2020 Supreme(Cal) 308
IN THE HIGH COURT OF CALCUTTA
Arindam Sinha, J.
Board Of Trustees Of The Port Of Calcutta - Appellant
Versus
Marino Dredg Co. (p) Ltd. - Respondent
AP No.26 of 2004
Decided On : 13-01-2020
Mr. Hirak Mitra, Sr. Adv. Mr. Nilay Sengupta, Adv. Ms. Swati Agarwal, Adv, for the Appellant; Mr. P.K.Das, Sr. Adv. Mr. Amitava Mukherjee, Adv. Mr. Rajesh Jana, Adv, for the Respondent
The main legal point established in the judgment is the importance of compliance with contract terms and the validity of awarded claims under the relevant legal provisions.
Headnote:
Arbitration Petition - Dredging Project - Arbitration and Conciliation Act, 1996 - Sections 34, Contract Act, Evidence Act - [Sections 34, Contract Act, Evidence Act]
Fact of the Case:
The arbitration petition is for setting aside an award related to a dredging project. The award-holder had two claims awarded, one for pending bills and the second for a refund of the security deposit. The award-debtor raised objections regarding the completion of the work and the validity of the awarded claims.
Finding of the Court:
The court found that the work had been completed, and the claims of the award-holder were valid. The court rejected the counter-claims of the award-debtor and dismissed the petition.
Issues: The issues revolved around the completion of the contract work, validity of the awarded claims, and compliance with the General Conditions of Contract.
Ratio Decidendi: The court relied on the provisions of the Contract Act, Evidence Act, and the Arbitration and Conciliation Act, 1996 to determine the validity of the awarded claims and the completion of the contract work.
Final Decision: The court dismissed the petition, upholding the validity of the awarded claims and the completion of the contract work.
JUDGMENT
Arindam Sinha, J. - This arbitration petition is for setting aside award dated 3rd November, 2003. Parties to the arbitration had entered into agreement for dredging/excavation of approach channel and basin project of shore based pilot station at Sagar Island. The agreement was pursuant to award-debtor having accepted tender of award-holder, for doing said work as to be completed and handed over in satisfactory condition. Work was to be done within 18 calendar months from date of receipt of work order. Consideration payable was provided in the agreement, which included fixed consideration and rates, for construction of fencing, protection and dredging.
2. Two claims of award-holder stood awarded, along with interest. The first claim is for pending bills and the second, for refund of security deposit. Arbitrator found work had been completed. Award-debtor had admitted receipt of bills under first claim awarded. Award-debtor, at material point of time did not raise any objection regarding those bills. The first claim was awarded on bills due, found to be in respect of work actually executed. The second claim, for refund of security deposit, was awarded on Arbitrator finding, the work had been completed. 10 % interest per annum, from 8th February, 2002 (date of first sitting of arbitration) till date of award, was allowed on aggregate award amount. Rest claims of award-holder were rejected as also counter- claims of award-debtor.
3. Mr. Mitra, learned senior advocate appeared on behalf of petitioner/award- debtor. He submitted, General Conditions of Contract is part of the contract between parties. He referred to clause 6 therein as terms for payment. All payments made prior to issue of certificate in From G.C.2 shall be treated as mere advances. Respondent/award-holder had not obtained completion certificate in Form G.C.2. He relied on Specifications with Special Conditions, General Issues clause 2.6 to submit, dredging depths were to be maintained at contractors expense, till date of completion certificate for whole of the work. Extra dredging, due to bank collapse, had to be borne by contractor. There could not have been award made on bills for work done but not completed. Quantum meruit payment is not permissible under the contract. Finding in paragraph 10.5 of impugned award that work was completed, is perverse and patently illegal. The work was not completed prior to 1st July, 2001, on and from which date admittedly contractor had suspended work. Suspension of work can only be of on going work till before completion. He relied on Treitel and Chitty on Contract to submit, where complete performance was obligation on part of contractor, there can be no recovery for partial performance. He cited an English case of Sumpter Vs. Hedges reported in (1898) 1 QB 673 , in which it was held that plaintiff could not recover from defendant, in respect of work he had done as upon a quantum meruit, on no evidence of fresh contract to pay for the same when the contract was for the whole.
4. He elaborated, the agreement made on 25th June, 1999 was pursuant to, inter alia, letter of intent dated 16th June, 1999. With reference to clauses 5.12 and 6.1 in General Conditions, he emphasised, scope of the contract required contractor to obtain certification by Forms G.C.1 and G.C.2. The forms have been disclosed at pages 183 and 184 in the petition. He also drew attention to the correspondence, disclosed between pages 258 to 269 in the petition, culminating in his client having terminated the contract. He pointed out, admitted position is, there was no application made to the engineer for issuance of certificates, even by Form G.C.1.
5. He relied on judgment of Supreme Court in ONGC Ltd. v. Saw Pipes Ltd. reported in (2003) 5 SCC 705. He submitted, this decision is the authority for deciding the challenge as it was rendered prior to amendment made in year 2015 to Arbitration and Conciliation Act, 1996. The judgment declared, it is settled