2010 Supreme(Cal) 656
High Court of Judicature at Calcutta
SANJIB BANERJEE
Alstom Projects India Limited
Versus
Galaxy Engineering Contractors
GA No. 2495 of 2003 & AC No. 15 of 2003
Decided On : 18-06-2010
For the Petitioner:Moloy Kumar Ghosh, Ms. Mitusree Boral, Tapan Kumar Dey, Advocates.
For the Respondent:Dipak Basu, Sr. Adv., Ms. Samapti Chatterjee, Ms. Chaitali Mukhopadhyay, Ms. Adhiti Banerjee, Ms. Nandita Das, Advocates.
The assessment of damages is within the authority of the arbitrator and the court will not interfere unless it can be objectively demonstrated that the figure arrived at by the arbitrator is palpably erroneous.
Headnote:
ARBITRATION - PRINCIPAL AMOUNT AWARDED - CHALLENGE - PERVERSE AWARD - MISCONDUCT OF ARBITRATOR - LACK OF EVIDENCE - DAMAGES - SECTION 73 OF THE CONTRACT ACT, 1872 - ASSESSMENT OF DAMAGES - SUBJECTIVITY - REASONABLENESS - JUDICIAL INTERFERENCE.
Fact of the Case:
The petitioner challenges the principal amount of an arbitration award, alleging that it is perverse and that the arbitrator misconducted himself by awarding an amount despite recording that there was no evidence to substantiate the extent of loss suffered by the respondent.
Finding of the Court:
The court held that the arbitrator's assessment of damages was within his authority and that there was material before him to make a reasonable assessment. The court also found that the quantum assessed by the arbitrator on account of damages did not appear to be outlandish.
Issues: 1. Whether the arbitrator's award is perverse and the arbitrator misconducted himself by awarding an amount despite recording that there was no evidence to substantiate the extent of loss suffered by the respondent? 2. Whether the assessment of damages was within the authority of the arbitrator? 3. Whether there was material before the arbitrator to make a reasonable assessment of the quantum of damages?
Ratio Decidendi: 1. The court held that there is a distinction between a claim being found to be without basis and a claim being found to have been overstated. In the present case, the arbitrator found that the contractor had suffered loss and damage, but that the contractor's estimate of the quantum of loss suffered was an over-statement. 2. The court also held that there was material before the arbitrator, in the particulars furnished by the claimant, as to how the quantum of damages should be assessed. It cannot be said that there was no basis presented before the arbitrator to make a reasonable assessment of the quantum of damages. 3. The court further held that even though the specific reason as to what impelled the arbitrator to arrive at the figure of Rs.25 lakh has not been made clear, on a reading of the entirety of the award and the value of the contract, the quantum assessed by the arbitrator on account of damages does not appear to be outlandish.
Final Decision: The court dismissed the petition challenging the award and decreed the award in terms of the arbitrator's award.
SANJIB BANERJEE, J. : –
1. The petitioner seeks to have the principal part of an award set aside on the ground that it is perverse and that the arbitrator has mis-conducted himself and the proceedings in awarding an amount despite recording that there was no evidence to substantiate the extent of loss suffered by the respondent. Under a purchase order of October 12, 1989 the respondent was required to take up the job of fabrication, erection and commissioning of two electrostatic precipitators for the Madhya Pradesh Electricity Board in Korba. It was the respondent-claimant’s case before the arbitrator that despite such contractor having completed all work, the commissioning could not be done on account of default on the part of the petitioner herein. The claimant complained in its statement of claim that it had suffered loss and damage on account of such inordinate delay and sought an amount of Rs.51 lakh on the ground that the petitioner herein could not arrange for the commissioning to be completed despite the claimant being ready and willing to do the same by December, 1992. The contractor said that it had to wait till the middle of 1994 to complete the commissioning work and its men and material were uselessly detained at site when they could have been gainfully engaged elsewhere. The arbitrator considered such claim under issue no. 3. The arbitrator recorded the basis of the claim and concluded, on the basis of the material before him, that the head of claim was justified since the job that remained outstanding was negligible and was equivalent to five per cent of the work assigned to the contractor. The arbitrator found that by July, 1992 the contractor had indicated that it would finish the entirety of the work by December, 1992, but no effective steps were taken for shutting down the plant to enable the new precipitators to be commissioned. The award records that the contractor had to wait at the Korba site needlessly and that it was the petitioner herein who was responsible for the delay.
The arbitrator noticed the claim for the 17 months’ delay made by the contractor at Rs.3 lakh per month and the petitioner’s contention that the contractor was not entitled to such amount and the contractor should have taken appropriate steps for mitigation of damages. After nearly four pages of discussion on such aspect, the arbitrator held as follows:
“I am of the view that the claimant has suffered damages. The claimant has claimed it in particulars specified in the Statement of Claim to justify the damages of Rs.51 lakhs that it has suffered loss on being detained at Korba site cannot be doubted. Its claim of Rs.3,00,000/- per month as the profit per month which it could have earned if it could do similar job is the claimant’s over estimate no doubt. But I am of the view that whether such contract could have been available to the claimant during the period the same value was not a certainty. So, it would not be proper to award the claimant damages for Rs.51 lakhs as claimed by it. However, on considering the case from all its aspects and regard being had to the fact that the claimant was a very efficient and competent contractor and even after the completion of this job the respondent offered it another contract which the claimant, however, did not undertake, the claim of compensation made in this arbitration proceeding is genuine as the claimant suffered loss for being detained for 17 months. However, in the light of the facts and circumstances of the case I award the claimant Rs.25,00,000/- as damages.” (Page 12 of the award)
The petitioner argues that the present challenge to such aspect of the award is not on the basis of any mistake of fact or reasonableness of the reason in support thereof or of inadequate evidence. The petitioner says that the assessment of the quantum of damages is based on no evidence at all and is, as such, perverse. The petitioner concedes that in a matter of such nature there is an element