2016 Supreme(Pat) 1221

IN THE HIGH COURT OF JUDICATURE AT PATNA
Ramesh Kumar Datta, J.
Sai Engicon And Construction Pvt. Ltd. – Petitioner
Versus
The State of Bihar through the Principal Secretary-cum-Commissioner, Department of Road Construction & Ors. – Respondent
CWJC No. 9896 OF 2016, 5558 OF 2015
Decided On : 14-09-2016

Act Referred

GOVERNMENT CONTRACT : .

Headnote

Contract Rescission - Road Construction - Contractors Registration Rules, 2007 - Rule 11(a)(ii), Rule 8(1)(a) - C.W.J.C. No.5558 of 2015, C.W.J.C. No.9896 of 2016

Fact of the Case:

The petitioner sought to quash orders rescinding a contract and blacklisting the petitioner under the Contractors Registration Rules, 2007.

Finding of the Court:

The court found that the rescission order did not comply with the principles of natural justice as the petitioner's reply to the show cause notice was not considered. The order was quashed. The court also held that the blacklisting order could only be made after an independent adjudicatory forum decided the disputed issues of fact.

Issues: Violation of principles of natural justice in rescission order, validity of blacklisting order based on disputed issues of fact.

Ratio Decidendi: The court held that failure to consider the petitioner's reply to the show cause notice made the rescission order invalid. It also emphasized that disputed issues of fact should be decided by an independent adjudicatory forum before a blacklisting order can be made.

Final Decision: The impugned orders in the two writ petitions were quashed, and the writ applications were allowed. The court directed the Executive Engineer to give the petitioner an opportunity to file an additional reply to the show cause if intending to proceed with the rescission of the contract. It also allowed the respondents to proceed with blacklisting after the issues are decided by an independent adjudicatory body.

Advocates Appeared:
For the Petitioner:Mr. Jitendra Singh, Senior Advocate Mr. Mrigank Mauli, Mr. Prince Kumar Mishra and Mr. Sanket, Advocates
For the Respondent:Mr. Kinkar Kumar, S.C.9 and Mr. Zaki Haider, Advocates

ORDER :

Ramesh Kumar Datta, J.

1. Heard learned counsel for the petitioner and learned counsels for the State in both the writ applications.

2. Both the writ applications have been filed by the same petitioner against two different orders arising out of the same subject matter. Hence, they have been heard together and are being disposed of by this common order.

3. C.W.J.C. No.5558 of 2015 has been filed by the petitioner for quashing the order dated 31.03.2015 passed by the respondent No.3, the Executive Engineer, Road Construction Department, Road Division, Bhagalpur, by which he has rescinded the Agreement dated 05.05.2014 for execution of the strengthening work of Ganga Bridge (Vikramshila Setu) approach Road including Four lane, Service Lane and Beautification work in Ist K.M. (Length of Road-10.60 K.M.) under IRQP for the year 2013-14 on the ground of delay in execution of work. The writ application further seeks quashing of the consequential order dated 31.03.2015, by which it has been directed that the balance of the work would be carried out at the risk and cost of the petitioner and further the bank guarantee as well as the security deposit shall be forfeited and the additional expenses incurred for getting the work completed shall be realized by way of instituting certificate case. Further direction has been sought for restraining the respondent authorities from invoking the bank guarantee and forfeiting the security deposit of the petitioner, apart from others.

4. C.W.J.C. No.9896 of 2016 has been filed for quashing the order dated 11.05.2016 passed by the Principal Secretary-cum-Commissioner, Road Construction Department, Government of Bihar, by which the appeal assailing the order dated 15.07.2015 passed by respondent No.2, Engineer-in-Chief-cum-Additional Commissioner-cum-Special Secretary, Road Construction Department, Government of Bihar, blacklisting the petitioner under Rule 11 (a) (ii) of the Contractors Registration Rules, 2007 and Rule 8 (1) (a) of the Office Order No. 154 dated 18.06.2015 has been rejected. Further for quashing the said order dated 15.07.2015.

5. The brief facts as relevant for deciding the present matter are that the petitioner, pursuant to a notice inviting tender, was granted contract for strengthening work of Ganga Bridge (Vikramshila Setu) approach road including four lane, service lane and beautification work in 1st K.M. (Length of Road-10.60 K.M.). The bid of the petitioner was 15% below the scheduled rate. The provisional work order dated 28.02.2014 was issued. The work was to be completed within a period of seven months. Various problems indicated in the writ petition, including the damage to Pirpainti-Shivnaraynpur Bridge through which the materials had to be brought were informed to the authorities. A direction by the Election Commission dated 21.04.2014 for the stoppage of contract work till 16.05.2014 was issued. Further, permission was sought by the petitioner to bring minor minerals from the State of Jharkhand which was not replied and the respondents kept on directing the petitioner to complete the work within the time-frame. Apart from threatening to take other action, penal action against the petitioner was threatened under the provisions of Bihar Contractors Registration Rules. While granting additional lead for bringing materials by letter dated 04.10.2014 the respondents thereby admitted the problem with regard to the damage to various bridges. Further, there was failure of the respondents to regulate the traffic jam on the Vikramshila Bridge over which the major part of the work was to be carried out but the same was not done by the respondent authorities.

6. After threatening the petitioner with the rescission of the contract work if the work was not completed by 31.12.2014, ultimately a show cause notice dated 24.02.2015 was issued to the petitioner to file its reply within three days as to why action be not taken against it. Further a show cause dated 28.03.2015 was also














1
2
3
4
5
6
7
8
9
10
11