with P.A. Sawant Bhalwal i/b. Vyas Bhalwal, for appellants.
Hiroo Advani Akshay Patil, i/b. Advani and Co., for respondents.

Headnote:Arbitration and Conciliation Act, 1996 - Sections 30 and 33 - Jurisdiction of Arbitrator - Execution of contract - Delayed - Umpire allowed compensation for delay - Resisted - Under terms of contract compensation for delay prohibited - Arbitrator acted without jurisdiction - Such plea not raised at any stage - Held - Point not raised in pleadings cannot be permitted to be raised in appeal - Point of jurisdiction mixed question of fact and law - Arbitrator acted within jurisdiction - Appeal dismissed. - At the ousted Court must mention that this contention was not raised nor argued before the Single Judge nor this contention was taken before the Umpire. The contention is not even raised in the memo of appeal. Since the appellant has not made necessary averments in the petition filed by them for setting aside the award in court is of the appellant should not be allowed to raise this point in this appeal for the first time especially as the question depends upon the facts which are conspicuous by their absence in the pleadings. It is well-settled that specific averments and grounds for setting aside the award have to be set out in the pleadings to enable the Court to set aside the award even though the award may be a nullity as alleged in the instant case. An application for setting aside the award under Section 14 has to be made within thirty days of service of notice. Otherwise the Award cannot be set aside on any ground contemplated by Section 30 of the Arbitration Act. The expression "otherwise invalid" appearing in clause (c) of Section 30 of the Act includes Awards that are nullities. In the instant case no fact has been stated in the petition to show that the Umpire has exceeded his jurisdiction in making the award or in other words he travelled beyond the terms of the contract in awarding the compensation claimed by the respondent

       Arbitration and Conciliation Act, 1996 - Sections 30 and 33 - Award - Compensation for delay - Computation of - Award challenged - Compensation figure computed arbitrarily - Claimed amount reduced to half without any basis - Held - Umpire given cogent reasons in support at award - Even if findings given by Arbitrator on misunderstanding of facts or law, it cannot be ground for setting aside award. - There may be a conflict as to the power of the arbitrator to grant a particular remedy. One has to determine the distinction between an error within the jurisdiction and an error in excess of the jurisdiction. Court cannot substitute its own evaluation of the conclusion of law or fact to come to the conclusion that the arbitrator had acted contrary to the bargain between the parties. If on a view taken of a contract, the decision of the arbitrator on certain amounts awarded is a possible view though perhaps not the only correct view, the award cannot be examined by the Court. Where the reasons have been given by the arbitrator in making the award the Court cannot examine the reasonableness of the reasons. If the parties have selected their own forum, the deciding forum must be conceded the power of appraisement of evidence. The arbitrator is the sole Judge of the quality as well as the quantity of evidence and it will not be for the Court the take upon itself the task of being a Judge on the evidence before the arbitrator.

JUDGMENT - SHAH A.P., J.:---This appeal is directed against the order of the learned Single Judge dismissing the petition under sections 30 and 33 of the Arbitration Act, 1940 for setting aside the Award passed by the learned Umpire Mr. Justice D.Y. Chandrachud (retired C.J.I.) short facts concerning the Award in question may be stated as follows:

By a telex dated 6-6-1988, the appellant placed order on the respondent for design engineering, fabrication, supply and installation and testing and commissioning of pipelines for the D-18 field. The telex set out the terms and conditions of the contract between the parties. Clause (1) of the telex referred to technical specifications and scope of work. These had to be "as per the tender document and as clarified through exchange of various telexes and letters". Clause 2 of the telex called "delivery schedule" provided that the complete scope of the work to be completed by end of October 1988. The price payable for the total work was FF 2,65,40,000. One of the important terms of the contract was that 10% of the contract value would be paid to the respondent on their opening the letter of credit on their vendor for the supply of pipe against equivalent bank guarantee for refund. The respondents were to submit a performance bond in the sum of FF 26,54,000 which was 10% of the contract value at the time of the signing of the contract. By the said telex the respondent was asked to collect a draft contract by 22-6-1988 so that the contract could be signed by 4-7-1988. The telex stated that until the contract was signed by the parties, the telex order shall remain binding on the parties. As originally agreed between the parties, the date of commencement of the contract was 6-6-1988 and the date of completion was 6-12-1988 and that, any rescheduling of the commencement and the completion dates had to be by mutual agreement in terms of Clause 8.5 of the contract. According to the respondent, the schedule of the project was affected by the delays caused by the appellant in keeping several key free issue components for the project ready. It was imperative, according to the respondent, that once their marine spread was mobilized it would remain fully busy upon arrival in India in order that stand by cost could be avoided. The appellant was not agreeable to paying U.S.D. 35,000 per day as stand by charges demanded by the respondent. According to the respondent, the first stage invoice was submitted by them to the appellant on 14-8-1988 but no payment was made by the appellant as stipulated. As a matter of fact the said payment was never made on the ground that the appellant could not have made the payment in foreign exchange unless the written contract was signed by the appellant. On 26-9-1988 the appellant demanded written consent to the change in the schedule and asked the respondents to reach the site on 17-11-1988. According to the respondent, as a result of re-scheduling the completion date had also to be pushed further to 29-12-1998. If that was not done, and if the original schedule in Annexure 6 of the draft contract was allowed to stand, the respondent would have become liable for liquidated damages. It appears that discussions were held in various meetings between the parties. While the negotiations were in progress, the appellant encashed the bid bond for U.S.D. 1,75,000.

2.Disputes and differences having arisen between the parties, the respondent filed Arbitration Suit No. 3945 of 1991 under section 20 of the Arbitration Act for reference of the dispute to the arbitration as per the contract. In the statement of claim annexed to the suit the respondent claimed U.S.D. 21-2-1989 details of which are given in paragraph 27 of the statement of claim. However, the respondents restricted their claim on 2 million dollars, in addition, to the claim for refund of amount of bid bond with interest at 12 percent per annum from 28-12-1988 which is the date of invocation of bid amount till realizati

























Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top