IN THE HIGH COURT OF CALCUTTA
Soumen Sen, J.
TATA STEEL LIMITED - Appellant
Vs.
LINDSAY INTERNATIONAL (P) LTD - Respondent
G.A. No. 3904 of 2015 and A.P. No. 1734 of 2015
Decided On : 28-11-2016
ARBITRATION - Setting aside of award - Grounds - Perversity and non-application of mind - Whether the arbitrator has assigned any reason for allowing the claim on account of goodwill and loss of profit and on that ground alone the award is liable to be set aside - Whether the arbitrator has completely misdirected its mind in allowing the claim on account of failure of consideration by overlooking the fact that the foreign buyer has asked for refund over Rs.3 Crores from the petitioner which presupposes that the petitioner has received a sum over Rs.3 Crores and unless the petitioner could prove in the proceeding that they had paid the aforesaid sum, the petitioner cannot claim any amount in this regard as it would be an unjust enrichment.
Fact of the Case:
The respondent is the award holder. The petitioner has filed an application being G.A. No.3904 of 2015 for stay of operation of an award passed on 25th August, 2015. The petitioner has also filed an application being A.P. No.1734 of 2015 for setting aside of the said award.
Finding of the Court:
The award allowing a sum of Rs. 1,08,07,398/ for failure on consideration is without any evidence or basis. However, the claimant on account of loss of profit should be Rs. 42,00,000/- instead of Rs. 50,96,533/- in view of evidence of the claimant before the arbitrator. The award for a sum of Rs. 8,99,915/- being an expenditure incurred by the claimant on account of shipment expenses is also based on evidence and, accordingly, is upheld. However, having regard to the fact that no evidence was led for loss of goodwill and loss of business which would be evident from the evidence adduced on behalf of the claimant, in my view, awarding a sum of Rs.1 Crore for loss of goodwill and/or loss of business is without any evidence and suffers from non-application of mind.
Issues: Whether the arbitrator has assigned any reason for allowing the claim on account of goodwill and loss of profit and on that ground alone the award is liable to be set aside.
Ratio Decidendi: The arbitrator has completely misdirected its mind in allowing the claim on account of failure of consideration by overlooking the fact that the foreign buyer has asked for refund over Rs.3 Crores from the petitioner which presupposes that the petitioner has received a sum over Rs.3 Crores and unless the petitioner could prove in the proceeding that they had paid the aforesaid sum, the petitioner cannot claim any amount in this regard as it would be an unjust enrichment.
Final Decision: The application being A.P. No.1734 of 2015 is allowed in part. The award stands modified to the aforesaid extent. G.A. No.3904 of 2015 is also disposed of in terms of this order.
Soumen Sen, J.
The respondent is the award holder.
2. The petitioner has filed an application being G.A. No.3904 of 2015 for stay of operation of an award passed on 25th August, 2015. The petitioner has also filed an application being A.P. No.1734 of 2015 for setting aside of the said award.
3. The dispute between the parties arose out of an agreement dated 8th January, 2003, under which the petitioner was to manufacture and supply goods as stated in the agreement for a total consideration of Rs.1,22,00,000/-. The goods to be supplied under the agreement, inter alia, included one Pipe End Facing and Chamfering Machine Model No. EFM-4(L)-Single Tube along with maintenance, insurance, spares and consumables for the said machine; Single Pipe Hydro Tester Model No. HP-4(L) and maintenance, insurance and spares for the single pipe hydro tester model. The agreement also included charges for supervision of erection, adjustment and commissioning by the petitioner.
4. This agreement was made to satisfy the respondent's obligation for export of Kazakstan for utilization at Ispat Karmet, Kazakstan in their pipe plant.
5. The petitioner alleged to have supplied the goods and performed the work in terms of the contract. However, a part consideration out of the said Rs.1,22,00,000/- was paid to the petitioner by the respondent and thereafter on the allegation, the petitioner had committed a breach of the agreement in supplying the goods agreed to be supplied under the agreement, the respondent made a demand on the petitioner for refund of the entire consideration. The respondent claimed that there was a total failure of consideration and prayed for refund of the consideration money.
6. In terms of the arbitration clause contained in the agreement dated January 8, 2003, the Hon'ble Justice Ronojit Kumar Mitra (Retd.) was appointed as the Sole Arbitrator to adjudicate upon the disputes and difference between the parties.
7. The respondent as claimant in the arbitration proceeding has made the following contention:-
(A) The respondent-claimant under a contract dated December 26, 2000 agreed to sell to Ispat Karmet Kazakhstan, one Pipe End Facing & Chemfering Machine, Model No.EFM. 4(L) Single tube and one Single Pipe Hydro-tester, Model No.HT-4(L) (hereinafter referred to as "the said two machines"). Thereafter the name of Ispat Karmet Kazakhstan was changed and is presently known as Mittal Steel Termirtua.
(B) The Claimant on January 8, 2003 entered into an Agreement with Tata Steel Limited. In the Agreement the Claimant is mentioned as the "Buyer", the petitioner as the "Seller" and Ispat Karmet Kazakhstan as "End User" (hereinafter referred to as "the Agreement"). Under the Agreement the petitioner agreed, inter alia, to manufacture and commission the said two machines, inclusive of maintenance, insurance, spares and consumables of the machines for 20 days. The respondent in terms of the Agreement further undertook supervision of erection, adjustment and commissioning of the machines at its own cost. The contract price was agreed at Rs.1,22,00,000.
(C) The petitioner entrusted M/s. ITL Industries Ltd. (hereinafter referred to as "ITL") to manufacture the two machines, in accordance with the specifications supplied by the claimant. During the course of manufacture of the two machines, the claimant in terms of the Agreement was entitled to inspection.
(D) Upon completion of manufacture of the two machines, the petitioner issued "inspection release note" and the claimant 'the dispatch clearance'. The two machines in terms of the Agreement were then shipped and transported by the petitioner to the End User's designated plant in Kazakhstan. In the presence of technical experts including one Mr. Arun Khanwalker on behalf of ITL, on March 9, 2004 erection and commissioning process of the two machines commenced.
(E) The End User alleged that due to diverse defects and deficiencies in the basic design, the two machines failed to attain the production
Associate Builders Vs. Delhi Development Authority
Centrotrade Minerals & Metals Inc. Vs. Hindustan Copper Ltd.
Delhi Development Authority Vs. R.S. Sharma
Hindustan Zinc Ltd. Vs. Friends Coal Carbonization
Indu Engineering & Textiles Ltd. Vs. Delhi Development Authority
K.P. Poulose Vs. State of Kerala
Oil & Natural Gas Corporation Ltd. Vs. Saw Pipes Ltd.
Oil and Natural Gas Corporation Ltd. Vs. Western Geco International Ltd.
ONGC Ltd. Vs. Garware Shipping Corporation Ltd.
P.R. Shah Shares & Stock Brothers Vs. M/s. B.H.H. Securities P Ltd.
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.