IN THE HIGH COURT OF JUDICATURE AT PATNA
Anil Kumar Sinha, J.
Sarita Devi - Appellant
Versus
The State Of Bihar & Ors. - Respondent
Civil Writ Jurisdiction Case No. 4888 of 2021
Decided On : 29-09-2021
Bihar Panchayat Raj Act, 2006 – Section 18 (5) – Removal from post of Mukhiya of Gram Panchayat – It is submitted that there is no violation of principle of natural justice and order has rightly been passed under Section 18 (5) of 2006 Act inasmuch as Additional Chief Secretary-cum-Principal Secretary, has come to definite finding that petitioner has deliberately violated instructions/circulars of State Government and with bad intention, paid amount to Panchayat Secretary instead of getting work executed through Ward Implementation and Management Committee, which shows misuse of power by Mukhiya and action of Mukhiya comes under purview of misconduct in discharge of duty – Order of removal of Mukhiya has already taken effect and tenure of Mukhiya has also come to an end, and a fresh election has been announced – Removal of petitioner on the ground of misconduct, under Section 18 (5) of 2006 Act shall not operate as disqualification to contest future election. (Paras 20, 22 and 24)
JUDGMENT
1. The petitioner, who, at the relevant point of time, was the Mukhiya of Gram Panchayat Raj East Soren, under the Makhdumpur Block, in the district of Jehanabad, has filed the present writ application, for quashing order, dated 14.12.2020, passed by respondent no. 2-the Additional Chief Secretary -cum-Principal Secretary, Panchayati Raj Department, Government of Bihar, Patna, whereby the petitioner has been removed from the post of the Mukhiya, Gram Panchayat Raj East Soren, in exercise of power conferred upon the State Government, under Section 18 (5) of the Bihar Panchayat Raj Act, 2006 (herein after referred to as the 2006 Act') with further direction to the District Magistrate, Jehanabad, to take steps for recovery of the alleged misappropriated amount from the petitioner as well as the Panchayat Secretary, under the Bihar and Orissa Public Demand Recovery Act. The further prayer of the petitioner is for a direction to the respondent authorities to reinstate her on the post of Mukhiya of the Gram Panchayat Raj East Soren.
2. The brief fact, involved in the present writ application, is that the District Magistrate, Jehanabad, vide letter no. 1266, dated 07.12.2018, recommended initiation of proceeding under Section 18 (5) of the 2006 Act against the petitioner to the Department of Panchayati Raj, on the basis of the allegation that the petitioner, in the capacity of Mukhiya, has withdrawn a sum of Rs. 54,60,000/- from the account of the Gram Panchayat in illegal manner for execution of the schemes under the Mukhyamantri Sat Nischaya Yojana in violation of the Government instruction/ circulars, issued vide Memo Nos. 5751 and 5752, dated 30.06.2017. The charges, along with supporting evidence, were served upon the petitioner, vide letter no. 131, dated 04.01.2019, requiring the petitioner to submit her defence upon the charges levelled against her.
3. In reply to the said show cause, dated 15.01.2019, the petitioner stated that the wards were selected for the execution of the scheme by the Aam Sabha of the Gram Panchayat and the same was also approved in the meeting of the Executive Committee and accordingly, the concerned Junior Engineer was directed to prepare the estimate of the selected schemes and place the same before the petitioner for its approval. The Junior Engineer, thereafter, prepared the estimate of the scheme and placed it before the petitioner for technical approval. After the technical approval given by the petitioner, the concerned records were sent to the Block Development officer, Makhdumpur, for administrative approval and the Block Development officer, Makhdumpur, granted administrative approval of the schemes on 21.05.2017 and it was communicated to the petitioner, vide letter no. 110, dated 21.05.2017 (Annexure-1 series).
4. It has further been stated by the petitioner that in view of Government instructions, the Executive Agent of all the schemes was the Panchayat Secretary and, accordingly, the Panchayat Secretary moved a proposal with agreement paper before the petitioner and the petitioner issued the work order after accepting the agreement on 01.06.2017, for which the file was placed before the petitioner with administrative approval of the Block Development officer, Makhdumpur, and for the purpose of the execution of the work, advance amount was sanctioned by the petitioner in favour of the Panchayat Secretary, and after receipt of the advance amount, the Panchayat Secretary proceeded with the execution of the work and completed the work of Scheme Nos. 1 to 4 of 2017-18 and the final measurement thereof was already taken by the Junior Engineer on 20.05.2018 and the same was counter signed by the Assistant Engineer also on 16.08.2018.
5. The further defence of the petitioner was that insofar as the work of Scheme Nos. 5 to 8 are concerned, though the materials were brought to the site for construction from the advance amount received by the Panchayat Secretary and the same were about to be st
The court established that the petitioner's involvement in financial irregularities and bribery constituted gross misconduct under Section 18 (5) of the Bihar Panchayati Raj Act, 2006.
Compliance with the principles of natural justice and the authority of the Chief Executive Officer under Section 92 of the M.P. Panchayat Raj Avam Gram Swaraj Adhiniyam, 1993.
The court upheld the dismissal of a public servant for misappropriation of funds, citing the lack of violation of natural justice and the adequacy of the disciplinary proceedings.
Section 14 (1)(g) of the Maharashtra Village Panchayats Act, 1958 aims to disqualify a Sarpanch who misuses their position by misappropriating public money through contracts awarded to relatives.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.