IN THE HIGH COURT OF CALCUTTA
Moushumi Bhattacharya, J.
Radhey Shyam Pandey - Appellant
Versus
Union Of India And Others - Respondent
WPA 10668 of 2021
Decided On : 06-04-2022
termination - Lease Agreement - Clause 23.2, Article 226(2) of The Constitution of India, Om Prakash Srivastava vs Union of India; (2006) 6 SCC 207, Uttar Pradesh Power Transmission Corporation Limited vs CG Power And Industrial Solutions Limited; (2021) 6 SCC 15, Oil and Natural Gas Commission vs Utpal Kumar Basu; (1994) 4 SCC 711, M/s. Erustan Equipment & Chemicals Ltd. vs State of West Bengal; (1975) 1 SCC 70
Fact of the Case:
The petitioner seeks withdrawal of a termination letter and refund of security deposit from the Railways. The Railways terminated the Lease Agreement and forfeited the security deposit, citing breach of agreement by the petitioner.
Finding of the Court:
The impugned termination letter was found to be in violation of the contractual terms and the petitioner's right to a fair hearing. The court allowed the petition and restrained the Railways from giving further effect to the termination letter.
Issues: Jurisdiction of the Court, Alternative remedy in the form of arbitration, Breach of contractual terms, Blacklisting without fair hearing
Ratio Decidendi: The court held that the termination letter violated the contractual terms and the petitioner's right to a fair hearing. It also emphasized the petitioner's right to approach the Writ Court despite the presence of an arbitration clause.
Final Decision: The impugned termination letter was revoked and set aside. The respondent Railways was restrained from giving any further effect to the termination letter.
JUDGMENT
Moushumi Bhattacharya, J. - The petitioner seeks a direction on the North Eastern Railway to withdraw a letter of termination dated 31st March, 2021 issued by the Senior Divisional Commercial Manager, being the respondent no. 4 herein. By the said impugned communication, the petitioner's security deposit of Rs.23,02,661/- was forfeited and the petitioner was restrained from taking part in the tender of the North Eastern Railway for the next two years. The impugned letter referred to Scenario-3 of a letter dated 3rd December, 2020 which provides for termination of the contract between the Railways and the Leaseholder (petitioner).
2. The petitioner emerged as the successful bidder for a tender for lease of 23 tonnes parcel space and a Lease Agreement was executed between the petitioner and the Railways for a period from 17th January, 2020 to 16th January, 2025. The operation of the trains was suspended by the Railways by reason of the Covid-19 pandemic. The petitioner thereafter declined to accept the offer of the Railways for a substitute train for limited operation. The petitioner invoked clause 23.1 of the Lease Agreement by a letter dated 6th February, 2021 with 60 days prior notice and the Railways issued the impugned communication of 31st March, 2021 under clause 23.2 of the Lease Agreement and terminated the contract.
3. According to learned counsel appearing for the petitioner, the petitioner's right to terminate the contract emanates from clause 23.1 of the Lease Agreement and the Railway Board Circular dated 3rd December, 2020 (Scenario-2 of the Circular). The petitioner sought refund of the security deposit under the said clause. The Railways however, without taking into account the petitioner's invocation, issued the impugned communication by applying Scenario-3 of the Circular and forfeited the security deposit of the petitioner. Counsel submits that the petitioner was blacklisted for two years without there being any provision for such under the relevant Agreement. It is submitted that the Lease Agreement pertained to a specific train i.e. Train No.13020/13019. It is also submitted that the petitioner is entitled to freight adjustment in the event of suspension of service and that the Railways are under a statutory obligation for guaranteed supply of Lease Space. Counsel submits that the petitioner has a right to approach the Writ Court and that the alternative remedy in the form of recourse to arbitration would not apply in the present case.
4. Learned counsel appearing for the respondent Railways submits that the facts of the present case do not give rise to a cause of action which would confer jurisdiction on this Court and that this Court should not interfere in the case of a determinable contract. Counsel relies on the clauses in the Agreement which entitle the respondent to forfeit the security deposit and that the contract was liable to be terminated since the petitioner (Leaseholder) failed to operate the contract continuously for 10 days without giving any notice. Counsel places emphasis on clause 23.2 of the Agreement under which the North Eastern Railway has right to terminate the contract as a punitive measure without giving any notice for breach of agreement. Counsel urges that the Railways suffered huge monetary loss by reason of the petitioner failing to start the work as would be evident from letters exchanged between the parties. It is also submitted that the Agreement contains an arbitration clause and the petitioner has an alternative remedy available to invoke.
5. Since a point of maintainability has been raised by the respondent Railways, this point is being dealt with first. The impugned letter of termination dated 31st March, 2021 was received by the petitioner in Howrah, within the jurisdiction of this Court. The entire cause of action of the writ petitioner arises from this letter of termination. The impugned letter not only terminated the Lease Agreement but also debarred the petition
Om Prakash Srivastava vs. Union of India; (2006) 6 SCC 207
Whirlpool Corpn v Registrar of Trade Marks; (1998) 8 SCC 1
Oil and Natural Gas Commission vs. Utpal Kumar Basu; (1994) 4 SCC 711
Assistant Excise Commissioner vs. Issac Peter; (1994) 4 SCC 104
Datar Switchgears Ltd. vs. Tata Finance Ltd.; (2000) 8 SCC 151
Harbanslal Sahnia vs. Indian Oil Corpn. Ltd.; (2003) 2 SCC 107
Jagdish Mandal vs. State of Orissa; (2007) 14 SCC 517
Kerala State Electricity Board vs. Kurien E. Kalathil; (2000) 6 SCC 293
M/s. Erustan Equipment & Chemicals Ltd. vs. State of West Bengal; (1975) 1 SCC 70
National Agricultural Coop. Marketing Federation India Ltd. vs. Gains Trading Ltd.; (2007) 5 SCC 692
The court emphasized the importance of fair play and the right to a fair hearing before imposing penal consequences or termination of a contract.
The court established that contractual termination and debarment must comply with the specific terms of the agreement and adhere to principles of natural justice.
The court established that termination of a lease contract without proper notice violates principles of natural justice and contractual obligations.
Contractual termination notice must be issued by the authorized Railway Administration, adhering to principles of natural justice.
Disputes arising from contract termination must be resolved through arbitration, not writ jurisdiction, especially when complicated questions of fact are present.
The necessity for compliance with contractual provisions regarding termination, specifically the requirement for notice and written reasons, is essential for the validity of such actions.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.