IN THE HIGH COURT OF CALCUTTA
Kalyan Jyoti Sengupta and Asim Kumar Mondal, JJ.
Board of Trustees for the Port of Calcutta - Appellants
Vs.
Royal Constructions - Respondent
A.P.O. No. 18 of 1991
Decided On: 25.09.2012
ARBITRATION - AWARD - LUMP SUM AWARD - VALIDITY - COURT'S POWER TO SCRUTINIZE - PROHIBITORY CLAUSE AGAINST ESCALATION OF PRICE - APPLICABILITY BEYOND STIPULATED PERIOD OF CONTRACT - PRINCIPLE OF UNJUST ENRICHMENT - SECTION 70 OF THE CONTRACT ACT.
Fact of the Case:
In an arbitration proceeding, the sole arbitrator awarded a lump sum amount of Rs. 2,53,000/- out of a total claim of Rs. 3,91,052.35p without providing any reasons. The appellant, being aggrieved by the award, filed an application under sections 30 and 33 of the Arbitration Act, 1940 (since repealed) for setting aside the award on the ground of legal misconduct committed by the arbitrator.
Finding of the Court:
The court held that the arbitrator's award was not sustainable as it was not possible to award the amount claimed under the terms of the contract. The court further held that the prohibitory clause against escalation of price as contained in the contract was not applicable beyond the stipulated period of the contract, and that the principle of unjust enrichment under section 70 of the Contract Act was correctly applied by the trial judge.
Issues: 1. Whether the arbitrator's lump sum award was valid without providing any reasons? 2. Whether the prohibitory clause against escalation of price was applicable beyond the stipulated period of the contract? 3. Whether the principle of unjust enrichment under section 70 of the Contract Act was correctly applied by the trial judge?
Ratio Decidendi: 1. A lump sum award by an arbitrator without providing any reasons is not sustainable. 2. A prohibitory clause against escalation of price in a contract is not applicable beyond the stipulated period of the contract, especially when the delay in completion of work is attributable to the employer. 3. The principle of unjust enrichment under section 70 of the Contract Act can be applied when a party has been unjustly enriched at the expense of another.
Final Decision: The appeal was dismissed, and the judgment and order of the trial judge was affirmed.
Kalyan Jyoti Sengupta, J.
1. The appeal has been preferred by the above named appellants being aggrieved by and dissatisfied with the judgment and order of the learned Trial Judge dated 22nd November, 1990 whereby and whereunder the award of the learned sole Arbitrator has been made rule of the Court, and decree has been passed. The short fact of the case leading to bringing action by the appellant is summarized as follows:-
The respondent above named was awarded contract for 60% of the total works of annual maintenance of road at residential area of the Haldia Dock Complex by the appellant. The appellant was successful tenderer for the entire tender works agreeing to execute the works at a sum of Rs. 8,83,362.12. But the same could not be completed within the time stipulated for various reasons. Accordingly extension of time was granted for completion of the same. The payment was made for the works done and the respondent is said to have signed the final bill of payment and "no claim certificate" was issued by the respondent. Thereafter the respondent demanded of the appellant for making payment of a sum of Rs. 3,91,052.35 on various heads. Obviously such payment was not made by the appellant, and hence dispute arose. In terms of the agreement the dispute was referred to Sole Arbitration of one Mr. D.P. Roy Chowdhury. The statement of claim was filed by the respondent naturally counter statement was also filed by the appellant to contest the claim made by the respondent before the learned Arbitrator.
2. In the statement of claim aforesaid aggregate amount of Rs. 3,25,768.37p on account of principal under various heads, and interest at the rate of 18.5% calculated from 1st June to 30th June, 1986 amounting to Rs. 65,283.98 p. thus aggregating to Rs. 3,91,052.35p. was made. Break up of the head of the claim are as follows:-
3. The defence taken that most of the claims are not admissible under the Special Condition of Contract or General Conditions of Contract. It was contended that the claim No. 1 was not permissible under Clause 7 of the Special Condition of Contract; Claim No. 2 is also prohibited under Clause 65 of General Condition of Contract; Claim No. 3 is not allowable under Clause 10 of the Special Condition of Contract; Claim No. 4 is also disallowable under Clauses 24, 25(a) and 26(a) of the General Condition of Contract; Claim No. 5 is prohibited by Clause 26(a) of General Condition of Contract; Claim No. 6 is not allowable under Clause 48(b) of General Condition of Contract; Claim No. 7 cannot be allowed under Clause 7 of the Special Condition of Contract; Claim No. 8 is hit by Clause 33 of the General Condition of Contract; Claim No. 9 is also the same position under Clause 65 as Claim No. 8 is; Claim No. 10 is also barred by Clause 65 of General Condition of Contract; Claim No. 11 being the amount of interest is prohibited under Clause 13(g) as quoted above.
4. After several sittings the learned Sole Arbitrator has awarded a lumpsum amount of Rs. 2,5300/- without spelling out his mind, out of total claim as above. In addition thereto cost of the arbitration of a sum of Rs. 26,720/- has been allowed no pendente lite interest has been allowed in the awarded sum.
5. The appellant thus filed an application under sections 30 and 33 of the Arbitration Act, 1940 (since repealed) for setting aside the same principally on the ground of legal misconduct committed by the learned Arbitrator having awarded the lump sum amount and most of which are covered by prohibitory clause of the agreement. The learned Trial Judge however did not accept the challenge and upheld the award substantially and decree was passed accordingly.
6. Before us Mr. Shurit Roy Chowdhury, Barrister-at-Law contends that on plain reading of the claims under different heads it would appear that same are absolutely barred under various terms and conditions of the General Condition of Contract or Special Condition of Contract. Therefore, the learned Arbitra
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.