B.P.JEEVAN REDDY, M.M.PUNCHHI, SUJATA V.MANOHAR
U. P. State Sugar Corporation LTD. – Appellant
Versus
Sumac International LTD. – Respondent
The legal principle established by the Supreme Court emphasizes that courts should exercise restraint in staying the invocation of an unconditional bank guarantee, recognizing the importance of honoring such guarantees to maintain trust in commercial transactions. The Court clarified that the primary exceptions to this rule are cases involving clear fraud or situations of irretrievable injustice that would cause irreparable harm to one of the parties involved (!) .
In the context of your argument, the contention that "expiry" is merely a technicality does not meet the high threshold of "irretrievable injustice" as defined by the Court. The Court has consistently held that mere procedural or technical issues, such as the expiration of a guarantee, do not automatically constitute irretrievable injustice unless there are exceptional circumstances demonstrating that enforcement would cause unavoidable and substantial harm that cannot be remedied through other legal avenues (!) .
Therefore, unless the Railways can demonstrate a compelling and exceptional circumstance that would result in irreparable harm—beyond mere technicalities—the courts are unlikely to find that the invocation of the bank guarantee should be stayed on the ground of irretrievable injustice. The high threshold set by the Court underscores the importance of maintaining the integrity of unconditional guarantees and discourages courts from intervening unless clear and exceptional circumstances are established.
JUDGMENT
Mrs. Sujata V. Manohar, J.-Leave granted.
2. The appellant, U.P. State Sugar Corporation entered into an agreement dated 2nd of August, 1989 with the respondent, M/s. Sumac International Pvt. Ltd. under which the respondent agreed to design, to prepare an engineering lay-out and to manufacture or procure and supply to the appellant the machinery and equipment for a complete sugar plant for extension and modernisation of the appellant s existing sugar plant at Rohana Kalan, District Muzaffarnagar, U.P. The respondent was required to set up a new plant of 2500 TCD at a new site or an adjoining site close to the existing sugar plant of the appellant. The total contract price was fixed under Clause 2.1 of the contract at Rs. 1780 lacs.
3. Under the terms of the agreement the respondent was required to set up the plant and mark it ready for commercial production by 30th of November, 1990. The agreement stated that in this regard time was of the essence of the contract and if the respondent failed to do so the consequences were also spelt out in the contract. Under Clause 3 of the contract a month-wise progressive delivery report was to be submitted by the respondent and a PERT/CP
U.P. Cooperative Federation Ltd. v. Singh Consultants and Engineers (P) Ltd.
Svenska Handelsbanken v. M/s. Indian Charge Chrome & Ors.
Larsen & Turbro Ltd. v. Maharashtra State Electricity Board & Ors.
Hindustan Steel Workers Construction Ltd. v. G.S. Atwal & Co. (Engineers) Pvt. Ltd. 1995(6) SCC 76.
National Thermal Power Corporation Ltd. v. Flowmore Pvt. Ltd. & Anr.
State of Maharashtra & Anr. v. M/s. National Construction Co., Bombay & Anr.
Hindustan Steel Workers Construction Ltd. v. Tarapore & Co. & Anr.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.