SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2011 Supreme(Bom) 364

2011 (3) ALL MR 1
High Court of Judicature at Bombay
D.Y. CHANDRACHUD & ANOOP V. MOHTA
Shri Atesham Ahmed Khan & Others
Versus
M/s.Lakadawala Developers Pvt. Ltd. & Others
WRIT PETITION NO.1977 OF 2010
Decided on : 23-02-2011

Advocates appeared:
For the Petitioners:Aspi Chinoy, Sr.Advocate with Z.A. Jariwala i/b. Thakore Jariwala & Asso., Advocates.
For the Respondents:R1, Rajiv Narula i/b. Thakore Jariwala & Associate, R2, S.G. Surana, R5 & R6, M. Sayed, AGP, R3 R4 & R7, G.D. Utangale i/b. Utangale & Co., Advocates.

Headnote:Development Control Regulations for Greater Mumbai, 1991 - DCR 33(10)-Constitution of India, Article 14-Slum Rehabilitation Scheme-Proposal for-Acceptance of-Rejection of subsequently-Proposal initially accepted as required consent of minimum 70% slum dwellers was obtained-Later on percent of consent as shown found incorrect-Proposal rejected by Authorities-No opportunity afforded to proposers-Violation of principle of natural justice-Order rejecting proposal not sustainable-Set aside.-The facts as they have emerged on the record would indicate that the first and second respondents had submitted an application on 15th June, 2006. The application was accepted and scrutiny fees were paid. The application by the first and second respondents in the prescribed format contained a statement that a total number of 1235 structures were involved. However, it is common ground that together with the application, the first and second respondents submitted a slum plan which showed that there were 1400 slum structures. The first and second respondents claimed at that stage to have the consent of 911 slum dwellers. When the Slum Rehabilitation Authority was moved on behalf of the petitioners in a complaint, the basis on which the proposal of the first and second respondents was rejected was that considering that there were 1400 existing tenements, it was found on scrutiny that the first and second respondents had not produced the consent of 70%. 870 slum dwellers had signed the common consent form which worked out to 65%. The proposal was initially accepted by the Slum Rehabilitation Authority on the basis that 870 out of 1235 slum dwellers, amounting to 70.50% had furnished their consents. However, considering the fact that the total number of slum dwellers involved was not 1235, but 1400, the Slum Rehabilitation Authority was of the view that the first and second respondents did not have the stipulated consents of 70% of the slum dwellers. However, this order of the Slum Rehabilitation Authority was passed without furnishing to the first and second respondents an opportunity of explaining their position. The High Power Committee cannot be faulted for having come to the conclusion that the order of the Slum Rehabilitation Authority recording and rejecting the proposal of the first and second respondents was passed in breach of the principles of natural justice. Whether as a matter of fact the application submitted by the first and second respondents was valid on the date on which it was submitted, was a matter on which the first and second respondents ought to have been given an opportunity of explaining their position. The SRA acted hastily by immediately, on the same day, allowing the complaint of the petitioner and rejecting the proposal of the first and second respondents. Hence, on a considered view of the matter, Court is not inclined to interfere with the direction that has been issued by the High Power Committee by which the decision of the Slum Rehabilitation Authority dated 26th October, 2006 has been set aside.

Judgement Key Points

Please provide the legal document content (to replace {content} in the template), and I'll analyze it to extract key points with individual references in square brackets (e.g., (!) (!) ).


JUDGMENT :-

DR. D.Y. CHANDRACHUD, J.

Rule; by consent returnable forthwith. With the consent of Counsel and at their request the Petition is taken up for hearing and final disposal.

2. The First and Second Petitioners are Chief Promoters of a proposed Cooperative Housing Society, representing slum dwellers of a plot of land bearing CTS 6/1 (part) at Mankhurd, Mumbai. The Third Petitioner is a developer. The First Respondent is also a developer appointed by the Second Respondent which is another proposed Cooperative Housing Society, representing the interest of the slum dwellers. The dispute in this case pertain to a Slum Rehabilitation Scheme under DCR 33(10) of the Development Control Regulations.

3. On 15 June 2006, an application for sanctioning a slum rehabilitation scheme was submitted by the First and Second Respondents to the Slum Rehabilitation Authority. Annexure-I to the application provided that 1235 structures existed on the land in question. Together with the application, the First and Second Respondents annexed a slum plan and a development agreement showing a total of 1400 existing tenements. On the same day, the First and Second Respondents submitted an Architect’s certificate and a certificate of financial capacity both of which referred to the total number of slum structures as 1403. At that stage, the First and Second Respondents claimed that they had the consent of 911 slum dwellers. The application was accepted. On 17 June 2006, the application was sent for scrutiny by the Deputy Collector of the Slum Rehabilitation Authority to the Additional Collector (Encroachment and Removal) for scrutiny. The Additional Collector forwarded the application in turn to the Deputy Collector. The First and Second Respondents were called upon to produce documents and on 25 July 2006, the First and Second Respondents produced a compilation of documents including inter alia the voters’ list and location plan. On 26 September 2006, the First and Second Respondents produced the consents of 1000 slum dwellers out of a total of 1350 slum dwellers.


4. The Petitioners submitted the proposal to the Slum Rehabilitation Authority on 13 October 2006. On 26 October 2006, a complaint was submitted by the Petitioners to the Slum Rehabilitation Authority against the First and Second Respondents. On the same day, an order was passed by the Slum Rehabilitation Authority recording that out of 1403 slum dwellers, the First and Second Respondents had consents of only 864 slum dwellers. Since this represented 61.58% of the slum dwellers and was less than the required consent of 70%, the proposal of the First and Second Respondents was, it was observed, required to be recorded and rejected.

5. The First and Second Respondents thereupon submitted a representation to the State Government upon which the Government called for a report from the Slum Rehabilitation Authority. The Slum Rehabilitation Authority by its communication dated 25 January 2007, informed the State Government that upon receipt of the proposal of the First and Second Respondents, it was found after scrutiny that the Architect had shown a total number of 1235 existing tenements out of which 870 had signed a common consent which represented 70.50% of the slum dwellers. The Slum Rehabilitation Authority, however, noted that it was found from the slum plan and from the agreement submitted by the Architect that there were actually 1400 tenements and on this basis the First and Second Respondents had consents of 65%. This being less than the required 70% consents, the proposal was recorded and rejected. The Slum Rehabilitation Authority stated in its report that subsequently on 26 September 2006 the First and Second Respondents had submitted independent agreements of occupants representing 1000 out of 1350 tenements.

6. The First and Second Respondents moved the High Power Committee constituted by the State of Maharashtra in order to challenge the order passed by the Slum Rehabilita










Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top