2013 Supreme(Bom) 274

High Court of Judicature at Bombay
R.D. DHANUKA, J.
State of Maharashtra (at the instance of Irrigation Department, Executive Engineer, Koyna Division No.2)
Versus
Hindustan Construction Company (Ltd. (“HCC”) & Another
Arbitration Appeal No.6 of 2007
Decided on: 01-02-2013

Act Referred

ARBITRATION AND CONCILIATION ACT : S.34, S.8(2), S.37(3), S.37, S.28(a), S.20, S.11
LIMITATION ACT : S.9, Art.55(ii), Art.54, Art.18, Art.137(ii), Art.137, Art.113(x), S.14

Advocates Appeared:
For the Appellant:A.A. Kumbhakoni, learned counsel a/w Mrs S.V. Sonawane learned A.G.P., Shardul Singh, Abhay Anturkar, Advocates.
For the Respondents:Aspi Chinoy, senior Counsel a/w Mr Arif Doctor i/b M/s Haresh Joshi & Co., Advocates.

JUDGMENT

1. By this appeal filed under Section 37 of the Arbitration And Conciliation Act 1996 (for short herein after referred as 'the Act'), the Government seeks to challenge an order and judgment dated 29th June 2006 passed by the learned District Judge, Ratnagiri rejecting arbitration application No.44 of 2003 filed by the Government under Section 34 of the Act.

2. The Government had challenged an award delivered by the Arbitral Tribunal allowing some of the claims made by the respondent (for short the Government is referred as 'Government' and the respondent is referred as 'the contractor'). Some of the relevant facts for the purpose of deciding this appeal are as under:

Pursuant to the invitation of tender on 1st April 1991 by the Government and submission of bid by the contractor on 17th June 1991, the Government awarded the work of construction of civil work of pressure and power house in ICT contract No.2 to the contractor. The amount of the contract awarded was at Rs.6825 lakh. Both the parties entered into an agreement on 20th March 1992. Stipulated date of commencement of the work was 20th March 1992. The stipulated date of completion was 19th March 1997. The Government granted extension of time to complete the work to the contractor till 31st March 2000. The work was completed by the contractor on 31st March 2000. The date of completion of maintenance period was 3rd October 2000.

3. The dispute arose between the parties during execution of work in respect of hidden expenses. The contractor invoked arbitration clause. On 27th April 1998, first arbitration proceedings started. By an award dated 4th December 1998, the claim of the contractor was partly accepted by the learned arbitrator. Pursuant to said award, the Government paid sum of Rs.10.2 crore to the contractor. The Government did not challenge the said award.

4. On 3rd October 2000, defect liability period ended. The dispute arose between the parties. The matter was referred to arbitration. Arbitral Tribunal was constituted by appointment of one arbitrator by each party. The presiding arbitrator was appointed by the Central Water Commission, New Delhi.

5. On 26th June 2003, the learned arbitrator made an award in favour of the contractor awarding a sum of Rs.17,81,25, 152/-. Being aggrieved by the said award, the Government filed arbitration application No.44 of 2003 on 22nd March 2003 in the Court of District Judge, Ratnagiri challenging the said award under Section 34 of the Act. By an order and judgment dated 29th June 2006, the learned District Judge dealt with five objections raised by the Government by way of preliminary objections only and negatived each of such objection and rejected the said arbitration application. The Government has filed this appeal under Section 37 of the Act for impugning the order and judgment dated 29th June 2006 passed by the learned District Judge.

6. Though Mr. Kumbhakoni, the learned counsel appearing for the Government wanted to advance arguments in respect of various other issues touching the merits of the claims, however, as the learned senior counsel appearing for the contractor objected to such additional submissions which were not made before the learned District Judge, Mr. Kumbhakoni the learned counsel was not allowed to agitate those additional issues. Mr. Kumbhakoni, the learned counsel, therefore did not address this Court on additional issues raised by the Government and addressed this Court only on five preliminary objections raised by the Government before the District Judge in this proceedings also.

7. Mr. Kumbhakoni, the learned counsel submits that the contractor had accepted payment under final bill without making any protest and thus the contract itself cease to exist. The learned counsel submits that the claims thus made by the contractor were not arbitrable in view of such accord and satisfaction due to acceptance of final bill without protest. The learned counsel submits that the contractor had accepte
































































































































1
2
3
4
5
6
7
8
9
10
11