IN THE HIGH COURT OF CHHATTISGARH AT BILASPUR
GOUTAM BHADURI, SANJAY S. AGRAWAL, JJ.
South Eastern Coalfields Limited - Appellant
Versus
M/s S. Kumar Associates Through Its Power Of Attorney Holder Rajendra Rajput – Respondent
FA No.267 of 2016
Decided on : 08-11-2023
Court Fee Refund - Civil Procedure - Section 96 of CPC - Explanation to Order 41 Rule 22 of CPC
Fact of the Case:
The plaintiff, a proprietorship firm, was awarded a contract work by the defendants-SECL. The plaintiff claimed that the defendants-SECL failed to provide the necessary land for the work, leading to non-performance of the contract. The plaintiff sought a total sum of Rs.14,52,761/- along with interest.
Finding of the Court:
The trial Court decreed the plaintiff’s claim in part, entitling him to a total sum of Rs.14,52,761/- payable by the defendants-SECL within a period of two months from the date of pronouncement of the judgment.
Issues: The main issue was whether the finding of the Court decreeing the plaintiff’s claim in part, despite holding that the plaintiff failed to establish the fact that on account of non-compliance of the terms and conditions of the alleged agreement by the defendants-SECL, he failed to complete the alleged contract work within the period provided therein, is perverse.
Ratio Decidendi: The Court found that the plaintiff failed to establish that the non-provision of land by the defendants-SECL led to the non-performance of the contract work. The Court also noted that the plaintiff stopped the alleged contract work without valid reasons and failed to complete the work within the stipulated time. However, as the defendants-SECL did not exercise its power for termination or imposition of penalty as provided under the agreement, the plaintiff was entitled to the amount for the work done by him.
Final Decision: The appeal and cross-appeal were dismissed, and the plaintiff was entitled to the total sum of Rs.14,52,761/- payable by the defendants-SECL within a period of two months from the date of pronouncement of the judgment. The plaintiff was also entitled to a court fee refund of Rs.1,02,400/- paid inadvertently on the cross-objection/appeal under Order 41 Rule 22 of CPC.
JUDGMENT :
Sanjay S. Agrawal, J.
1. This appeal has been preferred by the defendants-South Eastern Coalfields Limited (hereinafter referred to as “SECL”) under Section 96 of the Code of Civil Procedure, 1908, (hereinafter referred to as 'CPC') questioning the legality and propriety of the judgment and decree dated 05.05.2016 passed by Third Additional District Judge, Surguja at Ambikapur in Civil Suit No.21-B/2012, whereby the learned trial Court has decreed the plaintiff’s claim in part entitling him to a total sum of Rs.14,52,761/- payable by the defendants-SECL within a period of two months from the date of pronouncement of the judgment, while the cross appeal has been preferred by the plaintiff under Order 41 Rule 22 of CPC against the findings recorded in relation to issues No.1-a & 1-b.
2. Briefly stated the facts of the case are that the plaintiff, a proprietorship firm engaged in the business of contractorship carrying out work for various government, semi-government and public sector undertaking, was awarded the work of “hiring of HEMM for excavating (including drilling in all kinds of Strata/overburden) loading into tippers, transportation and unloading the excavated material and slit; dumping, dozing and scraping (removal of bands, preparation) maintenance of haul road, water sprinkling and spreading of materials at the site shown and as per the directives of the Management/Engineer-in-chief at Amera OC project with minimum 1,01,290 cubic meter per month.” The said contract work was allotted to the plaintiff in pursuance to the tender/NIT floated by the defendants-SECL on 11.03.2008, where the plaintiff was declared the successful bidder and work order was issued to him on 20.01.2009 and, an agreement was executed on 10.02.2009 and the plaintiff was to carry out the said work as per the terms and conditions stipulated therein.
3. According to the plaintiff, the defendants-SECL was to provide the land for carrying out the alleged contract work along with the layout, but, since the defendants-SECL has failed to provide the land for the said purpose, therefore, he failed to perform his part of the contract. It is pleaded further that owing to non-performance of the terms and conditions of the alleged agreement by the defendants-SECL, the alleged contract work becomes unworkable and request was, therefore, made for its repudiation vide letter dated 01.06.2009 while raising the final bills amounting to Rs.20,42,704/- and since the bank guarantee furnished by him of Rs.5,89,943/- was never renewed, therefore, after adjusting the same, (Rs.20,42,704-Rs.5,89,943), the plaintiff has claimed total sum of Rs.14,52,761/- along with the interest at the rate of 24% per annum from the date of institution of the suit till its realization.
4. While contesting the aforesaid claim, it was pleaded by the defendants-SECL that despite being made available the necessary layout, the plaintiff has failed to perform the work in time as per the terms and conditions stipulated in the alleged agreement dated 10.02.2009 as he failed to make out requisite arrangements of machines for doing the alleged contract work in time which was the essential term of the alleged agreement. It is contended further that a hindrance register was made for the purposes of recording all kinds of obstruction in pursuing the said contract work in which the representatives of both plaintiff and the defendants-SECL have put their signatures and in the said register, a complaint pertaining to the deficiency in providing the land was neither made by the plaintiff nor was it a serious dispute exists between the parties. It is, therefore, contended that it was not the reasons for which the plaintiff has failed to perform his work in time. It is contended further that since the plaintiff has failed to complete the alleged contract work in time, therefore, he is not entitled to obtain the amount as mentioned in his three running bills i.e. 13.02.2009, 03.03.2009 and 31.03.2009 an
Babulal Agrawal vs. Jyoti Shrivastava and others
In Re: Chidambaram Chettiar”, reported in AIR 1934 Mad 566
AI
The Court clarified the provisions of Section 96 of CPC and the Explanation to Order 41 Rule 22 of CPC, emphasizing the right of the respondent to file a cross-objection against any finding recorded ....
The lack of privity of contract and failure to establish a cause of action were central to the court's decision.
In works contracts, the party maintaining measurement records bears the burden to prove the quantity of work performed. Absent such evidence, the contractor's claim for work done must be upheld. Post....
The court affirmed that a contractor's claims for delays caused by defendants were valid, and it has the discretion to adjust interest rates based on economic conditions.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.