SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2013 Supreme(Pat) 49

IN THE HIGH COURT OF PATNA
RAMESH KUMAR DATTA, J.
M/s. NCC Ltd. (formerly known as Nagarjuna Construction Company Limited), 41 Nagarjuna Hills, Hydrabad-82, through its Vice President Mr. B.A.N. Raju, S/o Late Venkatapathi Raju, residing at Plot 789, Sri Residency, 4th Floor, Bhagathsingh Nagar, Near Vasanth Nagar, Hyderabad - Petitioner
IVRCL Ltd. (Infrastructure and Project Ltd.), M-22/3 RT, Vijay Nagar Colony, Hyderabad (A.P.) through its Manager Project Sri Y. Raghunadha Reddy Son of Shri Ramamuni Reddy Resident of C-7, Kosi Colony, Birpur - Petitioner
Versus
The State of Bihar through Principal Secretary, Water Resource Department & Ors. - Respondents
CWJC Nos. 19809 of 2011; 97 of 2012
Decided on: 10-01-2013

Advocates appeared:
For the Petitioner/s:Mr. Y.V. Giri, Sr. Advocate with Mr. Ashish Giri, Advocate
For the State:Mr. Awdhesh Kumar Pandey GA 9 with Mr. Pawan Choudhary, Advocate, Mr. Prashant Pratap, G.P.6 with, Mr. Asit Kumar Jha, Advocate

Headnote:Constitution of India-Article 226-Writ petition-Maintainability-Even in contractual matters or where there is existence of alternative remedy there is no absolute bar to exercise of jurisdiction by High Court if issues of jurisdiction and violation of natural justice arise-Effect of an order declaring defaulter would have serious consequences upon right of contractor to exercise his fundamental right under Article 19(1)(g) of Constitution and cannot be considered as a purely contractual situation or violation of contractual right-It cannot be assumed that such a matter is not maintainable before High Court in its writ jurisdiction. (Paras 24 and 25)

       Constitution of India-Articles 19(1)(g)-Even if authorities of State have power to debar a contractor from participating in future contract after they are declared defaulter on account of not making targeted progress, still finding regarding default cannot be made by State authorities and that must come from a proper adjudicatory forum whether a Court or Arbitral Tribunal-Only after such finding it can be open to authorities of State to declare a contractor as a defaulter and debar it from participating in future tenders. (Paras 27 to 20)

       AIR 2001 SC 2477-Applied.

       (1998)8 SCC 1-Relied.

       2005(3) PLJR (SC) 97; AIR 1977 SC 1496; (2007)9 SCC 593; (2012)2 SCC 108-Referred.

       

ORDER

Heard learned counsel for the petitioners in both the cases and learned counsels for the State.

2. Both the writ applications raise common issues and have accordingly been heard together and are being disposed of by this common order.

3. In CWJC No. 19809 of 2011 direction has been sought to quash the order dated 18.10.2011 issued by the respondent Engineer-in-Chief (Central), Water Resources Department, Government of Bihar in which after holding the petitioner as having not made proportionate progress in completion of the work as per the contract in terms of Clauses 3.3 and 4.8 of the SBD (Standard Bidding Document) the petitioner M/s. NCC Ltd. has been declared a defaulter and debarred from participating in all future tenders.

4. In CWJC No.97 of 2012 also by an order dated 30.9.2011 the Engineer-in-Chief (Central) has for the same reasons held the petitioner M/s. IVRCL Ltd. as defaulter and debarred from participating in future tenders.

5. Both the orders have been challenged by the petitioners in the present writ petitions.

6. In the first writ petition M/s. NCC Ltd. had been awarded a contract for execution of certain works for restoration of Eastern Gandak Canal System including Gandak Barrage and its appurtenants after tender was floated for the said purpose. The contract value was Rs.448.84 crores and the final agreement dated 6.8.2009 was entered into and on the same date notice was issued to the petitioner to proceed with the work. The work was to be completed by 5.9.2011. It is the case of the petitioner that the contract consisted of reciprocal promises by which the promiser and the promisee had to fulfil their part of obligation as per the contract, i.e., authorities had to provide with encumbrance free sites so as to enable the petitioner to complete the contract, accord necessary approvals and necessary permissions, issue approved drawings, undertake joint measurements for 1722 structures to be repaired. A show cause notice dated 18.10.2011, which the petitioner claims to have received on 25.10.2011, was issued to the petitioner by the Engineer-in-Chief (Central), Water Resources Department seeking clarification on as many as eight grounds including not achieving proportionate progress in the work as per the contract and neglect, failure and delay on the part of the petitioner for which the reply to be filed within 15 days as to why blacklisting proceeding should not be started against it and on failure to reply ex parte steps would be taken for blacklisting proceedings against the petitioner company. On the same date as the show cause notice the impugned order dated 18.10.2011 was issued stating that the petitioner had not made proportionate progress in terms of the contract towards the completion of the work and therefore in terms of Clauses 3.3 and 4.8 of the SBD it was declared as a defaulter and debarred from participating in any future tender. The order is under challenge in the present proceedings.

7. The petitioner replied to the show cause letter dated 18.10.2011 by his letter dated 31.10.2011 in which various issues were raised including the failure on the part of the department on various counts which led to the delay in completion of the project. It also expressed its shock on the debarring order stating that it practically amounted to blacklisting without providing any opportunity of being heard. It was further stated in the show cause that the department cannot arrive at a unilateral finding of the contractor being a defaulter and proceed to initiate proceedings of blacklisting which has to be adjudicated by a competent judicial authority, in the present case by Arbitration. It was further stated that the department cannot use its sovereign power for the purposes of settling contractual disputes and in case the department has any grievance in respect of the contract it should invoke the arbitration clause which is the competent authority for settling these disputes and a request was made in the












































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top