IN THE HIGH COURT OF JUDICATURE AT PATNA
P.B. BAJANTHRI, ARUN KUMAR JHA, JJ.
M/s Malti Infrastructure Pvt. Ltd. – Appellant
Versus
The State of Bihar – Respondent
Civil Writ Jurisdiction Case No.7421 of 2017
Decided on : 05-05-2023
TENDER - Cancellation of Tender - Notification No. 3162 (s) dated 09.05.2016 - 163(2) - The court upheld the cancellation of the tender based on the provision that if only one bidder remains after evaluation of technical bid, the bid should be re-tendered. The court found that the tender in question was rightly rejected on account of a single bidder, and the petitioner failed to show any emergency warranting consideration of the single bid.
Fact of the Case:
The petitioner participated in a tender for construction work, and after the technical bid evaluation, the tender was cancelled due to the petitioner being the single remaining bidder. The petitioner filed a writ petition challenging the cancellation.
Finding of the Court:
The court found that the cancellation of the tender was justified based on the provision in Notification No. 3162 (s) dated 09.05.2016, which stipulates re-tendering if only one bidder remains after technical bid evaluation. The court held that the petitioner failed to demonstrate any emergency warranting consideration of the single bid.
Issues: Cancellation of tender based on single bidder, Applicability of tender guidelines, Prima facie case for interference with administrative decision
Ratio Decidendi: The tender was rightly rejected on account of a single bidder as per the applicable notification. The court upheld the principle that tenders are to be evaluated based on rules prevailing at the time of issuance, and subsequent amendments do not apply retroactively.
Final Decision: The writ petition was dismissed, and the court found no illegality or irregularity in the cancellation of the tender.
JUDGMENT :
ARUN KUMAR JHA, J.
Heard learned counsel for the petitioner and learned counsel for the respondents.
2. The present writ petition has been filed claiming the following reliefs :
ii. Further for restraining the respondents from finalizing and awarding the re-tender and work order pursuant to impugned fresh NIT issued for construction of above work till disposal of the writ.
iii. For granting any other relief/s for which the petitioner be found entitled in the eye of law.”
3. The short facts, according to the petitioner, are that fourth time NIT No-2 of 2015-16 was issued by the Executive Officer, Nagar Panchayat, Motipur, Muzaffarpur for construction of Administrative Building of Nagar Panchayat, Motipur in which the petitioner participated as a bidder and after final evaluation of the technical bid, it was declared qualified. Thereafter, the Superintending Engineer issued letter to Executive Engineer, DUDA, Muzaffarpur for tools & plants verification of the petitioner company. The petitioner had been waiting for opening of the financial bid, but all of sudden, the Superintending Engineer cancelled the tender vide his letter no. 1837 dated 23.11.2016 in the light of letter no.3186 (3) dated 09.05.2016 and directed the Executive Officer, Nagar Panchayat, Motipur to re-tender the bid and, accordingly, re-tender was invited vide NIT No. 04/2016-17 on 08.12.2016 for the said work. Being aggrieved by the aforesaid decision dated 23.11.2016, the petitioner filed the present Writ.
4. The learned counsel for the petitioner submitted that the petitioner is aggrieved by the action of the respondents in rejecting the tender solely on the ground that there was a single tenderer after the technical bid. The learned counsel further submitted that even after inviting tender for fourth time, only the petitioner remained in contention as single tenderer. In such a situation, there was no logic in re-tendering the matter. Moreover, even the notification No. 3162 (s) dated 09.05.2016 of the Road Construction Department provides for award of contract to single tenderer. Thus, the learned counsel submitted that even the single tenderer can be awarded the contract and the same has been held by this Court as well. In support of this contention, the learned counsel has placed reliance on the order dated 21.07.2016 passed by this Court in CWJC No.8869 of 2016 and its analogous cases.
5. On the other hand, the learned counsel for the respondents while justifying the action of the respondents s
The court upheld the principle that tenders are to be evaluated based on rules prevailing at the time of issuance, and subsequent amendments do not apply retroactively.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.