SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Chh) 563

IN THE HIGH COURT OF CHHATTISGARH AT BILASPUR
ARUP KUMAR GOSWAMI, SANJAY AGRAWAL, JJ.
Shamsher Singh S/o Vidhyanchal Singh – Petitioner
Versus
General Manager Bhatgaon, South Eastern Coalfields Limited – Respondent
W.P. (C) No. 1012 of 2022
Decided On : 01-12-2022

Advocates:
Advocate Appeared:
For the Petitioner: Abhishek Banjare.
For the Respondent: Sudeep Agrawal.

Headnote:

Constitution of India, 1950 - Article 226 - Tender - Debarring him from work – Order of blacklisting - Hon’ble Court may kindly be pleased to direct concerned respondents to cancel letter of debarring him from work – Held, In Gorkha Security Services vs. Government (NCT of Delhi) and Others, Hon’ble Supreme Court has laid down that necessity of compliance with principles of natural justice by giving opportunity to person against whom action of blacklisting is sought to be taken has a valid and solid rationale behind it - With blacklisting many civil and/or evil consequences follow - No notice was issued before black-listing petitioner and therefore, order so far as black-listing of petitioner is concerned is interfered with - However, liberty is reserved for respondent to take steps if so advised in accordance with law with regard to black-listing of petitioner – Court is of opinion that present is not a case where this Court ought to exercise jurisdiction under Article 226 of Constitution of India to issue any such direction, as prayed for - Writ petition is partly allowed.

ORDER :

1. Heard Mr. Abhishek Banjare, learned counsel for the petitioner. Also heard Dr. Sudeep Agrawal, learned counsel, appearing for the respondent.

2. Pursuant to a Notice Inviting Tender (NIT) dated 24.08.2021 issued by the respondent for work of temporary patch repairing work at coal transportation road near Songara of Mahan sub area of Bhatgaon area, the petitioner was awarded the work for a total value of Rs. 10,19,520/- by an order dated 24.09.2021.

3. The order dated 24.09.2021 clearly stated that the petitioner should commence work within a period of ten days of issuance of the letter or handing over of the site, which ever is earlier and period of completion of work shall be fifteen days. The site for project was handed over to the petitioner on 01.10.2021 and therefore, the date of completion was to be 15.10.2021.

4. On 23.11.2021, the Staff Officer (Civil) Bhatgaon Area of the respondent issued a letter to the petitioner stating that the petitioner had neither started the work nor had submitted the work programme despite several requests being made in that regard. It was observed that the petitioner was not interested to take up the work and blocked important work. Accordingly, invoking Clause 6.1 of the General Terms and Conditions of the NIT, which is not enclosed by the petitioner in this petition, it was recorded as follows:

“If the contractor, without reasonable cause or valid reasons, commits defaults in commencing the work withing the aforesaid time limit, the company shall, without prejudice to any other right or remedy, be at liberty, by giving 15 day’s notice in writing to the contractor to commence the work, falling which to rescind the Letter of Acceptance of Tender/Work Order. The bidders will be banned for 02(two) years for being eligible to submit bids in CIL and its subsidiaries with the approval of Tender Acceptance Authority with intimation to all concerned and online blocking of bidder shall be done on receipt of written communication from the Tender inviting Authority by application admin of CIL e-Procurement Portal.

In light of the above department has no option other than to serve you 15 day’s notice in reference to above. This may be treated as final 15 day’s notice.”

5. In the letter dated 25.11.2022, the petitioner indicated certain difficulties faced by him but there is no denial of the fact that he had not given the work programme as alleged in the letter dated 23.11.2021. Subsequently, by an order dated 29.01.2022, the following action was taken:

“(i) Cancellation of your bid against NIT No. GM/BHAT/CVL/eTENDER/21-22/32 dated 24.08.2021 and to rescind the letter of acceptance of tender/Work Order.

(ii) Debarring from participation in Re-tender for the above work.

(iii) Forfeiture of EMD of Rs. 30,586.00 deposited by you for this work.

(iv) Debarring from participating in all future tenders of SECL, Bhatgaon Area for a period of 24 (Month) from the date of issue of this letter.”

6. By filing this petition, the petitioner prays for the following reliefs:

“10(i) That this Hon’ble Court may kindly be pleased to direct the concerned respondents to cancel the letter of debarring him from work.

10(ii) That this Hon’ble Court may kindly be pleased to direct the concerned respondents to allow the petitioner to complete his work as per work order.

10(iii) Any appropriate direction or order in favour of petitioner, which this Hon’ble Court deems fit in the circumstances of the case.”

7. The learned counsel for the petitioner submits that the petitioner is very much interested to do the work and therefore, a direction may be issued to the respondent to allow the petitioner to do the work which was started by him. It is further submitted that black-listing of the petitioner without issuing a show-cause notice is bad in law and therefore, the order of black-listing is liable to be set-aside.

8. Dr. Agrawal submits that the petitioner has not made any prayer for cancellation of the bid of the petitioner and rescindi

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top