SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Bom) 860

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
SOMASEKHAR SUNDARESAN, J.
Surinder Singh - Appellant 
Versus
Arrow Engineering Ltd. - Respondent
Arbitration Petition No. 470 of 2020, Arbitration Petition No. 478 of 2020 
Decided On : 23-04-2025

Advocates Appeared:
Mr. Mukesh Gupta a/w. Ashwini Patil i/b. Solicis Lex, Advocates for Respondent in Review Petition No.4/2021, Review Petition No.5/2021 & Review Petition No.6/2021 and for Petitioner in ARBP/470, 474, 479, 476, 471, 477, 475, 472, 481, 480, 468, 469, 465 of 2020 & 279/2021. Mr. Robin Jaisinghani a/w. Jacinta D’Silva, Advocates for Respondent and for Applicant in Review Petition.

The court ruled that stale arbitration proceedings should not be extended, as the parties demonstrated a lack of interest and sufficient cause for delay, leading to dismissal of the petitions.

Headnote:

(A) Arbitration and Conciliation Act, 1996 - Section 29-A - Petitions concerning arbitration proceedings - 18 Petitions pending since 2020, with no serious pursuit by parties - Court found no cause for extending the mandate of the Learned Arbitral Tribunal, deeming the proceedings stale and unproductive - Petitioners failed to demonstrate sufficient cause for delay and lack of interest in arbitration - Court ruled that extending the mandate would not benefit either party and would prolong the dispute unnecessarily. (Paras 11, 15, 21)

Facts of the case:
The Petitioners initiated arbitration against Arrow Engineering Ltd. for specific performance of contracts to construct bungalows. The proceedings stalled due to disputes over fees and lack of action from the Petitioners for several years.

Findings of Court:
The Court found that the arbitration proceedings had gone stale, with no cause for extending the mandate of the Learned Arbitral Tribunal, and ruled that the Petitions should be dismissed.

Issues: The main issues included whether there was sufficient cause to extend the mandate of the Learned Arbitral Tribunal and the implications of the Petitioners' inactivity in pursuing the arbitration.

Ratio Decidendi: The Court concluded that the Petitioners had lost interest in the arbitration, and extending the mandate would serve no useful purpose, as the proceedings had effectively become dormant.

Result: All the Petitions are finally disposed of by their being dismissed.

JUDGMENT :

Context and Background :

1. This is a bunch of Petitions filed and pending under Section 29-A of the Arbitration and Conciliation Act, 1996 (“the Act”) in connection with arbitration proceedings between multiple Petitioners (“Petitioners”) and the common Respondent, Arrow Engineering Ltd. (“Arrow”). These matters have been pending on the docket of this Court for a long time (since 2020), with neither party seriously pursuing the matter.

2. As it transpires, there have been a total of 22 Petitions, of which four came to be withdrawn. Of the 18 remaining Petitions, three Petitions (Arbitration Petition (L) Nos. 4321, 4322 and 4323 of 2020) were heard and disposed of by a Learned Single Judge of this Court by an order dated October 12, 2020 (“October 2020 Order”) extending the mandate of the Learned Arbitral Tribunal until November 1, 2021. Review Petitions were filed by Arrow in each of the Petitions that were disposed of, and the Learned Single Judge tagged the three Review Petitions with these Petitions by an order dated December 8, 2020.

3. Thereafter, nothing concrete has moved in the matter. Even the extended mandate expired. No fresh petitions under Section 29-A of the Act were filed by the three parties involved.

4. These matters were listed by the Court on its own motion, when it was found that these Petitions have been pending for over five years. The proceedings got underway after a few rounds of jostling among the parties about the appropriate manner to proceed further.

Arbitration Proceedings:

5. The underlying arbitration proceedings relate to contracts by which, Arrow was to construct bungalows in the Navi Mumbai International Airport Influence Notified Area (“NAINA”) that was being planned by the City and Industrial Development Corporation of Maharashtra Ltd. (“CIDCO”). The claims from the Petitioners were for Arrow to be directed to specifically perform the contracts to construct the Petitioners’ bungalows.

6. Indeed, it was that the Petitioners that had initiated arbitration and secured orders under Section 11 of the Act from this Court to get the arbitration proceedings underway. A Learned Senior Counsel of this Court was appointed as an arbitrator on June 30, 2016. Pleadings in the arbitration were completed by April 26, 2017. On June 19, 2017, an application was made by the Petitioners before the Learned Arbitral Tribunal asking for leave to approach this Court for issuance of witness summons under Section 27 of the Act to a planning official of CIDCO (NAINA), since bringing a government servant as a witness into a private arbitration was not within the powers of the Petitioners. The application was allowed by the Learned Arbitral Tribunal.

7. No Petition under Section 27 was filed in Court. On October 29, 2017, an application was moved before the Learned Arbitral Tribunal requesting that the mandate of the Learned Arbitral Tribunal be terminated on the premise that the Petitioners realised that they would be unable to afford the fees of the Learned Arbitral Tribunal. It was also pointed out that in another parallel arbitration proceedings being conducted before another arbitral tribunal, Arrow had been unable to pay arbitrator fees, on the premise that its accounts had been frozen. Therefore, the Petitioners submitted, they would be burdened even more by having to pay Arrow’s fees as well to the Learned Arbitral Tribunal. Arrow filed a reply stating that there was no scope for termination of arbitration proceedings on the premise that payment of costs was unaffordable. However, Arrow submitted that a simple termination of arbitration as envisaged in the Act would be acceptable. A rejoinder was filed by the Petitioners contending that Arrow indeed had initially consented to terminate the arbitral proceedings due to the fees being unaffordable and even had traded drafts of a joint application for termination. However, it was submitted, after one Mr. Vineet Malhotra (the promoter of Arrow) was arrested, Arrow

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top