IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ANOOP V. MOHTA,J.
Union of India -Petitioners.
V/s.
M/s. Arctic India Bangalore -Respondents.
ARBITRATION PETITION NO.355 OF 2004
Decided on:25th April, 2007.
Advocates appeared :
Mr. S. R. Rajguru i/by Dr. T. C. Kaushik for the petitioners.
Mr. Sulip Sen i/by M.s D.S.K. Legal for the respondents.
3. The arbitrator fixed the date, time and place for hearing of the matter. The arbitrator has passed award dated 29/03/2004.
4. The respondents has preferred the present Arbitration Petition No.355 of 2004. He has also filed Arbitration Petition No.354 of 2004 for another contract between the parties.
5. By an order dated 24/11/2004, the Court had decided Arbitration Petition No. 354/2004, the petition under section 34 was dismissed. Based on the above order the present petition was also dismissed.
The petitioners therefore, preferred an appeal and by an order dated 08/11/2006 the Division Bench has admitted the matter and after hearing the same remanded the Arbitration Petition No.355 of 2004 for re-hearing. By an order dated 07/02/2007 the present petition has been re-admitted.
6. A preliminary objection was raised by the petitioners on arbitrability of the claims. The learned Tribunal has rightly arrived at the conclusion based on Clause 70, as the arbitration clause provides that before arbitration clause was invoked there should be; either "completion" of works agreed to by both parties or; "alleged completion". In the present case, the respondents contended that the work had been completed, the petitioners however disputed the same. In view of this, the dispute was rightly referred to the arbitrator as the completion of the work itself was the bone of the contention. The other circumstances, as recorded by the learned Tribunal, is that the plant could not have been put to use from 29/07/1999 unless the contract had not been completed by the respondents.
7. In the present case as referred above, in Arbitration Application No. 212 of 2002 filed by the petitioner, arbitrator was appointed by this court on 31/01/2003 and thereafter, arbitrator entered into the record. The submission as raised by the learned counsel appearing for the petitioner that the dispute was not arbitral, therefore, has no force.
8. Claim No.1:-
The amount of the final bill-After perusing all the above as well as the documents and after considering the submission of the learned counsel appearing for the petitioners, I have noted that though time was fixed for completion of the work, yet there was delay on the part of the petitioners (U.O.I.) as they failed to handover the building for dismantaling the old A/C plant. The petitioners altered the job as per their own will, that resulted in great delay in handing over the building to the contractor and in the result the contract could not be completed in time as s
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.