IN THE HIGH COURT OF CALCUTTA
SANJIB BANERJEE, J.
Larsen & Toubro Ltd.
Vs.
Visa Power Ltd.
AP No. 522 of 2012
Decided on: July 10, 2012
BANK GUARANTEE - INJUNCTION - IRREVOCABLE BANK GUARANTEE - ENCASHMENT RESTRAINED - GROUNDS - FRAUD, IRRETRIEVABLE INJUSTICE, SPECIAL EQUITY - CONDITIONS - EXCEPTION TO RULE OF PAYMENT - INDEPENDENT CONTRACT - FACTS NOT MEETING EXCEPTIONS.
Fact of the Case:
Petitioner sought an injunction restraining respondent from invoking/receiving payments under three bank guarantees furnished in connection with a contract for setting up a power plant. Petitioner claimed substantial dues, alleging respondent's failure to adhere to payment schedules and attempts to modify the work scope. Respondent disputed the amount owed and asserted that bank guarantees had been invoked but payment not yet received.
Finding of the Court:
The court held that the facts presented, even if taken as the petitioner's best arguable case, did not meet the high threshold required for granting an injunction against the encashment of irrevocable bank guarantees. The court emphasized that bank guarantees are independent contracts governed by their own terms and that disputes relating to the underlying contract cannot be grounds for restraining payment under a bank guarantee.
Issues: 1. Whether the facts presented by the petitioner met the exceptional circumstances required for granting an injunction against the encashment of irrevocable bank guarantees? 2. Whether the respondent's conduct amounted to fraud vitiating the foundation of the bank guarantees?
Ratio Decidendi: 1. The court reiterated the established legal principles governing bank guarantees, emphasizing the exceptions to the rule of payment: fraud, irretrievable injustice, and special equity. 2. The court found that the petitioner's allegations, even if accepted, did not constitute fraud at the inception of the transaction or irretrievable injury that would make it impossible for the petitioner to recover the money if the respondent encashed the bank guarantees. 3. The court clarified that the third exception, special equity, must be ejusdem generis with the other exceptions and that the respondent's conduct, though unfair, did not rise to the level of shocking behavior that would warrant an injunction.
Final Decision: The court dismissed the petition, holding that the petitioner was not entitled to an injunction restraining payment under the bank guarantees or an order in the nature of attachment before judgment.
1. The Court: The principal prayer made in this petition under section 9 of the Arbitration and Conciliation Act, 1996 is for an injunction restraining the respondent from invoking or receiving payments under three several bank guarantees furnished in connection with a contract for setting up a power plant in Raigarh. There is an incidental prayer in the nature of attachment before judgment.
2. The arbitration clause is not in dispute. Upon leave under Clause 12 of the Letters Patent having been granted on July 6, 2012, it was submitted on behalf of the respondent that it had an objection to the authority of this Court to entertain the petition. The objection has not been elaborated upon today. On July 6, 2012, the respondent had, however, been gracious enough to not insist on immediate payment from the bank since the matter could not have been conveniently concluded on that date. The concession recorded in the order dated July 6, 2012, however, did not create any equity in favour of the petitioner nor did it bind the respondent to abide thereby beyond the time that the matter was due to be taken up in Court. The respondent says that the bank guarantees have been invoked but the payment has not yet been received. There will be no impediment to the payment under the three several bank guarantees being received and the bank or banks are left free to make payment thereunder.
3. A letter of award was issued for the design, supply, erection and commission of the two 600 MW units of the proposed power plant. Four several contracts were entered into by the parties on December 7, 2011 for the supply of machinery, construction of the plant, supply of raw material and the commissioning of the units. The case made out by the petitioner is that notwithstanding the agreement envisaging regular payments to be made on 30-day after basis following the running bills being of the petitioner being submitted, the respondent has failed to adhere to the payment schedule and the respondent has subsequently sought to modify the scope of the work as originally contemplated.
4. The petitioner demonstrates from the correspondence exchanged between the parties that payments in accordance with the agreed terms were not tendered by the respondent. The petitioner refers to the minutes of several meetings held between the representatives of the parties from which it is evident that the respondent sought time to make payment and only made part payments of the long overdue amounts. It appears to be fairly clear on the basis of the documents relied upon, that the petitioner has a substantial claim. The petitioner insists that bills of value in excess of Rs.141 crore have been certified for payment by the respondent. The respondent disputes such figure but it does not appear that the amount covered by the bills already raised and not paid for by the respondent is insubstantial.
5. The petitioner refers to the minutes of a meeting held on December 8, 2011, whereat the respondent admitted that a substantial amount remained due to the petitioner. In letters exchanged thereafter, it is evident that the petitioner claimed by January 14, 2012 that a sum in excess of Rs.76 crore was due in respect of the certified bills. The petitioner stresses on a letter dated January 19, 2012 issued by the respondent. It is evident from such letter that a financial tie-up had been completed by the respondent under which it was to obtain credit facilities from one or more banks. The petitioner says that in the respondent agreeing to release funds within thirty days of the bills being raised therefor by the petitioner, and in the respondent not having funds available to honour such commitment, the respondent had perpetrated fraud in inducing the petitioner to enter into an arrangement without believing that the respondent could honour its part of the bargain therein. The petitioner insists that the conduct of the respondent would amount to the fraud of the kind that would entitle
Federal Bank Ltd Vs. V.M. Jog Engineering Ltd
Hindustan Steel Works Construction Ltd Vs. Tarapore and Co.
UP State Sugar Corporation vs. Sumac International Ltd
Hindustan Construction Company Ltd Vs. Satluj Jal Vidyut Nigam Ltd
P.D. Alkarma Private Ltd Vs. Canara Bank
Satluj Jal Vidyut Nigam Ltd Vs. Jai Prakash Hyundai Consortium
Victor Cables Industries Ltd. Vs. Engineering Products (I) Ltd.
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.