SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Bom) 1920

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
SANDEEP V. MARNE, J.
Kinjal Dattatray Patil - Petitioner
Vs.
Nandadeep Co-operative Housing Society Ltd. Govandi, Mumbai - Respondent
Commercial Arbitration Petition No.430 of 2024
Decided On : 16-12-2025

Advocates:
Advocate Appeared:
For the Petitioner:Mr. Abhay S. Khandeparkar, Senior Advocate with Ms. Hetal Patel, Mr. Rohit Mahadik, Mr. Suraj Shetye, Mr. Hemanshu Vyas and Ms. Priyasha Pawar
For the Respondent: Mr. Saurabh Butala with Ms. Manvi Sharma, Ms. Aishwarya Hinge and Mr. Harshad A. Sathe

The right to sue accrues on receipt of termination notice, and discussions held do not extend limitation under arbitration or contract claims.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Claims barred by limitation - Petitioner challenges award dismissing its claims as time-barred, asserting that discussions with landowner delayed accrual of claim - Arbitral Tribunal ruled limitation issues were correctly decided as per pleadings without the need for evidence. (Paras 1, 5, 9, 15, 19)

(B) Limitation Act, 1963 - Article 58 & 55 - Court determined that right to sue arose on receipt of termination notice, and discussions did not extend the period for invoking arbitration. (Paras 15, 17)

Facts of the case:
The Petitioner, a Developer, entered into an agreement with a cooperative housing society, which was terminated in 2015; disputes led to arbitration proceedings initiated in 2018, found barred by limitation. (Paras 2-4)

Findings of Court:
The Arbitral Tribunal correctly dismissed the claims as barred by limitation, and no grounds for overturning were established. (Paras 19)

Issues: The Petitioner’s main contention was whether limitation could have been decided without evidence, and when the right to sue originated. (Paras 6, 9)

Ratio Decidendi: The court found the arbitral decision on limitation based upon mutual agreement between parties and relevant law, asserting the right to sue first accrued upon notice of termination receipt. (Paras 10-12)

Result: Petition dismissed; award upheld.

Table of Content
1. challenge to arbitration award based on limitation. (Para 1 , 2 , 3 , 4 , 5)
2. petitioner's argument against the award's decision on limitation. (Para 6 , 7)
3. court's consideration of the arbitrator's findings. (Para 8 , 9)
4. agreed procedural stipulations regarding interim awards. (Para 10 , 11 , 12 , 13)
5. analysis of limitation provisions relevant to arbitration. (Para 14 , 15 , 16 , 17)
6. assessment of the award's compatibility with public policy. (Para 18)
7. final dismissal of the petition. (Para 19)

ORDER:

SANDEEP V. MARNE, J.

1. By this Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (Arbitration Act), Petitioner challenges Award dated 1 November 2022 passed by the learned sole Arbitrator. By the Impugned Award, the learned Arbitrator has dismissed the claims of the Petitioner as barred by limitation.

2. Petitioner is a Developer. Respondent is a cooperative housing society (Respondent-Society) formed by employees of Municipal Corporation of Greater Mumbai (MCGM). Respondent-Society is seized and possessed of plots of land bearing Nos.9, 10, 11 and 15 admeasuring 5634 square meters of thereabouts at Sector-II, Deonar Municipal layout bearing Survey No.93, CTS No.1/3, village Deonar, Mumbai Suburban District (the land). The land is leased by MCGM in favor of Respondent-Society for a period of 60 years. In the year 1987 Respondent-Society constructed a building on the land comprising of Ground plus two upper floors having five wings. The plots in the building are occupied by members of the Respondent-Society who are employees of MCGM. In the year 2007 Respondent-Society decided to redevelop its building. Accordingly, Development Agreement and Power of Attorney dated 11 August 2007 was executed between the Petitioner and the Respondent-Society.

3. It appears that construction activity in accordance with the Development Agreement could not be completed. The Respondent- Society terminated the Development Agreement and Power of Attorney vide letter dated 31 August 2015.

4. The Petitioner replied the termination notice on 15 September 2015. According to the Petitioner, certain committee members of the Respondent-Society approached MCGM for cancellation of the Intimation of Disapproval (IOD) and Commencement Certificate (CC). According to the Petitioner, meetings took place with the MCGM officials with a view to resolve the disputes. In the above background, Petitioner invoked arbitration by letter dated 1 October 2018. Petitioner filed Arbitration Application No.219 of 2019 in which the learned sole Arbitrator was appointed.

5. Petitioner filed Statement-of-Claim. Respondent-Society filed Statement-of-Defence as well as Counterclaim. Respondent-Society also filed Application dated 24 October 2020 seeking dismissal of the Petitioner’s claim as being barred by limitation. It appears that Petitioner filed application for dismissal of Respondent-Society’s Counterclaim as barred by limitation. Both the applications have been decided by the learned Arbitrator vide impugned Award dated 1 November 2022. The learned Arbitrator has dismissed the claims of the Petitioner as being barred by limitation by allowing the application preferred by Respondent-Society. The Respondent-Society did not press the counterclaim against Petitioner and accordingly, the counterclaim of the Respondent-Society is also dismissed. Petitioner is aggrieved by the Award dated 1 November 2022 and has filed the present Petition under Section 34 of the Arbitration Act.

6. Mr Khandeparkar, the learned senior advocate appearing for the Petitioner-Developer has submitted that the learned Arbitrator has grossly erred in deciding the issue of limitation by way of interim Award without letting parties to lead evidence. That issue of limitation is only on question of law and fact, and could not have been decided merely on the basis of pleadings. He would submit that it is a specific case of the Petitioner-Developer that the issue

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top