2019 Supreme(Cal) 610
IN THE HIGH COURT OF JUDICATURE AT CALCUTTA
DEBANGSU BASAK, J.
S.S. Civil Construction Pvt. Ltd. & Another - Petitioners
Versus
Government of West Bengal & Others - Respondents
W.P. No. 863 (W) of 2019 With C.A.N. 3269 of 2019
Decided On : 25-07-2019
For the Petitioners:Saptangsu Basu, Sr. Advocate, Anuj Sinha, Biswanath Chatterjee, Saheli Sen, Sobhan Kumar Pathak, Advocates.
For the Respondents:Suman Sengupta, Subir Pal, Advocates.
The acceptance of a bid within the validity period creates a binding contract, and a show cause notice must have a basis.
Headnote:
Bid Validity - Refund of Earnest Money - Sections 3 and 4 of the Contract Act, 1872 - All India Reporter 1966 SC 543 (Bhagwandas Goverdhandas Kedia v. M/s. Girdharlal Parshottamdas and Co.) and All India Reporter 2006 Bombay page 231 (Pacific Refractories Ltd. v. Stein Heurtey India Projects Pvt. Ltd.)
Fact of the Case:
The petitioner participated in an e-tender for a construction project and deposited earnest money. The petitioner sought refund of the earnest money as the bid validity period expired before the acceptance of the bid.
Finding of the Court:
The court found that the bid was accepted within the validity period, creating a binding contract between the petitioner and the respondent. The show cause notice proposing suspension of the petitioner was found to have a basis and the authorities were allowed to decide on it.
Issues: Validity of bid acceptance, refund of earnest money, and suspension of the petitioner.
Ratio Decidendi: The acceptance of the bid within the validity period created a binding contract, and the show cause notice had a basis.
Final Decision: The court disposed of the case, allowing the authorities to decide on the show cause notice and made no order as to costs.
JUDGMENT :
1. The writ petition and an application for interim relief made therein have been taken up for hearing. The writ petitioner has asked for refund of the earnest money of Rs. 39,91,535/- deposited by the writ petitioner against e-tender for construction of work of Purbabishnupur-Raidighi Road-Chainage from 0.00 KMP to 19.630 KMP strengthening work in the district of 24 Parganas (South).
2. Learned Advocate appearing for the petitioner has submitted that, the petitioner participated in the e-tender dated July 11, 2018 issued by the Public Works (Roads) Directorate. He has referred to the bid validity clause of the tender documents. He has submitted that, the bid tender clause requires the bid to remain valid for a period not less than 120 days from the date of submission of the bid. The clause proceeds to lay down that, if the bidder withdraws the bid during the period of bid validity, his earnest deposit will be forfeited. He has referred to the letter dated December 13, 2018 by which, the petitioner placed on record that, the petitioner submitted the bid on August 3, 2018. The validity period of the bid expired on November 30, 2018 on expiry of 120 days from the date of submission of the bid. Consequently, the petitioner wanted cancellation of the bid and refund of the earnest money deposit. He has submitted that, the authorities purported to accept the bid of the petitioner on December 3, 2018. Consequently, the petitioner having withdrawn the bid after the expiry of 120 days from the date of submission of the bid, the purported acceptance is invalid. He has referred to the letter dated November 26, 2018 of the authorities and has submitted that, the claim that, such acceptance of bid was posted on November 26, 2018 is belied from the document at page 80 of the writ petition. He has referred to Sections 3 and 4 of the Contract Act, 1872 and submitted that, since, the bid of the petitioners stood withdrawn subsequent to the expiry of 120 days from the date of submission of the bid, the purported acceptance of the bid is of no consequence. Therefore, the authorities cannot invoke the provisions of the bid validity clause in the tender documents to forfeit the earnest money deposit or to take any coercive measure against the petitioner. The show-cause notice dated March 20, 2019 therefore is bad. He has relied upon All India Reporter 1966 SC 543 (Bhagwandas Goverdhandas Kedia v. M/s. Girdharlal Parshottamdas and Co.) and All India Reporter 2006 Bombay page 231 (Pacific Refractories Ltd. v. Stein Heurtey India Projects Pvt. Ltd.) in support of his contentions. He has submitted that, the show-cause notice as also the purported forfeiture of the earnest money deposit should be quashed. The authority should be directed to refund the earnest money deposit forthwith.
3. Learned Advocate appearing for the State has relied upon the Bid Validity Clause and Clause A.11 relating to award of contract of the tender documents. He has referred to the conduct of the petitioner and submitted that, the bid of the petitioner was accepted within the validity period prescribed under the tender conditions.
4. Therefore, there was no bar in issuing the work order in favour of the petitioner. He has relied upon Clause 30 of the Tender Clause relating to forfeiture of earnest money. He has submitted that, Clause 30(b) of the tender documents was invoked for the purpose of forfeiting the earnest money deposit. He has referred to the show-cause notice and submitted that, the show-cause notice cannot be a subject matter of the writ petition through an interim application as such show-cause notice has no nexus with the forfeiture of the earnest money deposit. He has referred to the various pleadings made on this behalf in the affidavit-in-opposition. He has submitted that, petitioner is not entitled to any relief.
5. The Public Works (Roads) Directorate had issued a notice inviting electronic tender no. 47 of 2018-2019 dated July 11, 2018. The petition