Tarun Chatterjee, Subhro Kamal Mukherjee
Calcutta Improvement Trust – Appellant
Versus
J. G. Engineers Private Limited – Respondent
Subhro Kamal Mukherjee, J.
This is an appeal against the judgment and order dated April 25, 2000 passed by a learned Judge of this Court rejecting an application for setting aside of the award filed under sections 30 and 33 of the Arbitration Act, 1940. (In short "the Act")
2. On or about May 30, 1994 an agreement was entered into by and between the parties appointing the respondent/contractor for construction of 48 flats at premises Nos. 19C and 19D, Golf Club Road, Calcutta. It was stipulated in the agreement that the entire work, contracted for, should be completed and possession of the flats should be delivered within 18(eighteen) months from April 12, 1994.
3. After taking over the site the contractor progressed with the works to some extent, but could not complete the work within the time frame. By a letter dated December 23, 1994, the contractor, inter alia, stated that it was not possible for the contractor to recommence the work and to show minimum progress of the work due to reasons allegedly beyond their control and submitted a re-schedule of the work and asked for permission to restart the work. It was categorically stated in the said letter that opportunities sh
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.