High Court of Judicature at Bombay
D.Y. CHANDRACHUD & A.A. SAYED
Edifice Developers and Project Engineers Ltd.
Versus
M/s. Essar Projects (India) Ltd.
APPEAL NO.11 OF 2012 IN ARBITRATION PETITION NO.313 OF 2007
Decided on : 03-01-2013
Arbitration - Construction Contract - Arbitration and Conciliation Act 1996 - Section 34
Fact of the Case:
The case involved a dispute between the parties regarding the construction of a building. The Arbitral Tribunal awarded various amounts to the Appellant, including principal retention money, overhead losses, loss of profit, and reimbursement of expenses. The Learned Single Judge affirmed the award in part but set aside the arbitral award in respect of certain claims.
Finding of the Court:
The court found that the Arbitrator's reliance on Hudson's Formula for quantifying overhead losses was erroneous, as the Appellant failed to produce evidence to support the claim. The court also held that the award for loss of profit, underutilized plant and equipment, and infrastructure expenses was based on conjecture and lacked supporting evidence.
Issues: The issues involved the validity of the arbitral award in quantifying various claims, including overhead losses, loss of profit, underutilized plant and equipment, and infrastructure expenses.
Ratio Decidendi: The court held that the Arbitrator's reliance on Hudson's Formula without supporting evidence was erroneous. It also emphasized the need for evidence to support claims for loss of profit, underutilized plant and equipment, and infrastructure expenses.
Final Decision: The court dismissed the appeal and upheld the judgment of the Learned Single Judge, setting aside the arbitral award in part due to the lack of evidence supporting the claims.
(Dr. D.Y. Chandrachud, J.) :
This Appeal arises from a judgment of a Learned Single Judge dated 11 November 2011 on a petition under Section 34 of the Arbitration and Conciliation Act 1996.
2. On 28 February 1998 a letter of intent was issued by the Respondent to the Appellant for the construction of Plant 'C' building at a contract price of Rs.1.63 Crores. A reference was made to arbitration of the disputes and differences between the parties in the execution of the work under the contract. By the award of the Arbitral Tribunal, the Respondent was directed to pay an amount of Rs.1.93 Crores to the Appellant together with interest at 10% per annum on the principal sum of Rs.1.84 Crores. The heads of claim which were awarded by the Arbitral Tribunal were as follows:
1) Principal Retention Money Amount payable by the Respondent to the Appellant Rs.1,43,028/-
2) Principal amount of overhead loss Rs.1,32,53,248/-
3) Principal amount of loss of profit Rs.13,50,715/-
4) Loss for underutilized plant and equipment Rs.38,11,531/-
5) Reimbursement of infrastructure expenses Rs.2,01,417
Interest was awarded on the principal retention money and loss of profits pendentelite.
3. The Learned Single Judge affirmed the award of the Arbitral Tribunal insofar as it allowed the claim in respect of retention money in the amount of Rs.1.43,028/-holding that the claim arose out of the contract and that the conclusion which was arrived at by the Arbitrator was a possible conclusion to be drawn on the basis of the material on the record. The arbitral award in respect of the remaining claims was, however, set aside.
4. The Appellant had claimed an amount of Rs.1,88,15,960/-towards overhead losses on the basis of Hudson's Formula. While noting that the Appellant had not produced either the basis of the account or led any oral evidence in support of the claim, the Arbitrator nonetheless allowed the claim on the basis of a finding that Hudson's Formula is adopted for quantification of claims for overhead losses in India. The award contains the following finding:
“35(i) The Claimants have claimed a sum of Rs.1,88,15,960/-for overhead loss on the basis of Hudson Formula. The Respondents have denied their liability and have stated that no evidence of actual loss alleged to have been suffered by the Claimants has been led so as to entitle the Claimants to claim the same from the Respondents. It is correct that the Claimants have not produced their basis of account nor led any oral evidence to prove the overhead loss caused to or suffered by the Claimants. However, in the construction industry when the resources are mobilized and the delay is caused in execution of work which is not attributable to the contractor, overhead losses consequently caused to the contractor, the contractor becomes entitled to same on the basis of Hudson Formula even in want of direct evidence to prove the same.
This formula is adopted for quantification of claims for overhead losses in India. Even in the case of Messrs A.T. Brij Paul Singh & Brothers Vs. State of Gujarat (AIR 1994 SC 1703) on which reliance is placed by Dr. Dave, learned Techno – Legal Consultant for the Claimant, this formula has been accepted by the Hon'ble Supreme Court for quantification of claims for overhead losses. On the basis of Hudson Formula, the Claimants have claimed overhead losses upto 28th January 2002 amounting to Rs.1,88,15,960/-.”
5. The Learned Single Judge, while setting aside the arbitral award noted that -
(i) The Respondent had specifically objected to the adoption of Hudson's Formula noting that this was not an accepted method or measure for the quantification of losses and that the Appellant had in fact failed to produce any evidence in support of the claim. The Arbitral Tribunal had not dealt with the objections of the Respondent;
(ii) The finding of the Arbitrator that Hudson's Formula had been accepted by the Supreme Court in the decision in M/s. A.T. Brij Paul Singh and Bros. v. Sta
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.