In the High Court of Bombay at Nagpur
THE HONOURABLE MR. JUSTICE B.P. DHARMADHIKARI
M/s. Arunodaya Coal Agency
Versus
Western Coalfields Ltd., through its Chief Managing Director & Another
FIRST APPEAL No. 680 OF 2006
Decided on : 21-01-2009
Arbitration - Accord and Satisfaction - Arbitration and Conciliation Act, 1996, Section 37 - 34 - 16 - 194/1999 -- 2000 - 17th on account bill - 8th on account bill - Accord and satisfaction found by arbitrator and maintained by the lower court - No interference warranted under Section 37 of the Act
Fact of the Case:
The appellant contractor challenged the judgment of the Principal District Judge, Nagpur, in Misc Civil Application 157/2004 under Section 34 of the Arbitration and Conciliation Act, 1996, which upheld the arbitrator's finding of accord and satisfaction between the parties. The dispute arose from the deduction made by the employer from the 8th on account bill, which the contractor protested. The employer claimed accord and satisfaction, which was upheld by the arbitrator and the lower court.
Finding of the Court:
The court found that the contractor's protest on the 8th on account bill was withdrawn, and subsequent bills were without protest. The court also noted that the contractor signed the final bill without protest and provided a no-claim certificate. The court upheld the finding of accord and satisfaction, concluding that the dispute was resolved and the deduction was accepted by the contractor.
Issues: The issues revolved around whether there was accord and satisfaction between the parties, and whether the contractor's protest on the 8th on account bill was withdrawn and subsequent bills were without protest.
Ratio Decidendi: The court held that the findings of the arbitrator and the lower court, which concluded accord and satisfaction, were based on a proper appreciation of the evidence and were not incorrect. The court found that the contractor failed to provide evidence of coercion or duress, and the dispute in relation to the 8th on account bill was resolved and the deduction was accepted by the contractor.
Final Decision: The court dismissed the appeal under Section 37 of the Arbitration and Conciliation Act, 1996, finding no case warranting interference.
1. In this Appeal under Section 37 of Arbitration and Conciliation Act, 1996, referred to as "Act" hereafter, appellant contractor challenges the judgment dated 3/7/2006 delivered by the Principal District Judge, Nagpur in Misc Civil Application 157/2004 filed before him under its Section 34 for quashing and setting aside of order dated 28/1/2004 passed by sole arbitrator accepting the defence of present respondent employer WCL that because of accord and satisfaction there was no arbitrable dispute between parties. Sole Arbitrator has delivered the order dated 28/1/2004 after appreciation of evidence produced by parties and after hearing the arguments. The parties point out from various earlier orders of this Court that appeal is to be heard finally at admission stage. Accordingly "Admit". Rule made returnable forthwith and heard finally by consent.
2. It is not in dispute that contractor was successful in tender process for work regarding excavation, transportation and spreading of earth at colliery of respondent employer WCL. Work began as per schedule and agreement no. 194/1999 -- 2000 signed between parties. Contractor continued to get payment through running account bills up to 7 bill. In the eighth on account bill, contractor alleged that unilaterally Rs. 9 lakh were deducted by employer on the pretext that there was overpayment to contractor up to 7th on account running bill. He therefore registered his protest by letter and also in eighth bill and he got the payment after deduction. Before the start of work, area where excavation had to be done was surveyed jointly and the initial reduced level plan (R.L.Plan) was jointly signed by both the sides. The employer asserted that there were some error committed in recording the initial reduced level's and therefore volume of earth work evaluated was in excess of the actual quantity of the earth work and hence deduction was effected in eighth on account bill. Though this was not accepted by contractor he continued to work and also got payments under subsequent on account bills. The 17th on account bill was final bill and contract was closed thereafter. Contractor then approached Chairman cum Managing Director of present respondent/employer with request to appoint an arbitrator to settle the dispute pertaining to eighth on account bill and accordingly sole arbitrator came to be appointed. Employer raised preliminary objection that there was no arbitrable dispute and therefore Arbitration proceedings needed to be dropped. The arbitrator recorded evidence and also took note of rival arguments and in paragraph 6 proceeded to analyze the facts. Contractor was found to be working contractor with respondents who executed contracts in past and was continuing to execute work even in present. He was fully aware of the system of acceptance of final measurements and giving a "no claim" certificate in the final bill. The arbitrator therefore found that signing of final bill under coercion was not even the remotest possibility. The arbitrator also found that after deduction in eighth on account bill, there was continuous dialogs between employer and contractor regarding the deduction and the contractor was convinced regarding the correctness of the deduction made. The arbitrator also noticed that on account bills after eighth bill were without any protest and in every successive bill there was certificate that contractor accepted the measurement. The arbitrator found that this indicated that contractor got convinced that deduction was not wrongful. It was found that in final bill total quantity of work done was shown as 672313 cubic meters as against the committed quantity in the agreement as 631000 cubic meters. After completion of work, contractor voluntarily applied for additional 10% of quantity and above all he gave an absolute no claim certificate in the final bill. The final measurements of volume were accepted by him not only in that bill but also in the abstract of final
R. A. Deshmukh v. City and Indl. Devp. Corpn. of Maharashtra Ltd.(DB) AIR 1997 Bom. 284
Oil and Natural Gas Corpn. Ltd. v. SAW Pipes Ltd. AIR 2003 S.C. 2629
Bharat Coking Coal Ltd. v. Annapurna Construction AIR 2003 S.C. 3660
M/s Ambica Construction vs Union Of India 2006 (12) SCALE 149
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.