SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
judgment-img

2007 Supreme(Bom) 617

ANOOP V.MOHTA
Union of India – Appellant
Versus
M/s. Arctic India Bangalore – Respondent


JUDGMENT The petitioners have challenged award dated 29/03/2004 under Section 34 of the Arbitration and Conciliation Act-1996 (for short," Arbitration Act.) 2. A contract was executed by and between the parties in respect of replacement of BER A/C plant at NAD Karanja based on the tender dated 27/01/1996. The respondents’ tender was accepted on 09/04/1996. The amount of contract was Rs.86,13,066/- (Rupees Eighty six lacs thirteen thousand sixty six only). The period of completion was 15 months. The date of commencement/ completion as per the work order was 24/04/1996 to 23/07/1997. The work was actually completed, as contended by the respondents, on 11/08/1999/01/10/1999. The claimant/respondents submitted final bill on 17/07/2002 but returned by the petitioners on 31/07/2002. Thus, as dispute arose a sole arbitrator was appointed by letter dated 26/03/2003, in view of terms and condition 70 of IAFW-2249 being part of the contract between the parties. The date of completion of contract as per work order for phase-I was 23/07/1997. The certificate of completion for phase-I was of 29/07/1999. There was no certificate of completion for phase-II. As final bill was returned unpaid, on 2






















































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top