2020 Supreme(Bom) 465

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
G.S. Patel, J.
Shekhar Appu Shetty - Appellant
Versus
Ravindra Ganesh Bhat - Respondent
Commercial Arbitration Petition No. 111 of 2020
Decided On : 23-01-2020

Important Points

The main legal point established in the judgment is that the Respondent was not required to invoke arbitration afresh under Section 21 of the Arbitration and Conciliation Act 1996 prior to fling his Statement of Claim dated 16th August 2017. The Court concluded that the Arbitral Tribunal had the jurisdiction to decide the claims of both the Claimant and the Respondent.

Subject

Arbitration Law - Jurisdiction and Invocation of Arbitration

Act Referred

ARBITRATION AND CONCILIATION ACT : S.31(3), S.34, S.34(2)(a), S.38(1)(a), S.38(3)

Headnote

patent illegality - Arbitration and Conciliation Act 1996 - Section 34(2-A) - Section 34(2) - Section 34(1) - Section 21 - Section 8 - Section 11(4) - Section 29-A - Associate Builders vs Delhi Development Authority (2015) 3 SCC 49 - Ssangyong Engineering Construction Company Ltd vs National Highway Authority of India.,2019 SCCOnLineSC 677 - G S Patel, J.

Fact of the Case:

The Petition challenges an arbitral Award dated 18th October 2019. The claim of the present Petitioner, Shetty, was rejected entirely, and the opposing claim by the Respondent, Shet, was allowed. The disputes arose between the parties in 2014, leading to termination of the Conducting Agreement by Shet. Shetty invoked the arbitration agreement under Clause 19 of the Conducting Agreement and sought to refer the disputes between the parties to arbitration before the arbitrator named in the said clause. The Hon'ble Court appointed the sole Arbitrator to decide the disputes between the parties arising out of the Conducting Agreement. The parties fled Consent Terms on 6th May 2019, which continued the arbitration clause and introduced new reciprocal obligations. Disputes once again arose between the parties leading to the Respondent terminating the Conducting Agreement by his Advocate's notice dated 14th August 2017. Both sides fled their respective claims before the Arbitrator in view of the facts which transpired post the fling of the Consent Terms.

Finding of the Court:

The Court found that the Respondent was not required to invoke arbitration afresh under Section 21 of the Act prior to fling his Statement of Claim dated 16th August 2017. The Court held that the parties never intended for the reference to terminate, but that the same should continue even after the filing of the Consent Terms. The Court concluded that the Arbitral Tribunal had the jurisdiction to decide the claims of both the Claimant and the Respondent.

Issues: The main issue was whether the Respondent was required to invoke arbitration afresh under Section 21 of the Act prior to fling his Statement of Claim dated 16th August 2017.

Ratio Decidendi: The Court held that the Respondent was not required to invoke arbitration afresh under Section 21 of the Act prior to fling his Statement of Claim dated 16th August 2017. The Court concluded that the Arbitral Tribunal had the jurisdiction to decide the claims of both the Claimant and the Respondent.

Final Decision: The Petition was dismissed, and there was no order as to costs. The operation of the order was stayed for a period of four weeks from the date of the judgment.

Advocates Appeared:
Ravi Gadagkar, Advocate, Usha R Gadagkar, Advocate, J.S. Kini, Advocate, Sapana Krishnappa, Advocate

JUDGMENT

G S Patel, J. - The Petition challenges an arbitral Award dated 18th October 2019. By that Award, to put it briefy, the claim of the present Petitioner, Shetty, was rejected entirely, and the opposing claim by the Respondent, Shet, was allowed. For reasons that will soon became apparent, I have not used the expression ''counter claim'' to describe the pleadings presented by Shet before the learned sole Arbitrator.

2. I believe it is necessary in all Section 34 Petitions frst to clearly identify the precise ground for challenge and the scope of that challenge. As the Supreme Court has now repeatedly said, the challenge in Petitions under Section 34 are not in the nature of First Appeals or regular intra-court appeals. They have a far more restricted and limited remit. Any challenge must lie within the contours of Section 34 of the Arbitration and Conciliation Act 1996, and specifcally, sub-clauses (1), (2) and (2-A). To avoid any ambiguity, I will now reproduce these three sections:

"(1) Recourse to a Court against an arbitral award may be made only by an application for setting aside such award in accordance with sub-section (2) and sub-section (3).

(2) An arbitral award may be set aside by the Court only if-

(a) the party making the application furnishes proof that-

(i) a party was under some incapacity, or

(ii) the arbitration agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law for the time being in force; or

(iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or

(iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration: Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the arbitral award which contains decisions on matters not submitted to arbitration may be set aside; or

(v) the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the agreement of the parties, unless such agreement was in confict with a provision of this Part from which the parties cannot derogate, or, failing such agreement, was not in accordance with this Part; or

(b) the Court fnds that-

(i) the subject-matter of the dispute is not capable of settlement by arbitration under the law for the time being in force, or

(ii) the arbitral award is in confict with the public policy of India.

Explanation 1.-For the avoidance of any doubt, it is clarifed that an award is in confict with the public policy of India, only if,-

(i) the making of the award was induced or afected by fraud or corruption or was in violation of section 75 or section 81; or

(ii) it is in contravention with the fundamental policy of Indian law; or

(iii) it is in confict with the most basic notions of morality or justice.

Explanation 2.-For the avoidance of doubt, the test as to whether there is a contravention with the fundamental policy of Indian law shall not entail a review on the merits of the dispute.

(2A) An arbitral award arising out of arbitrations other than international commercial arbitrations, may also be set aside by the Court, if the Court fnds that the award is vitiated by patent illegality appearing on the face of the award: Provided that an award shall not be set aside merely on the ground of an erroneous application of the law or by re-appreciation of evidence."

3. This framework received extensive analysis in Associate Builders vs Delhi Development Authority., (2015) 3 SCC 49 These heads and their implicit sub-heads were all examined and legal dimensions and contours were specifcally set out.

4. Mr Gadagkar for the Petitioner fairly submits that he places the entirety of his case within the ''pa