SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1997 Supreme(Del) 643

High Court Of Delhi
CDS GUJRAL - Appellant
Versus
DELHI DEVELOPMENT AUTHORITY - Respondent
Suit 184 of 1994
Decided On : 08/07/1997

Advocates Appeared:
A.SALVAN, ASHOK CHHAPARIA, R.L.PAL

Headnote:Arbitration Act 1940 - Sections 14,17 & 29 r/w Section 3 of Interest Act — Rule of the court — Award made by the arbitrator — Objections of respondent — Escalation of labour charges — Awarding of pre-suit interest — Rejection of counter-claim — Rate of pre-suit interest modified from 18% to 12% — No jurisdiction to adjudicate counter-claim — No merits in objections — Dismissed — Made rule of court.

       Held:

       With regard to award of interest at the rate of 18%p.a., there cannot be any dispute with regard to award of pendente lite and future interest which the Arbitrator has awarded. Ms. Salwan has raised serious dispute with regard to award of interest from 10.4.1986 till 10.4.1987 @ 18% p.a. on the ground that grant of interest at 18%p.a. is too exorbitant and cannot be granted by the Arbitrator in terms of Section 2(b) of the Interest Act. Ms. Salwan says that the normal interest which can be accrued on a deposit of nationalised bank would not be more than 12%. There is some force in the argument of learned counsel for the respondent. As award of pre-suit interest @ 18% p.a. is on higher side, I modify the award under this head to the extent that interest from 10.4.1996 till 10.4.1987 shall be calculated at the rate of 12% p.a.

Vijender Jain, J. (Oral)

( 1 ) THE petitioner filed the petition under Sections 14, 17 and 29 of the Arbitration Act read with Section 3 of the Interest Act for making the award rule of the Court. Award was made by the Arbitrator, Mr. A P Paracer, Additional Director General (Retd.) C. P. W. D. on 23. 12. 1993. The respondent filed their objections against the award under Section 30 of the Arbitration Act. The Arbitrator entered the reference on 10. 4. 1987.

( 2 ) LEARNED counsel for the respondent, Ms. Ansuya Salwan, has challenged the whole award. The main thrust of the argument of the learned counsel for the respondent, is to Claim No. 3 under the award. Ms. Salwan says that award of a sum of Rs. 1,12,185. 40 paise to the petitioner-claimant on account of extra expenditure incurred towards rise in wages of labour for the quantum of work after the expiry of stipulated contract period was erroneous. She has contended that Arbitrator has completely ignored that under the provisions of the contract entered into between the parties, there was a provision for escalation in labour wages under Clause-10 (c) of the contract and the said increase was payable only if there was no delay attributable on the part of the claimant-petitioner. She has also contended that the Arbitrator had no material before him to come to a conclusion that the labour element for execution of such work was 20%. She has also contended that when penalty had been imposed on the claimant in terms of Clause-2, Arbitrator had no jurisdiction to grant the award under Claim No. 3. In support of her arguments, she has cited Bharat Furnishing Co. vs. DDA and anr. 1992 (1) Arb. L. R. 327, R S Rana Vs. DDA and anr. 1993 (2) Arb. L. R. 165 and Sudhir Brothers Vs. DDA 1995 (2) Arb. L. R. 437. Another challenge by learned counsel for the respondent is to Claim Nos. 5 and 6. She has contended that on one hand, the Arbitrator has awarded under Claim No. 3 for additional expenses towards escalation of cost of labour and still under Claim No. 5, i. e. rise in price of bricks and under the head Claim No. 6, i. e. rise in wages because of statutory notification, Arbitrator has awarded a sum of Rs. 25,000/= in favour of claimant thereby awarding increase in labour twice and on this score Arbitrator has misconducted the proceedings and, therefore, the award be set aside.

( 3 ) YET another objection, which has been raised by the learned counsel for the respondent, is with regard to the award of interest under Claim No. 12. Ms. Salwan has contended that as per Section 2 (b) of the Interest Act pre-suit interest at the rate of 18% is not permissible. She has further contended that this is not the rate on which interest is payable by the nationalised bank. She has also contended that the Arbitrator was appointed on 30. 3. 1987, he entered into reference on 10. 4. 1987 and the grant of interest at the rate of 18% from 10. 4. 1986 till 10. 4. 1987 is unwarranted in law, that being too exorbitant.

( 4 ) ANOTHER argument raised by the learned counsel for the respondent is with regard to rejection of counter-claim No. 2. However, at the time of addressing arguments, the learned counsel for the respondent was candid enough to point out that the judgment of this Court reported in DDA Vs. M/s Sudhir Brothers 1995 (2) Arb. L. R. 307 delivered by a Division Bench held that the Arbitrator acted without jurisdiction in going into the said question and that was not within the power of the Arbitrator. However, she wants this Court to hold that if respondent-DDA is to recover the amount on account of counter Claim No. 2, this Court may grant her liberty to do so and condone the delay, if any, in initiating the appropriate proceedings for recovery.

( 5 ) ON the other hand, Mr. Rajesh Lakhanpal, learned counsel appearing for the petitioner, has contended that the award is well-reasoned award. The Arbitrator was a former Additional Director General (Retd.) C. P. W. D. and was well-versed and experience









Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top