SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1988 Supreme(SC) 235

SUPREME COURT OF INDIA
SABYASACHI MUKHARJI AND S. RANGANATHAN, JJ.
Major (Retd.) Inder Singh Rekhi, Appellant
Versus
Delhi Development Authority, Respondent.
Civil Appeal No. 1178, of 1988, D/- 24-3-1988.
Advocates appeared
Mr. Hardev Singh, Sr. Advocate and Miss Madhu Moolchandani, Advocate with him, for Appellant; Mr. S. B. Saharya, Mr. V. B. Saharya and Mr. Ratna Nair Advocaters, for Respondent.

Advocates:
HARDEV SINGH, MADHU MULCHANDANI, RATNA NAIR, S.B.SAHARYA, V.B.SAHARYA

Headnote:Arbitration Dispute—WHEN A DISPUTE ARISES - DISPUTE ARISES—WHEN - whether the provisions of this article is confined to applications under the code of civil procedure only - contract for building houses — reference of disputes — period of limitation has to be computed from date of claim is asserted and payment is denied — application of article 137.

Judgment

SABYASACHI MUKHARJI, J. :- Special Leave granted.

2. The Delhi Development Authority vide its letter dated 5th October, 1976 accepted the tender of the appellant for construction of 240 Janta Houses at the estimated cost of Rs. 24,49,262/-. The work was to commence on 15th October, 1976 and was required to be completed by 14th July, 1977. By a subsequent extension of time the work was finally completed on 2nd April, 1980 and the houses so constructed have been allotted to several people. Between Feb. 1983 to Dec. 1985 the appellant sent several letters to the respondent requesting them to finalise the bills. It appears, however, that the first of such letters was written on 28th Feb. 1983. Thereafter the appellant wrote several letters and finally on 4th Sept. 1985 to the respondent to finalise the bills and ultimately served the notice through his counsel requesting it to release the security of Rs. one lakh and refer the dispute to arbitration. The respondent failed to do so. In Jan. 1986 the appellant filed an application under S. 20 of the Arbitration Act, 1940 (hereinafter called the Act) seeking a direction from the Court that the respondent be directed to file the arbitration agreement in the Court and the dispute be referred to the arbitration. The learned single Judge of the High Court of Delhi dismissed the application as barred by time. There was an appeal to the Division Bench of the High Court of Delhi. The Division Bench upheld the decision of the learned single Judge. Hence this appeal to this Court.

3. The question is, whether the High Court was right in upholding that the application under S. 20 of the Act was barred by limitation. In view of the decision of this Court in Kerala State Electricity Board, Trivendrum v. T.P.K.K. Amsom (1977) 1 SCR 996, it is now well-settled that Art. 137 of the Limitation Act, 1963 would apply to any petition or application filed in a Civil Court. Sub-sec. (1) of S. 20 of the Act provides as follows :

"Application to file in Court arbitration agreement : - Where any persons have entered into an arbitration agreement before the institution of any suit with respect to the subject-matter of the agreement or any part of it, and where a defence has arisen to which the agreement applies, they or any of them, instead of proceeding under Chapter II, may apply to a court having jurisdiction in the matter to which the agreement relates, that the agreement be filed in Court."

4. Therefore, in order to be entitled to order of reference under S. 20, it is necessary that there should be an arbitration agreement and secondly, difference must arise to which this agreement applied. In this case, there is no dispute that there was an arbitration agreement. There has been an assertion of claim by the appellant and silence as well as refusal in respect of the same by respondent. Therefore, a dispute has arisen regarding non payment of the alleged dues of the appellant. The question is for the present case when did such dispute arise. The High Court proceeded on the basis that the work was completed in 1980 and, therefore, the appellant became entitled to the payment from that date and the cause of action under Art. 137 arose from that date. But in order to be entitled to ask for a reference under S. 20 of the Act there must not only be an entitlement to money but there must be a difference or a dispute must arise. It is true that on completion of the work a right to get payment would normally arise but where the final bills as in this case have not been prepared as appears from the record and when the assertion of the claim was made on 28th Feb. 1983 and there was non-payment, the cause of action arose from that date, that is to say, 28th of Feb. 1983. It is also true that a party cannot postpone the accrual of cause of action by writing reminders or sending reminders but where the bill had not been finally prepared, the claim made by a claimant is the accrual of the cause of action. A dispute



Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top